| Miscellaneous Information / Notes |
| A 10,000 SF OF MULTIPURPOSE BUILDING WITH |
| CLASSROOMS OFFICES BATHROOMS INCLUDES PARKING |
| |
| |
| ***EXPEDITED REVIEW. RB*** |
| |
| ***FRONT COUNTER: FOR ANY REVISIONS PLEASE NOTIFY |
| ROBERT BROWN IN PERSON OR BY EMAIL*** |
| |
| 9/28/10 ADDED TCO FEES PER D WISE - DRF |
| 6/9/10 EXTEND TCO PER D WISE EXPIRATION: 9/7/10 - |
| DRF |
| 3/11/10 TCO ISSUED.CALLED GC FOR P/U. FILED UNDER |
| "B".KC |
| 3/10/10 SUBMITTED COMPLETION AGREEMENT OCCUPANCY |
| REQUEST $500 ROUTED TO KCONRAD SEW |
| 2-8-10 BLDG/MECH REV TRACKING #10020196 REV ROUTED |
| DIRECTLY TO L MARTINEZ PER R BROWN WL |
| 12/14/09 MECH ONLY REVISION 17A PICKED UP BY JEFF |
| HALVERSON. RJR |
| 12/02/09 REVIEW OF MULTI-TRADE REVISION COMPLETE. |
| CALLED BILL TO ADDRESS MECHANICAL COMMENT(S) |
| ON-LINE; THESE PLANS RETAINED IN LARGE BIN "B" MAW |
| 11/24/09 MECH ONLY REV. CALLED FOR P/U. LEFT MSG |
| FOR BILL LYNCH. SM PLAN UNDER "B" RJR |
| 11/5/09 MECH REV PER ATTACHED PLANS $80 SEW |
| 11/5/09 BLDG/ELEC/MECH REV PER ATTACHED PLANS $440 |
| SEW |
| 10-27-09 BILL LYNCH PICKUP NO FEE CHGD BLDG METAL |
| SHOP DRAWING (DATED 10-22-09) & PRE CAST SHOP |
| DRAWING REV (DATED 10-22-09) SEE BELOW WL |
| 10-26-09 CALLED CONTRACTOR REVISIONS ARE FILED |
| UNDER "B" SMALL PLAN JW |
| 10-22-09 REV #15 "CORRECTION TO MTL FRAMING SHOP |
| DRAWINGS I-LAG 750SD SELF TAPPING FASTENER" (ORIG |
| CAME IN AS METAL FRAMING SHOP DRAWING CHGD TO REV |
| # 15 BY J WITMER) NO FEE CHARGED PER R BROWN |
| (ROUTED TO J WITMER) WL |
| 10-22-09 REV #16 BLDG 3 SETS (PRE-CAST) SHOP |
| DRAWINGS, PROD DATA CONCERNING PROPOSED CONST |
| MATERIALS (ROUTED TO J WITMER) WL |
| 10/07/09 CALLED CONTRACTOR DENIED REVISIONS FILED |
| UNDER "B" SMALL PLAN JW S1-S4 |
| 10/01/09 SUBMITTAL METAL FRAMING SHOP DRAWINGS NO |
| FEE SPALMER |
| 9/30/09 BLDG REVS SUBMITTED 9/15 UNDER "B" (LARGE |
| BINS)FOR PU. CALLED AND SPOKE TO BILL REMINDING OF |
| BLUE CARD/RECEIPT. DV PALMER |
| 9/15/09 BLDG REV $80 SPALMER |
| 9/9/09 CUSTOMER SIGNED OUT 1 SET OF PLANS SPALMER |
| 9-08-09 CALLED CONTRACTOR , CONTACT BILL LYNCH |
| ABOUT FAILED ENERGY CALCULATIONS AND A 104& A-601 |
| PLANS ARE FILED UNDER "B" SMALL PLANS IN THE REAR |
| OF OFFICE JW |
| 8/27/09 CALLED CONTRACTOR APPROVALS FILED UNDER |
| "B" SMALL PLAN JW |
| 8/27/09 SUBMITTALS FORWARDED TO J. WITMER DESK JW |
| 08/27/2009 BLDG SUBMITTAL HOWEVER EXPLAINED TO |
| CUSTOMER THAT ONCE PLANS EXAMINER REVIEWS FEES MAY |
| APPLY PRIOR TO P/U MMILLER |
| |
| 08/27/2009 BLDG SUBMITTAL HOWEVER EXPLAINED TO |
| CUSTOMER THAT ONCE PLANS EXAMINER REVIEWS FEES MAY |
| APPLY PRIOR TO P/U MMILLER |
| 8-24-09 BILL LYNCH PICKUP ELEC REV (DATED 8-14-09) |
