| Miscellaneous Information / Notes |
| EXISTING GAS STATION W/C-STORE WILL TURN BAYS INTO |
| C-STORE (ZBA # 3247-09) |
| |
| |
| |
| 3/18/10 NOC SUBMITTED AND UPDATED INSPECTION HOLD |
| RELEASED SEW |
| 3-11-10 SADID MIRZADEH PICKUP PERMIT WL |
| 3/11/10 ISSUED, CALLED CONTR, BIG BIN 'M' SMH |
| 3/10/10 PLANS ROUTED TO PROCESSING (MM DESK) SMH |
| 3/9/10 NEED IMPACT FEE RECEIPT, CONTR WILL EMAIL, |
| SENT PLANS TO BE STAMPED - PROVISO, CONTR TO |
| OBTAIN SECOND SET OF MISSING SPEC SHEETS/LANDSCAPE |
| PLAN/PRODUCT APPROVALS PRIOR TO INSPECTION SMH |
| 3/9/10 SET OF PLANS RETURNED W/IMPACT STAMP |
| CHANGED FROM TBD TO CONTRACTOR PUT W/PLANS FROM |
| THE BACK ROUTED TO SHILL SEW |
| 2/11/10 PU ONE SET OF PLANS FOR IMPACT STAMP SEW |
| 2/10/10 NEED IMPACT/CONTRACTOR APPLICATION ONLY, |
| NO FEE TO RESUBMIT, CALLED CONTR L/M, BIG BIN 'T' |
| SMH |
| ***CUSTOMER LEFT BLUE CARD AT MY DESK MMILLER |
| 1/20/10 SENT TO KF-RAK |
| 01/12/2010 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
| 11/24/09 CALLED/LEFT MESSAGE FOR DENIED COMMENTS |
| TO BE ADDRESSED; PLANS RETAINED IN LARGE BIN "T" |
| MAW |
| 11-06-09 2 HRS EXPEDITED PLMG REVIEW ADDED. |
| KSTEVENS |
| 11/05/09 2 HR EXPEDITED REVIEW FEE ADDED FOR |
| ELEC./WRT |
| 11/04/09 3 HR EXPEDITED REVIEW FEE ADDED FOR BLDG |
| SMH |
| 11/03/09 SENT TO KF--RAK |
| 11/02/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
| ROUTED TO LMARTINZED W/PLANS SEW |