| Miscellaneous Information / Notes |
| INSTALLATION OF 200 KW DIESEL GENERATOR AND 1200 |
| GALLON DIESEL SUB-BASE FUEL TANK |
| |
| |
| |
| |
| |
| 9/30/09 NOC FAXED AND UPDATED INSPECTION HOLD |
| RELEASED SEW |
| 9-2-09 KATHY DAVEY PICKUP PERMIT *NEED NOC PRIOR |
| TO 1ST INSPECTION* (GAVE HER COPY OF STATUTE |
| REGARDING NOC BEING OVER 90 DAYS WITHOUT |
| COMMENCING WORK) WL |
| 09/01/2009 CALLED CUSTOMER OWES FEES $ 338.40 & |
| NEEDS NOC OK TO PRINT ONCE FEES ARE PAID FILED |
| UNDER "V" MMILLER |
| 9/1/09 PERMIT VALUE WAS INCREASED BACK TO ORIGINAL |
| APPLICATION VALUE. THE VALUE WAS DECREASED TO |
| DELETED GENERATOR COST AS IT WAS OWNER SUPPLIED. |
| SPOKE TO DAVE HOUGE OF VANS ELECTRIC AND EXPLAINED |
| FBC 108.3 WHICH REQUIRES THE VALUE OF EQUIPMENT |
| EVEN IF OWNER SUPPLIED. TOLD HIM PERMIT IS READY |
| TO ISSUE ONCE BALANCE OF $338.40 IS PAID. |
| CONFIRMED WITH DOUG WISE. DV PALMER. |
| |
| |
| 09/01/2009 OK TO RELEASE 4X THE FEE HOLD PER JAKE |
| LEAHY/DOUG WISE NO WORK STARTED APPROVED PLANS |
| READY FOR P/U FILED UNDER "V" MMILLER |
| 9/1/09 PLANS PASSED BY ZONING, HAND DELIVERED TO |
| DWISE DKF |
| 08/26/2009 3RD RESUB PLANS MMILLER |
| 7/27/09 KELLY FREEMAN ADVISED CUSTOMER THAT THE |
| FIRST ZONING REVIEW REQUIRED A MINOR AMENDMENT, |
| AND THAT THE ZONING REVIEW CANNOT BE PASSED |
| WITHOUT ONE. PLANS AND APPLICATION FILED IN DENIED |
| APPLICATIONS CABINET FOR LARGE PLANS UNDER 'V'. RB |
| 7/24/09 PLANS IN PLAN REVIEW ROOM AND EMAIL SENT |
| TO KELLY FREEMAN TO DO THE ZONING REVIEW. RB |
| 7/17/09 2ND RESUB $136.80 PLACED IN DOUG WISE |
| OFFICE SPALMER |
| 7/17/09 CHANGE VALUE FROM 99,000 TO 57,000 SPALMER |
| 6/8/09 APP/PLANS TAKEN OUT OF C-13 & GIVEN TO DOUG |
| W PER HIS REQUEST SLS |
| 6/4/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
| ROUTED TO DWISE SEW |
| 6/4/09 1ST RESUB W/PLANS & APPL NO FEE SEW |
| 4/28/09 PU BY KATHY SEW |
| 04/23/09 CALLED FOR DENIED PLANS P/U; UNDER "V" |
| MAW |
| 04/01/09 - TO MCRUZ FOR FURTHER PROCESSING DKF |