| Miscellaneous Information / Notes |
| NEW 6000 SQ FT ADDITION ONTO EXISTING SOUTH FL |
| SCIENCE MUSEUM CONSTRUCTED IN THREE PHASES |
| |
| |
| |
| |
| 5/24/13 PICK UP BY JEFF GD |
| 5/21/13 ISSUED 2ND TCO FOR PHASE 3. CALLED JEFF |
| FOR P/U.OWES $500.00. TO CO BOX, "H".KC |
| **DIGITAL PLANS** SEE PROJECTDOX |
| 02/21/13 TCO PICK UP BY JEFF PUT COPY IN PROCESSED |
| FOLDER TO BE SCANNED BY TEQUESTA GD |
| |
| 2/21/13 CALLED JEFF TO P/U REVISED TCO. IN CO BOX |
| UNDER 'H'. RB |
| 2/1/13 JEFF WADE P/U TCO FOR PHASE 1. RB |
| 2/1/13 TCO REQUEST ROUTED TO RB DESK SH |
| 6/27/12 PERMIT CARD RE-PRINTED BECAUSE ELECTRICAL |
| SUB WAS NOT ATTACHED. NOTIFIED GRISSELL VIA EMAIL |
| THAT THE NEW CARD IS UP FRONT FOR P/U. SM BIN |
| UNDER "H" RJR |
| 6/27/12 PERMIT PRINTED. P/U BY MOISES. APPLICANT |
| NOTIFIED VIA EMAIL THAT PLANS ARE STAMPED AND |
| AVAILABLE FOR DOWNLOAD. ALSO NOTIFIED APPLICANT |
| THAT INSURANCE INFO NEEDS TO BE UPDATED PRIOR TO |
| SCHEDULING ANY INSPECTIONS. RJR |
| 6/27/12 RECEIVED PEDDS DOCUMENTS GIVEN TO RON |
| REQUEIRO SPALMER |
| 6-22-12 1 SET OF PEDDS SIGNATURE ROUTED TO R |
| REGUEIRO WL |
| 6/21/12 APPLICATION TURNED IN TO ADD CONTRACTOR & |
| SUBS TO THIS PERMIT SPALMER |
| 6/19/12 IMPACT FEE SUBMITTAL ROUTED TO RON FOR |
| PROCESSING LM |
| 6/18/12 PLANS RETURNED FROM PAYING IMPACT FEES |
| SPALMER |
| 4/26/12 ALL REVIEWS COMPLETE, NOTIFIED RR SH |
| 3/20/12 SECOND ROUND PLANS RECEIVED. REVIEWS |
| DISTRIBUTED. RJR |
| 2/21/12 APPL ROUTED TO RREGUEIRO SEW |