| Miscellaneous Information / Notes |
| NEW MERCANTILE CONST PRECAST W/2 LEVELS LOWER |
| LEVEL PKG, UPPER LEVEL SALES, ROOF STRUCTURE & |
| UPPER LEVEL STEEL FRAME TENANT: TARGET T-2427 |
| |
| |
| 10/28/2009 "CERTIFICATE OF OCCUPANCY" P/U SCOTT |
| MMILLER |
| 10/28/09 CALLED BRETT NANSEN OF RYAN COMPANY TO |
| P/U CO. SCOTT COPENHARVE OF RYAN CO. WILL P/U CO. |
| RB |
| 10/08/2009 FEES PAID APPROVED BLDG APPROVED ZONING |
| APPROVED ZONING THAT WAS SUBMITTED ON 09/16/2009 |
| WAS P/U BY SCOTT MMILLER |
| 10/07/09 RVSD SHEETS READY; ADVISED BRETT OF A FEE |
| ADJUSTMENT DUE TO THERE BEING 6 SHEETS INSTEAD OF |
| 5 SHEETS IN EACH SET; FILED LARGE BIN "R" MAW |
| 09/23/09 RCVD A REQUEST FOR A TCO FEES $ 500.00 |
| THAT KEN CONRAD ALREADY HAD AT HIS DESK ATTACHED |
| RCPT TO THE LETTER & RE-ROUTED TO KEN CONRAD'S |
| DESK MMILLER |
| 9-16-09 REV #7 $200 BLDG/ZONING/FIRE "A020, A151, |
| A217, A362, A611" (ROLLED PLANS) WL |
| 09/15/2009 APPROVED BLDG APROVED ELECTRICAL & |
| APPROVED FIRE THAT WAS SUBMITTED ON 09/08/2009 WAS |
| P/U BY BRETT MMILLER |
| 9-15-09 CALLED CONTRACTOR AND SPOKE WITH BRETT |
| HANSON REVISION IS FILED UNDER "R" LARGE PLAN JW |
| 9-8-09 REV #6 $110 BLDG/ELEC "REVISED ELEC |
| DRAWINGS SHOWING EXIST SIGNAGE IN PARKING |
| GARAGE"**ROLLED PLANS** WL |
| 08/25/2009 APPROVED BLDG REVISION THAT WAS |
| SUBMITTED 08/19/2009 WAS P/U BY BRETT MMILLER |
| 8-24-09 TCO $500 LTR ROUTED TO K CONRAD WL |
| 8-20-09 CALLED RYANS CO. STAMPED SHOP DRAWING |
| PLANS ARE FILED OUT FRONT UNDER "R" LARGE PLANS |
| 2ROLLS JW |
| 8/19/09 BLDG SUBMITTAL INFO REQUESTED PER JWITMER |
| FOR PRECAST SUBMITTAL SEW |
| 8/10/09 BRETT P/U SUBMITTALS DATED 7/2/09 SPALMER |
| 8-10-09 CALLED CONTRACTOR SPOKE WITH BRETT HANSON |
| SUBMITTALS ARE FILED UNDER "R" LARGE PLAN JW |
| FAILED SUBMITTALS ARE FILED BACK OF OFFICE UNDER |
| "R" LARGE PLANJW |
| 8-10-09 DEE HALVERSON PICKUP BLDG REV (DATED |
| 7-2-09) WL |
| 07/30/09 RSVD PLANS READY FOR P/U; LARGE BIN "R" |
| MAW |
| 7/23/09 EXPEDITED REVIEW REQUEST SUBMITTED AND |
| ROUTED TO LMARTINEZ SEW |
| 07/22/2009 BLDG SUBMITTAL NO FEE ROUTED TO KEN |
| CONRAD'S DESK MMILLER |
| 7/9/09 PLBG/ELEC REVISION DATED 6/10 P/U BY BRETT |
| SLS |
