| Miscellaneous Information / Notes |
| # 103 TENANT BUILD OUT |
| |
| |
| |
| |
| |
| 08/24/2009 "CERTIFICATE OF OCCUPANCY" P/U BY FRANK |
| MMILLER |
| 7/15/09 ELEC/MECH REV PU BY NAT SEW |
| 7/14/09 ELEC & MECH REVS CALLED FOR P/U. SPOKE TO |
| NAT. SM BIN UNDER "T" RJR |
| 06/26/2009 ELECTRICAL & MECHANICAL REVISION FEES |
| $110.00 MMILLER |
| 05/18/2009 APPROVED BLDG APPROVED ELECTRICAL |
| APPROVED PLUMBING APPROVED MECHANICAL & APPROVED |
| FIRE THAT WAS SUBMITTED ON 04/28/2009 WAS P/U BY |
| NAT HEALY MMILLER |
| 5/12/09 BLD,ELEC,MECH,PLUMB REVISION CALLED FOR |
| P/U. SPOKE TO NAT. SM BIN UNDER "T" RJR |
| 4/28/09 BLDG/ELEC/MECH $ SPALMER |
| 4/2/09 RECD CHANGE OF QUALIFIER LETTER SAME |
| COMPANY NEW QUALIFIER NO FEE SLS |
| 02/05/2009 RCVD NOC OK TO TAKE IN ALTHOUGH PARCEL |
| CONTROL NUMBER IS DIFFERENT OK PER ADRIANNA |
| MCKENZIE MMILLER |
| 12-31-08 NAT HEALY PICKUP PERMIT *NEEDS NOC PRIOR |
| TO 1ST INSPECTION* WL |
| 12/30/08 PERMIT FILED UNDER 'T' *LARGE BIN* LM/WL |
| 12/18/08 3RD RESUB PLANS/APP $80 SLS |
| 12/15/08 NAT P/U REV DATED 12/1/08 SPALMER |
| 12/12/08 CALLED FOR P/U. SPOKE TO NAT. PLUMBING |
| REVIEW PREVIOUSLY PASSED, BUT NEW SHEETS WERE |
| SUBMITTED. NO CHANGES TO PLUMBING DESIGN ARE |
| INDICATED ON PLANS. SINCE THE PLUMBING RISER IS |
| SHOWN ON PAGE M1, WHICH ALREADY FAILED, THE |
| PLUMBING REVIEW IS BEING SKIPPED TO FACILITATE A |
| QUICKER RESUBMISSION OF PLANS. THIS WAS AGREED TO |
| BY NAT HEALY. RJR |
| 12/12/08 4X FEE ADDED PER FS553.80(2)(B). FEE OF |
| $960 WILL BE DUE. DV PALMER. |
| 12/1/08 2ND RESUB W/PLANS & APPL $80 SEW |
| 11/17/08 PU BY NAT SEW |
| 11/15/08 DENIED PLANS CALLED FOR P/U. LEFT MSG FOR |
| NAT HEALY. LG BIN UNDER "T" RJR |
| 10/31/08 1ST RESUB NO FEE SPALMER |
| 8/25/08 NAT P/U PLANS JREYES |
| 8/20/08 CALLED FOR P/U/ SPOKE TO JACK. LG BIN |
| UNDER "T" RJR |
| 07/24/2008 OKAY TO CREATE UNIT PER ADRIANNA |
| MCKENZIE MMILLER |