| Miscellaneous Information / Notes |
| NEW BUILDING OUT PARCEL B2 |
| |
| |
| |
| |
| |
| |
| |
| 12/5/14 PLANS IN FILENET. CP |
| 10/2/14 REC'D TCOC LETTER FROM ARDAMAN & |
| ASSOCIATES.KC |
| 6/5/14 SUBMITTING PEDDS JM |
| 6/3/14 SUBMITTAL SHOP DRAWINGS JM |
| 5/29/14 RECEIVED PEDDS JM |
| 2/20/14 PERMIT PRINTED. APPROVED PLANS AVAILABLE |
| FOR DOWNLOAD. APPLICANT NOTIFIED VIA EMAIL. PERMIT |
| CARD UP FRONT FOR P/U UNDER "E" RJR |
| 2/18/14 PEDDS SUBMITTED AND ROUTED TO RREGUIERO |
| SEW |
| 2-13-14 LAST ZONING REVIEW FAILED IN ERROR. ALL |
| REVIEWS COMPLETE AND PASSED. PERMIT READY TO ISSUE |
| PENDING PAYMENT OF FEE BALANCE OF $20.00 AND |
| RECEIPT OF PEDDS SIGNATURE DOCUMENTS. APPLICANT |
| NOTIFIED VIA EMAIL. RJR |
| 2-5-14 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 1-7-14 RESUBMIT RECEIVED. REVIEWS ASSIGNED. RJR |
| 12-20-13 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 12/2/13 REVIEWED RESIDENT INSPECTOR AGREEMENT.KC |
| 11-13-13 RESUBMIT RECEIVED. REVIEWS ASSIGNED. RJR |
| 10-31-13 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 9/9/13 PLANS UPLOADED. PRESCREEN PASSED. REVIEWS |
| ASSIGNED. RJR |