| 7/8/09 ROLLED PLANS UNDER "R" (LARGER BROWN FAUX |
| WOOD BINS) FOR PICK UP. CALLED AND SPOKE TO |
| BRETT.REMINDED OF BLUE CARD. DV PALMER |
| 7/2/09 BLDG SUBMITTAL TIERRA INSP & TESTING |
| REPORTS PER KEN CONRADS REQUEST PUT ON KENS SHELF |
| SLS |
| 7/2/09 BLDG SUBMITTAL PRECAST-STRUCT STEEL-JOIST & |
| DECKING FINAL SHOP DRWGS MUNTERS UNIT WIND CALCS |
| NO FEE SLS |
| 7/2/09 BLDG/PLBG/ELEC/MECH REVISION #5 $2570.00 |
| SLS |
| 7/2/09 BLDG SUBMITTALS DATED 6/10/09 & 6/17/09 P/U |
| BY BRETT NANSEN SLS |
| 7/2/09 BLDG SUBMITTALS DATED 3/18/09 & 4/1/09 P/U |
| BY BRETT NANSEN SLS |
| 6-17-09 CALLED CONTRACTOR AND SPOKE WITH BRETT |
| SUBMITTAL FILED UNDER **LARGE BINS** "R" JW |
| 6-15-09 CALLED CONTRACTOR AND SPOKE WITH BRETT |
| PLANS FILED UNDER **LARGE BINS** "R" JW |
| 6/10/09 REV ELEC/PLUMB $200 SPALMER |
| 6/10/09 BLDG SUBMITTAL SHOP DRAWINGS NO FEE |
| SPALMER |
| 6/10/09 BRETT P/U REV DATED 4/9/09 SPALMER |
| 05/14/09 PLANS READY FOR P/U; IN **LARGE BINS** |
| "R" MAW |
| 04/23/09 BRETT NANSEN PICKUP SUBMITTAL (DATED |
| 04/16/09) WL |
| 04/21/09 CALLED CONTRACTOR PLANS FILED UNDER "R" |
| LARGE PLAN SPOKE WITH BRETT JW |
| 04/16/09 BLDG SUBMITTAL THAT WAS SUBMITTED ON |
| 04/09/09 WAS P/U BY BRETT MMILLER |
| 04/16/09 BLDG SUBMITTAL NO FEE (HILTI FIRESTOPPING |
| SUBMITTAL) MMILLER |
| 4/13/09 CALLED SPOKE WITH RYAN PLANS FILED UNDER |
| "R" **LARGE BINS** JW |
| 4/9/09 ELEC/PLUMBING REV RESPONSE TO GENERAL |
| REVISIONS TO PROJECT SUBMITTED ON 1/30/09 SEW |
| 4/9/09 BLDG SUBMITTAL REVISEDMETAL FRAMING DETAILS |
| & DESIGN CALCS SEW |
| 4/9/09 BRETT WILL PU PLANS FILED UNDER "R" SMALL |
| BIN ANOTHER DAY SEW |
| 4/09/09 SPOKE WITH CONTRACTORS REP BRETT, PLANS |
| FILED UNDER "R" SMALL PLAN JW |
| 4-01-09 CALLED CONTRACTOR SPOKE WITH SUBMITTALS |
| FILED UNDER "R" SMALL PLAN JW |
| 4/1/09 SUBMITTAL BLDG NO FEE SPALMER |
| 3/18/09 BLDG SUBMITTAL PRECAST GROUT CONCRETE MIX |
| DESIGNS IRRIGATION SYSTEM SUBMITTAL SEW |
| 3/18/09 PU BY BRETT SEW |
| 03/17/09 CALLED FOR PLANS P/U FILED ON FLOOR & |
| BOTH BINS "R" LARGE PLAN,SPOKE WITH BRETT'S VOICE |
| MAIL JW |
| 03/16/09 PLANS RECEIVED 2/13/09 READY FOR P/U; IN |
| LARGE BIN "R"; FIRE ALARM PLANS THAT WERE INCLUDED |
| ARE TO BE SUBMITTED UNDER A SEPARATE PERMIT |
