| Miscellaneous Information / Notes |
| PHASED WORK - MASTER 12040748 ELEVATORS AT BOILER |
| PORTION OF POWER BLOCK BUILDING. |
| |
| |
| |
| |
| |
| |
| 6/29/15 FEES REMOVED, N/A SEE RJR NOTE OF 2/6/14. |
| SAK |
| 3/10/15 PLANS IN FILENET. CP |
| 3/10/15 PEDDS APPROVED, APPLICANT INVITED TO |
| DOWNLOAD PLANS. CP |
| 3/10/15 PEDDS GIVEN TO SKENNEDY. CP |
| 3/10/15 SUBMITTAL OF PEDDS GIVEN TO CAROLINE PUELL |
| SPALMER |
| 2/17/15 EMAIL REMINDER TO SUBMIT PEDDS. CP |
| 1/15/14 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| SUBMIT PEDDS. CP |
| 1/13/14 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUMBIT. CP |
| 12/23/14 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 12/10/14 EMAILED REMINDER RESUBMIT. CP |
| 11/10/14 PLAN REVIEW COMPLETE, APPLICANT INVITED |
| TO RESUBMIT. CP |
| 10/22/14 APPLICANT RESUBMITTED ADDRESSING DENIED |
| COMMENTS, INCOMING COMPLETE. CP |
| 8/31/13 REMINDER EMAIL SENT TO RESUBMIT. CP |
| 7/22/14 EMAIL SENT FOR APPLICANT TO RESUB. CP |
| 3/26/14 - IF THE SCOPE OF THIS PERMIT EXTENDS TO |
| THE ADDITION OF AN ELEVATOR, ELECTRICAL DRAWINGS |
| AND AN ELECTRICAL PERMIT SHALL BE SECURED UNLESS |
| PERMITTED ELSEWHERE. (MA) |
| 3/19/14 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 2/14/14 PRESCREEN PASSED. REVIEWS ASSIGNED. RJR |
| 2/6/14 PHASED WORK, NO REVISION FEES. PROJECT |
| CREATED, INVITATION SENT. RJR |