| Miscellaneous Information / Notes |
| #08090611(COM-REMODEL) INSTALL 500KW EM GENERATOR |
| WITH EMERGENCY GENERATOR |
| |
| |
| |
| |
| |
| |
| |
| 11/3/09 LETTER SUBMITTED W/NEW PERMIT APPL TO |
| CHANGE CONTR $100 OKAY PER DWISE SEW |
| 09/09/2009 OK TO TAKE NOC IN PER ADRIANNA MCKENZIE |
| ALTHOUGH THERE (2) PARCEL CONTROL NUMBERS ALSO |
| RELEASED NOC SYSTEM MMILLER |
| 8/26/09 JAMES P/U PERMIT SPALMER |
| 8-24-09 CALLED FOR PERMIT P/U AND LEFT A MSG ON |
| NAT H'S VOICE INDICATING THE REQUIREMENT FOR THE |
| RECEIPT OR BLUE CARD AS WELL AS THE N.O.C. FEES |
| ARE DUE ALSO. "S" KSTEVENS. |
| 8/18/09 PUT BACK IN C3 RAK |
| 8/6/09 ADDED TWO HOURS TO EXPEDITED FEE FOR |
| ELECTRIC./WRT. |
| 8/5/09 TWO HOURS ADDED TO EXPEDITED FEE FOR |
| MECHANICAL. RJR |
| 8-04-09 ADD 2HR FOR BLDG EXPEDITED PLAN REVIEW JW |
| 8/3/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN TO |
| LUIS MARTINEZ SPALMER |
| 8/3/09 3RD RESUB $427.20 SPALMER |
| 8/3/09 PLANS DENIED AND GIVEN TO NAT HEALY TO |
| CHANGE OUT SHEETS BEFORE RESUBMITTING. DV PALMER. |
| 7/27/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
| FOR MECHANICAL. RJR |
| 7/24/09 INCREASED VALUE TO $178K BASED ON RESPONSE |
| TO PREVIOUS COMMENTS. LETTER FROM ARCHITECT IN |
| PACKAGE. FEES DUE BEFORE ISSUANCE. DV PALMER |
| 7/22/09 2 HRS ADDED FOR ELECTRICAL EXPEDITED |
| REVIEW./WRT. |
| 7/22/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN TO |
| DOUG WISE SPALMER |
| 7/22/09 2ND RESUB $75 SPALMER |
| 7/20/09 1 SET OF PLANS P/U BY NAT PER DEWEY SLS |
| 06/18/2009 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
| 4/17/09 APP/PLANS P/U BY NAT SLS |
| 04/16/09 CALLED FOR DENIED PLANS P/U; UNDER "S" |
| MAW |
| 04/09/09 ROUTED COPY PD RECEIPT FOR EXPEDITED PLAN |
| REVIEW TO DEWEY PALMER WL |
| 04/09/09 EXPEDITED FEES OF $510 ADDED TO FEES. |
| SPOKE TO NAT HEALY, WILL PAY.. ESTIMATED |
| COMPLETION DATE WILL BE 4/16/09 AS LONG AS FEES |
| ARE PAID ON 4/9. DV PALMER. |
| 04/08/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
| ROUTED TO DPALMER SEW |