| MAW/FIRE |
| 03/12/09 BLDG SUBMITTAL NO FEE MMILLER |
| 03/06/09 ENGINEER REVIEW-NO |
| [email protected] |
| 02/25/09 BLDG SUBMITTAL WIND LOAD CALCS SHORING |
| DESIGN STUD FRAMING DETAILS STUD DESIGN CRITERIA |
| SEW |
| 02/13/09 SUBMITTAL FOR BLDG/FIRE SPALMER |
| 01/30/09 BLDG/ELEC/PLUMBING/MECH/FIRE REV PER |
| ATTACHED PLANS $4,220 CONTRACTOR WILL BE BACK |
| MONDAY 02/02/09 TO PAY (HAD OLD FEE SCHEDULE) SEW |
| 01/09/09 WIND CALCS PU BY BRAD SEW |
| 01/09/09 CALLED CONTRACTOR SUBMITTAL FILED UNDER |
| "R" LARGE PLAN LEFY MEEASGE WWITH JW |
| 01/08/09 BLDG SUBMITTAL THRESHOLD AGREEMENT ROUTED |
| TO GSMITH SEW |
| 11/21/08 MECH SUBMITTAL WIND CALCS NO FEE SLS |
| 10-15-08 SCOTT COPENHARVE PICKUP PERMIT WL |
| 10/10/08 PLAS FILED UNDER 'R' (LARGE BIN) LM |
| 10/9/08 PLANS ONLY, UP FRONT UNDER(R), CUSTOMER |
| P/U PERMIT 10/3/08. LUIS TO CALL CUSTOMER TODAY |
| FOR P/U. ADARROUGH |
| 10/3/08 SCOTT PICKED UP PERMIT, PLANS WILL BE |
| PROCESSED NEXT WEEK LM |
| 9/25/08 PER CONTRACTORS REQUEST(SHILL OKAYED) |
| ADDED SQ FOOTAGE AND RADON FEES SEW |
| 9-16-08 ROUTED TO DIANE'S BOX. TM |
| 9/12/08 EARLY START FOR SITE WORK ONLY APP PER |
| RAB/AMM |
| 9-3-08 CHG FROM PLAN REVIEW TO PERMIT CONTR PAYING |
| 30% $9150.00 "PLAN REVIEW/PROJECT APPL WAS LOST" |
| OK TO SUBMIT WITH APPL FOR PERMIT..PLAN REVIEW TO |
| DETERMINE WHETHER THEY WANT ANOTHER APPL FILLED |
| OUT...CONTR DID NOT HAVE OCCUPATION BUSINESS TAX |
| FOR CONTR..THEY WILL SUBMIT THIS INFO PRIOR TO |
| PERMIT ISSUANCE WL |
| 8-21-08 SCOTT COPENHARVE PICKUP DENIED PLANS WL |
| 08/18/08 CALLED FOR PLANS P/U BOTTOM BIN NEAR "A" |
| MAW |
| 07/14/08 RESUB OF PLANS FOR PLAN REVIEW $$,280.00 |
| SEW |
| 07/02/2008 DENIED PROJECT P/U BY JOEL LEONARD |
| MMILLER |
| 07/01/08 CALLED FOR PLANS P/U; IN BOTTOM BIN "R" |
| MAW |
| 05/21/08 RESUB OF PLANS FOR PLAN REVIEW $2,280.00 |
| SEW |
| 05/21/08 PU BY JOEL SEW |
| 05/06/08 PLANS FOUND ON BACK RACK SHOULD HAVE WENT |
| OUT WITH 4/30 PICK UP BY JOEL. PLANS WILL BE FILED |
| UNDER 'R' (LARGE BIN) AND CALLED FOR PICK UP. |
| LEFT MESSAGE LM |
| 04-30-08 JOEL LEONARD PICKUP DENIED PLANS WL |
| 4/25/08 CALL FOR P/U W/CORR'S, UNDER(R) **LARGE |
| BINNS** 3 ROLLS, SPOKE TO CHERYL OUTZ |
| ADARROUGH |