| Miscellaneous Information / Notes |
| EXPANDING AN EXISTING ONE STORY HOUSE AND ADDING A |
| SECOND FLOOR AND RENOVATING THE EXISTING HOUSE |
| |
| |
| |
| |
| |
| |
| 6/3/11 SEE NEW PERMIT#11060119 SPALMER |
| 4/6/11 CHANGED TO REVOKED PER LM AND BO. RL |
| 3/23/11 ISSUED RED TAG FBC 105.1 FOR COMPLETING |
| WORK WITHOUT PERMIT, INVESTIGATED REVISION |
| RE-FILED UNDER OLD CONTRACTORS NAME 'B' LM |
| C.JORDAN |
| PERMIT CLOSED PER REQUEST OF CONTRACTOR ,WORK |
| COMPLETED TO DRYWALL ,MECH. ROUGH , ELECT ROUGH SP |
| 5/19/10 |
| 5/24/10 LETTER GIVEN TO SANDY.KC |
| 3/29/10 LETTER SUBMITTED TO CANCEL PERMIT ROUTED |
| TO KCONRAD SEW |
| 3-25-2010 CONTRACTOR SENDING LETTER TO REMOVE HIS |
| NAME. DO NOT ALLOW INSPECTIONS TO BE SCHEDULED - |
| DRF |
| 10-1-09 ROHAN PICKU REV (DATED 7-2-09) WL |
| 10/1/09 REV OK PUT OUT FRONT UNDER "B" CALLED JL |
| 9/28/09 KEVIN P/U REV DATED 9/23/09 SPALMER |
| 9/24/09 REV OK/OWES FEE/CALLED/UNDER 'B' RM |
| 9/23/09 BLDG SUBMITTAL ROOFING ENGINEERS LETTER NO |
| FEE SLS |
| 9/21/09 - NO ZONING REVIEW REQUIRED PLACE IN LM |
| CHAIR AV |
| 9/17/09 REV DENIED/CALLED/UNDER 'B' RM |
| 9/15/09 BLDG REVISION # 5 ROOFING PRODUCT |
| APPROVALS $80 SLS |
| 9/14/09 ELEC REV LOCATION FOR TRANSFER PANEL |
| LOCATION OF GENERATOR $140 SEW |
| 9/10/09 MECH REVISION P/U & BAL PD $170 BY KEVIN |
| MARAGH SLS |
| 9/10/09 REVISION PASSED, CALLED FOR P/U. SPOKE TO |
| KEVIN. MUST PAY EXPEDITED FEE ($170)WHEN PICKING |
| UP REVISION. SM PLAN UNDER "B" RJR |
| 9/10/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
| FOR MECHANICAL. RJR |
| 9/10/09 EXPEDITED REQUEST AND MECH PLANS ROUTED TO |
| RJR DESK. |
| 9/9/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
| ROUTED W/PLANS TO LMARTINEZ SEW |
| 9/9/09 MECH REV A/C DUCT IN KITCHEN $80 SEW |
| 7/28/09 PLANS FOR REV #1 $410 BLDG/ELEC/PLUMB/MECH |
| UNDER "B" IN HOLDING BIN(SMALL)./WRT. |
| 7/9/09 ROOFING REVISION # 2 $80 SLS |
| 07/06/2009 GAVE CUSTOMER RCPT TO PAY FOR REVISION |
| FEES MMILLER |
| 7-2-09 REV #1 $410 BLDG/ELEC/PLUMB/MECH WL |
| 7-2-09 ROHAN MARAGH PICKUP SOIL TEST (DATED |
| 5-1-09) WL |
| 5/8/09 CONTACTED ROHAN SOIL TEST SUBMITTAL READY |
| FOR PU "B" REMINED HIM OF BLUE CARD SEW |
| 05/01/2009 SOIL TEST SUBMITTAL NO FEE MMILLER |
| 3/18/09 FEES PAID INS UPDATED PERMIT/PLANS PU BY |
| ROHAN SEW |
| 3/17/09 PERMIT READY TO PRINT, UNDER(B)**LARGE |
| BINNS** WORKER'S COMP EXP, FEE'S DUE, SPOKE TO |
| KEVIN MARAGH ADARROUGH |
| 2/10/09 2ND RESUB $ SPALMER |
| 1/27/09 DENIED PLANS PU BY KEVIN SEW |
| 1/26/09 DENIED/LEFT MESSAGE/UNDER 'B' BIG PLAN BIN |
| RM |
| 12/22/08 1ST RESUB PLANS/APP NO FEE SLS |
| 11-19-08 KEVIN MARAGH PICKUP DENIED PLANS WL |
| 11-19-08 CALLED FOR P/U AND TALKED TO KEVIN |
| INDICATING THAT ALL TRADES AND ZONING HAD COMMENTS |
| AND REMINDED HIM OF THE REQUIREMENT FOR THE |
| RECIEPT OR BLUE CARD TO RETRIEVE THE |
| PLANS/APPLICATION. "B-LARGE" KSTEVENS |
| 11/7/08 - SENT TO INCOMING FOR FURTHER PROCESSING. |
| ~MC |