| Miscellaneous Information / Notes |
| 499 EVERNIA ST - CONSTRUCTION OF 8 STORY 315 UNIT |
| APARTMENT MID RISE & 8 STORY PARKING GARAGE |
| |
| |
| |
| 12/13/18 SCOTT P/U CERTIFICATE OF OCCUPANCY |
| SPALMER |
| 12/10/2018 ADDRESS WAS REVISED BY S. HILL, EMAILED |
| SCOTT ARCHER UPDATED CERTIFICATE OF OCCUPANCY AND |
| PLACED AT FRONT COUNTER, FILED UNDER A WITH COPY |
| SENT TO SCANNING. MM |
| 12/05/2018 CERTIFICATE OF OCCUPANCY PRINTED AND |
| PLACED AT FRONT COUNTER, FILED UNDER "A" WITH COPY |
| SENT TO SCANNING. MM |
| 11/15/18 COMPLETED AIPP REQUIREMENT PER S.WELTER; |
| OK TO REALEASE CO RES |
| 10/17/18 SCOTT P/U TCO SPALMER |
| 10/17/18 TCO PHASE 3 BEHIND COUNTER REG |
| 10/10/18 CCO IN BOX BEHIND COUNTER NEEDS TO BE |
| PAID |
| REG |
| 10/10/18 REQUEST TO EXTEND TCO ROUTED TO RICHARD |
| GATHRIGHT SPALMER |
| 9/4/18 SCOTT P/U TCO SPALMER |
| 8/31/18 PHASE II ADDED TO THE TCO REG |
| 8/24/18 REQUEST FOR TCO ROUTED TO RICHARD |
| GATHRIGHT & SCANNED TO THIS PERMIT SPALMER |
| 7/18/18 SCOTT P/U TCO SPALMER |
| 7/17/18 TCO FOR PHASE I ISSUED EMAILED SCOTT TO |
| P/U TCO. IN CO BOX UNDER "A". RB |
| 6/21/18 SPOKE TO SCOTT ARCHER RE:PHASED TCO |
| PROCESS. SAK |
| 06/21/18 REQUEST FOR TCO ROUTED TO STEVEN KENNEDY |
| & SCANNED TO THIS PERMIT SPALMER |
| 10/28/16 PLAN REVIEW COMPLETE, APPLICANT INVITED |
| TO DOWNALOAD PLANS. CP |
| 10/28/16 PERMIT PICKED UP BY ROBERT GD |
| 10/25/16 IMPACT FEE REVIEW OK, DOCUMENTS NOT |
| NEEDED (TWO SETS OF PLANS, EXTRA COPY OF RECEIPTS) |
| AT FRONT COUNTER PENDING PICKUP, NO FEES DUE, |
| FILED LARGE BIN "A" SH |
| 10/25/16 RESUB BRINGING PLANS BACK FROM IMPACT |
| FEES GD |
| 10/18/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 9/28/16 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 8/10/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/1/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 6/16/16 2ND REVIEW PLUMB AND GAS DENIED/ GPJ |
| 5/25/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 5/11/16 RESUBMIT REMINDER SENT. CP |
| 4/11/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 03/31/2016 ENG F FWD TO OUTGOING |
| 3/1/16 EMAILED THRESHOLD DOCS TO |
| [email protected] SH |
| 2/8/16 PLANS UPLOADED, INCOMING COMPLETE. LEM |
| 2/5/16 APPLICANT INVITED TO UPLOAD PLANS. LEM |
| 2/5/16 REQUEST FOR DIGITAL GIVEN TO CAROLINE PUELL |
| SPALMER |