| Miscellaneous Information / Notes |
| VISITOR CENTER - 3-STORY BUILDING UTILIZED TO |
| SUPPORT FUNCTION OF WASTE TO ENERGY FACILITY |
| |
| |
| |
| 7/19/16 CO ISSUED EMAILED TO MIKE, SENT TO |
| SCANNING AND ORIGINAL IN BOX UNDER "H" |
| 7/19/16 REQUEST FOR CO FROM MIKE SANCHEZ |
| 6/5/15 FEE PAID ON TCO AND PICKED UP BY RICHARD. |
| LWL |
| 6/2/15 TCO REQUEST SUBMITTED AND ROUTED TO KCONRAD |
| SEW |
| 02/17/15 JESSICA P/U STOCKING CERTIFICATE NSD |
| 2/11/15 ISSUED STOCKING CERTIFICATE. TO CO BOX, |
| "H". OWES $500.00.CALLED TAMMY FOR P/U.KC |
| 1/23/15 PLANS IN FILENET. CP |
| 12/4/14 TCO ROUTED TO KEN CONRAD. LWL |
| 11/26/14 FILES IN FILENET. CP |
| 4/10/13 CHANGE OF CONTRACTOR JM |
| 3/15/13 RECEIVED PEDDS DOCS. PERMIT PRINTED AND |
| P/U BY MIKE SANCHEZ. RJR |
| 3/13/13 PER APPLICANT REQUEST, ICF WALL SHOP |
| DRAWINGS ADDED TO THE PROJECT FOR REVIEW. RJR |
| 2/28/13 PRESCREEN PASSED REVIEW DISTRIBUTED |
| APPLICANT NOTIFIED VIA EMAIL CP |
| 1/10/13 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 11/22/12 RESUBMIT RECEIVED. REVIEWS ASSIGNED. RJR |
| 10/9/12 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
| APPLICANT NOTIFIED VIA EMAIL. RJR |
| 8/21/12 PLANS UPLOADED. REVIEWS DISTRIBUTED. RJR |