| Miscellaneous Information / Notes |
| BUILDOUT FOR RESTAURANT NAMED RELISH |
| |
| |
| |
| 4/14/10 DAN TOBIN P/U CERTIFICATE OF COMPLETION. |
| RB |
| 03/02/2010 RCVD TEMP POWER RELEASE ROUTED TO JAKE |
| LEAHY'S DESK MMILLER |
| 11/18/09 DANIEL PICKED UP PERMIT LM |
| 11-17-09 DANIEL TOBIN PICKUP 1 SET OF PLANS FOR |
| IMPACT FEE STAMP WL |
| 11/17/09 ALL REVIEWS PASSED EXCEPT "IMPACT." |
| CALLED FOR P/U. PLANS TO BE TAKEN TO PALM BEACH |
| COUNTY FOR ASSESSMENT AND PAYMENT OF PBC IMPACT |
| FEES. ALSO, FEE BALANCE OF $765 TO BE PAID. SPOKE |
| TO NAT HEALY. ONE SET PLACED UP FRONT (LG PLAN |
| UNDER "G") TO BE TAKEN TO PBC. THIS SET TO BE |
| RETURNED PRIOR TO ISSUANCE. OTHER SET WITH PERMIT |
| APPLICATION IS IN LARGE DENIED BIN UNDER "G" UNTIL |
| BOTH SETS ARE PROCESSED AND PERMIT IS ISSUED. RJR |
| 11/17/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
| FOR MECHANICAL. RJR |
| 11/16/09 ADDED 2 HRS FOR EXPEDITED |
| ELEC.REVIEW./WRT |
| 11-09-09 BLDG EXPEDITED REVIEW ADD 2 HRS JW |
| 11-9-09 2 HRS EXPEDITED PLMG REVIEW ADDED. |
| KSTEVENS. |
| 11/9/09 EXPEDITED REQUEST SUBMITTED LM |
| 11/03/2009 1ST RESUB PLANS SUBMTTED NO FEE MMILLER |
| 10/28/09 NAT HEALY P/U 1 SET OF DENIED PLANS |
| SPALMER |
| 10/27/09 DENIED PLANS FILED UNDER 'G' LM |
| 10-27-09 2 HRS FOR EXPEDITED PLMG REVIEW ADDED. |
| KSTEVENS. |
| 10/27/09 2HRS ADDED FOR EXPEDITED ELECTRICAL |
| REVIEW./WRT |
| 10/26/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
| FOR MECHANICAL. RJR |
| 10-20-09 BLDG EXPEDITED REVIEW ADD 2HR JW |
| 10/19/09 EXPEDITED REQUEST GIVEN TO LUIS MARTINEZ |
| SPALMER |