| Miscellaneous Information / Notes |
| SHELL - NEW CONST OF A SHELL ONLY PERMIT FOR |
| 5 STORY TO INCLUDE FOUNDATIONS STRUCTURAL |
| CONCRETE. |
| THE REMAINDER OF THE 20 STORY BUILDING IS COVERED |
| UNDER PERMIT 15031312. NO CERTIFICATE OF OCCUPANCY |
| OR CERTIFICATE OF COMPLETION TO BE ISSUED TO THIS |
| PERMIT. |
| |
| |
| |
| |
| STOCKING PERMIT GRANTED 8/14/17 REG |
| 8/14/17 FEE ADDED REG |
| 8/10/17 REQUEST FOR STOCKING PERMIT ROUTED TO |
| RICHARD GATHRIGHT & SCANNED TO THIS PERMIT SPALMER |
| 08/23/16 RECEIVED AND REVIEWED "DRY-IN" PLAN.KC |
| 08/31/2015 JAMES P/U PERMIT CARD NSD |
| 8/27/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS & PICK UP PERMIT CARD. CP |
| 8/27/15 PEDDS GIVEN TO SKENNEDY. CP |
| 08/27/15 PEDDS AND ORIGINAL PERMIT APP SUBMITTED |
| AND ROUTED TO CAROLINE/LAURA ASM |
| 8/24/15 PEDDS & ORIG APPLICATION FORM REQUIRED |
| BEFORE PERMIT CAN BE ISSUED. CP |
| 08/19/15 IMPACT FEES SUBMITTED AND ROUTED TO JIM |
| WITMER ASM |
| 8/18/15 GIVEN TO SKENNEDY. CP |
| 08/18/15 PEDDS SUNMIITED ROUTED TO CAROLINE ASM |
| 8/4/15 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| SUBMIT IMPACT FEES, PEDDS & FEES. CP |
| 7/14/15 - PASSED ELECTRICAL REVIEW. NOTIFIED LEM. |
| MA |
| 7/1/15 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 6/16/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 6/15/15- MECH DENIED/FIRE LINE SUBMITTAL DOCUMENTS |
| REQUIRED/CC |
| 6/2/15 - FAILED ELECTRICAL REVIEW AS NOTED. MA |
| 4/14/15 FEES PAID, INCOMING COMPLETE. LEM |
| 4/7/15 PLANS UPLOADED WAITING ON FEES. CP |
| 3/18/15 APPLICANT INVITED TO UPLOAD PLANS, PAY |
| FEES, AND EMAILED ART IN PUBLIC PLACES FORM. LEM |