| Miscellaneous Information / Notes |
| NEW BRISTOL CONDO COMPLETE BASE BUILDING, SEPERATE |
| PERMITS FOR UNITS: 904,1201,1503,1504,1801,2002, |
| 2101,2102,2103,2201,2202,2203,2301,2302,2401,2501, |
| 2502 |
| |
| |
| |
| FOUNDATION: 15050292/ 2010 FBC-B |
| |
| |
| 07/27/2020 AIPP REQUIREMENTS ARE MET PER EMAIL IN |
| NOTES REG |
| 03/31/20 TCO EXTENDED TO AUGUST 28,2020 REG |
| 01/22/20 ARRON PICKED UP TCO DOCUMENT REG |
| (PG) SEE "ATTACHMENTS" FOR ALL DOCUMENTS |
| PERTAINING TO CBAA JAN 16, 2020 - - - - - - - > > |
| > > > > |
| 01/16/20 CCO EXTENDED BY CBAA TO APRIL 30,2020 REG |
| 12/23/19 PHASE XII CCO ISSUED REG |
| 12/19/19 PHASE XI CCO ISSUED REG |
| 12/09/19 PHASE X CCO ISSUED REG |
| 11/15/2019 PHASE IX CCO ISSUED REG |
| 11/06/2019 PHASE VIII CCO ISSUED REG |
| 10/15/2019 PHASE VII CCO ISSUED REG |
| 9/20/2019 CCO EXTENDED TO 12/24/2019 ORIGINAL |
| BEHIND FRONT COUNTER REG |
| 9/20/19 REQUEST TO EXTEND TCO ROUTED TO RICHARD |
| GATHRIGHT AND SCANNED TO THIS PERMIT SPALMER |
| 8/23/2019 PHASE VI CCO ISSUED REG |
| 8/14/2019 PHASE V CCO ISSUED REG |
| 8/05/2019 PHASE IV CCO ISSUED REG |
| 7/18/2019 PHASE III CCO ISSUED REG |
| 7/08/2019 PHASE II CCO ISSUED REG |
| 6/24/2019 PHASE 1 CCO ISSUED EMAILED TO OWNERS AND |
| SUFFOLK, ORIGINAL BEHIND FRONT COUNTER UNDER "S"- |
| REG |
| 6/18/2019 TCO FOR INTERIOR DESIGNERS ONLY ISSUED |
| REG |
| 5/17/19 REQUEST FOR TCO TO RGATHRIGHT |
| 8/6/18 CERTIFICATE FOR TEMP CONSTRUCTION OFFICES |
| P1, AND 5A GRANTED FOR 6MONTHS REG |
| 7/3/18 MARGIT P/U STOCKING CERTIFICATE SPALMER |
| 7/3/18 STOCKING CERTIFICATE FOR CONSTRUCTION |
| OFFICE LEVEL P1 OK- REG |
| 6/22/18 REQUEST FOR STOCKING CERTIFICATE ROUTED TO |
| ROBERT BROWN & SCANNED TO THIS PERMIT SPALMER |
| 01/08/2017 SEE NOTES FOR STOP WORK ORDERS |
| 2/10/17 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO PICK UP PERMIT CARD. LEM |
| 2/10/17 PER DHARVEY/RBROWN, OK TO ISSUE PERMIT |
| WITHOUT ORIGINAL APPLICATION, COPY BEING SENT TO |
| SCANNING. LEM |
| 2/08/2017 FIRE ALARM, FIRE PROTECTION SPRINKLERS |
| AND |
| LOW VOLTAGE INCLUDED IN THE BASE PERMIT FEE, SEE |
| ATTACHMENT, $80.00 SUB-PERMIT. JW |
| |
| 2/08/2017 VALUE REDUCED BY $3,100,000.00 |
| FOUNDATION PERMIT VALUE. JW |
| 2/3/17 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 2/1/17 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 1/24/17 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 1/11/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/23/16 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 11/23/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 11/23/16 WAITING FOR CORRECTED PLANS TO BE |
| EMAILED. LEM |
| 11/21/16 RESUBMIT REMINDER SENT. LEM |
| 10/20/16 APPLICANT INVITED TO RESUBMIT. CP |
| 8/24/16 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 7/26/16 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 6/20/16 RESUMBIT REMINDER SENT. CP |
| 5/16/16 RESUBMIT REMINDER SENT. LEM |
| 4/13/16 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 1/7/16 FEES PAID, INCOMING COMPLETE. LEM |
| 12/4/15 PLANS UPLOADED, WAITING ON FEES. CP |
| 11/25/15 APPLICANT INVITED TO UPLOAD PLANS & PAY |
| FEES. CP |
| |
| |
| |
| |
| |
| |