| Miscellaneous Information / Notes |
| NEW SINGLE FAMILY RESIDENCE- SFHA, A5 FLOOD ZONE, |
| |
| |
| |
| |
| |
| 12/08/17 LARRY PICED UP C/O. SAK |
| 10/19/15 PERMIT P/U BY LAWRENCE, MS |
| 10/15/15 CALLED/NEEDS NOC/OUT FRONT, LARGE PLANS |
| UNDER 'T' RM |
| 10/14/15 PLANS RETURNED FROM PAYING IMPACT FEES |
| SPALMER |
| 10/9/15 ONE (1) SET OF PLANS SIGNED OUT FOR IMPACT |
| FEES BY LAWRENCE. LWL |
| 10/7/15 PASSED ALL REVIEWS. CONTRACTOR NOTIFIED |
| VIA EMAIL. SENT TO LARGE READY BIN "T". MA |
| 10/5/15 SENT TO TIM LARGE FOR PLUMBING REVIEW. RM |
| 9/24/15 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SPALMER |
| 9/24/15 NEW APPLICATION & NEW CONTRACTOR RECEIVED |
| SO PROJECT MAY CONTINUE PER DOUG HARVEY SPALMER |
| 9/22/15 DO NOT ISSUE. DO NOT PROCESS. DO NOT |
| ACCEPT CHANGES. RJ MELE CAME INTO THE OFFICE ON |
| SEPT 22, 2015, 4 PM. DEMANDED THEY BE REMOVED FROM |
| THIS PERMIT AND THEY WERE NOT SUPPOSED TO BE ON |
| THE PERMIT. APPARENTLY THEY WERE PUT BACK ON |
| AUGUST 30 OR 31 WHEN A REVISION THEY KNEW NOTHING |
| ABOUT WAS BROUGHT IN. THEY ARE NOT ASSOCIATED WITH |
| THIS PERMIT AND DO NOT WANT TO BE ASSOCIATED WITH |
| THIS PERMIT. |
| 9/15/15 - FAILED ELECTRICAL REVIEW AS NOTED. |
| CONTRACTOR NOTIFIED VIA EMAIL. SENT TO LARGE |
| DENIED BIN "R". MA |
| 9/15/15 TO MALBARRAN DESK FOR ELECTRICAL REVIEW. |
| RM |
| 9/14/15 TO RMCDOUGA DESK. SAK |
| 8/11/15 CONTRACTOR CALLED TO RE-CONFIRM COMPANY |
| AND LICENSE WAS REMOVED FROM PERMIT NOT TO CANCEL |
| AND CLOSE PERMIT.SPOKE W/ FRAN REGARDING SITUATION |
| AND STATED SHE WANTS REMOVED CONTRACTOR FROM |
| PERMIT TO TBD I FORWARDED INFO TO SANDY AND KEN, |
| MS |
| 8/10/15 RECEIVED NOTICE TO CANCEL BY CONTRACTOR, |
| ROUTED TO KEN CONRAD. LWL |
| 7/23/15 ZONING APPROVED SG. |
| 7/6/15 PLANS IN LIBRARY. LEM |
| 7-6-15 RESUB LEFT PKG IN "MEET & GREET" |
| AREA....RESUBMITTAL FORM WAS NOT FILLED OUT |
| PROPERLY WAS NOT SIGNED OR DATED, CORRECTIONS |
| SECTION (TRIANGLES, CLOUDS, OTHERS, ETC. WAS NOT |
| INDICATED)..."STRUCTURAL ELECTRICAL LANDSCAPING, |
| MECHANICAL, PLUMBING, DRIVEWAY" (OK PER S KENNEDY) |
| WL |
| 6/5/2015 APPROVED FOR ISSUANCE PENDING PAYMENT OF |
| FEE BALANCE. CONTACTED APPLICANT. LARGE "R" DAH |
| 4/23/15 ZONING APPROVED. SG |
| 4/17/15 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SPALMER |
| 04/10/15 PLANS RETURNED TO DENIED BIN LARGE "R" |
| ASM |
| 04/10/15 ONE SET PLANS SIGNED OUT & NOA'S BECAUSE |
| OF WRONG ADDRESS ON PLANS. ASM |
| 04/10/15 CHANGE OF CONTRACTOR SUBMITTED NO FEE ASM |
| NEEDS TO CLARIFY THE ADDRESS DUE TO REPLAT. |
| 3/24/15 DENIED/EMAILED/UNDER "P" LARGE PLANS RM |
| 2/26/15 ZONING FAILED. SG |