| Miscellaneous Information / Notes |
| FOUNDATION & STEEL SUPERSTRUCTURE FOR 52,300SF |
| RETAIL FURNITURE GALLERY (EXCLUDES ROOF STRUCTURE |
| AND ROOF COVERING) |
| |
| |
| 10/4/17 CLOSED, SEE 15091225. SAK |
| 10/06/2015 PERMIT P/U BY KYLE, MS |
| |
| 10/1/15 THRESHOLD AGREEMENT OK, CALLED CONTR, 1 |
| SET ROUTED TO RECORDS, 2 CONTRACTOR SETS AT FRONT |
| COUNTER LARGE 'T' (THE WHITING TURNER) SH |
| 9/29/15 PLANS IN FILENET. LEM |
| 9/29/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEED TO COME INTO CITY HALL TO PAY |
| FEES AND PICK UP PERMIT CARD. LEM |
| 9/28/15 EXCLUDES ROOF STRUCTURE AND ROOF COVERING |
| PER EMAIL FROM ARCHITECT, REVISED PERMIT |
| DESCIPTION AND SENT EMAIL TO RECORDS; THRESHOLD |
| DOCS OK'D BY KC, OUR COPY ROUTED TO RECORDS SH |
| 9/22/15 IMPACT FEE SUBMITTAL OK, ROUTED TO RECORDS |
| SH |
| 9/17/15 PLANS UPLOADED, INCOMING COMPLETE. LEM |
| 9/15/15 CUSTOMER SUBMITTED THRESHOLD PLANS ROUTED |
| TO SAMANTHA. LWL |
| 9-9-15 ROUTED IMPACT FEE RECEIPT/PLANS TO C PUELL |
| WL |
| 9/8/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 08/11/15 EXPEDITED FORM ROUTED TO CAROLINE ASM |
| 08/11/15 THRESHOLD PLAN ROUTED TO SAMANTHA ASM |
| 8/10/15 EXPEDITE REVIEW REQUESTED. LEM |
| 8/7/15 PLANS UPLOADED, INCOMING COMPLETE. LEM |