| Miscellaneous Information / Notes |
| NEW SINGLE FAMILY RESIDENCE WITH COVERED PATIO AND |
| ATTACHED GARAGES. |
| |
| |
| |
| 9/18/12 SENT EMAIL TO MIKE. MUST PICK UP DRIVEWAY |
| PLAN UNDER REVISION TRACKING # 10120645 WHEN |
| PICKING UP CO. IN CO BOX UNDER "D". RB |
| 9/18/12 INSPECTOR ID CORRECTED. DRIVEWAY PASSED BY |
| ZONING BECAUSE APPLICATION PREDATED |
| ZONING-IN-PROGRESS AND SURVEYOR PROVIDED CALC TO |
| SHOW THAT FRONT YARD IS 49% GREEN SPACE. HOLD |
| RELEASED. RB |
| 9/13/12 PLACED HOLD ON CO. FINAL INSPECTION |
| RECORDED WITHOUT INSPECTOR ID, DRIVEWAY |
| CONSTRUCTED IN VIOLATION OF CITY CODE AND MUST BE |
| REDUCED. SOLAR DOMESTIC SYSTEM MUST BE INSPECTED. |
| DBW |
| 7-31-12 TEMPORARY POWER RELEASE FORM ROUTED TO J |
| LEAHY WL |
| 01/19/2011 ENG REVIEW F [email protected] |
| ROUTED TO LUIS M. |
| 1/14/11 ROUTED TO MG (ENGINEERING). LMF |
| 12/16/10 FEE PAID NOC SUBMITTED PERMIT/PLANS PU BY |
| MIKE SEW |
| 12/16/10 CALLED/OWES FEES/INS.EXPIRED/NEEDS NOC/ |
| UNDER 'D' LARGE PLANS RM |
| 12/8/10 PASSED "L" WITH 'PROVISO'-MUST APPLY FOR A |
| LANDSCAPE PERMIT AND GET IT APPROVED PRIOR TO 1ST |
| INSPECTION.---RAK |
| 11/30/10 RESUB REVISED BUILDING TOTAL HEIGHT |
| SPALMER |
| 11/15/10 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SEW |
| 10/27/10 ENG REVIEW PASSED [email protected] |
| ROUTED BACK TO SHELF C-3 |
| 10/26/10 ROUTED TO MG (ENGINEERING). LMF |
| 10/25/10 FAILED "L" & SENT TO LMF---RAK |