| WL |
| 8/24/09 MECH/ELEC REVISION, CALLED FOR P/U. LEFT |
| MSG FOR BILL. SM BIN UNDER "B" RJR |
| 08/24/209 BLDG REVISION THAT WAS SUBMITTED ON |
| 08/18/2009 WAS P/U BY BILL LYNCH MMILLER |
| 08/24/2009 APPROVED BLDG REVISION THAT WAS |
| SUBMITTED ON 08/18/2009 WAS P/U BY BILL LYNCH |
| MMILLER |
| 8-20-09 CALLED CONTRACTOR REVISIONS ARE FILED |
| UNDER "B" SMALL PLAN JW |
| 8-18-09 SENT E-MAIL TO R BROWN.. (3) REVISIONS: |
| REV #11 $80 BLDG "GAINES PARK COMMUNITY CTR CURVED |
| MTL ROOF SOFFIT DETAIL", REV 12 BLDG $80 "SEMCO |
| FV-3000 ERV STRUCTURAL SUPPORT", & REV #13 $110 |
| "A-104 NEW FACILITY ROOF PLAN 3 COPIES, A-601, |
| WALL PENETRATIONS, ROOF DETAILS, 3 COPIES, ENERGY |
| CALCULATIONS (R-10 INSULATION) 3 COPIES)" WL |
| 8/14/09 ELEC/MECH REVISION SUBMITTED #10 $140 SLS |
| 07/30/09 FIRE REVIEW REVISIONS WERE DONE UNDER |
| SUB- |
| PERMITS 09020455 (FIRE LINE),08110335 |
| (SPRINKLER)MAW |
| 7-27-09 REV #9 $110 "REV #1 FIRE SPRINKLER SHOPS & |
| HYDRAULIC DESIGN INFORMATION" PER L MARTINEZ THIS |
| REV IS FOR 09020455 & 08110335..E-MAILED THIS INFO |
| TO R BROWN WL |
| 7/15/09 REVISION GIVEN TO JEFFREY LM |
| 6/30/09 BLDG/PLUMBING REV PER ATTACHED PLANS $590 |
| ROUTED TO RBROWN SEW |
| 6/30/09 ELEC REV PU BY BILL SEW |
| 6/26/08 ELEC REV OK,CALLED AND SPOKE TO BILL, |
| REMINDED OF BLUE CARD TO PICK UP REVISION. UNDER |
| *B* (SMALL) DV PALMER. |
| 6/18/09 BLDG REV PU BY BILL SEW |
| 6/18/09 5 SUBMITTALS PU BY BILL SEW |
| 6-17-09 CALLED CONTRACTOR SUBMITTALS FILED UNDER |
| "B" SMALL PLANS JW |
| 6/15/09 BLDG REV $110 SPALMER |
| 6/15/09 ELEC REV $110 SPALMER |
| 6/15/09 5 SUBMITTALS NO FEE RFI 70/71/72/73/74 |
| SPALMER |
| 6-02-09 SUBMITTALSHORING PLAN PICKED UP BY BILL |
| LYNCH |
| 6/2/09 BLDG SUBMITTAL SHORING PLAN NO FEE SLS |
| 6/1/09 JEFF PICKED UP SUBMITTAL LM |
| 5/29/09 CALLED FILED PLANS UNDER "B" SMALL PLAN JW |
| 05/28/2009 BLDG SUBMITTAL NO FEE ( SHORING PLAN 3 |
| SETS GAINES PARK COMMUNITY CENTER) MMILLER |
| 5/11/9 SUBMITTALS GIVEN TO J HALVERSON SMH |
| 5/11/09 CALLED FILED UNDER "B" SMALL PLANS SPOKE |
| WITH |
| BILL LYNCH JW |
| 5/5/09 (4) BLDG SUBMITTALS STOREFRONT SHOP DRAWING |
| & NOA STRUCTURAL CALCS FOR STEEL JOIST DESIGN |
| STRUCTURAL STEEL SHOPS & LETTER APPROVING RE-USE |
| OF JOIST SUPPORT CLIP SEW |
| 4/29/09 JEFF HALVERSON P/U REV DATED 4/17/09 |
| SPALMER |
| 04/29/09 CALLED CONTRACTOR PLANS FILED UNDER |
| "B"SMALL PLAN JW |
| 04/20/2009 APPROVED BLDG APPROVED PLUMBING & |
| APPROVED FIRE THAT WAS SUBMITTED ON 03/25/2009 WAS |
| P/U BY BILL MMILLER |
| *****CUSTOMER LEFT BLUE CARD AT MY DESK THAT IS |
| DATED 04/17/2009 FOR A BLDG REVISION MR. BILL |
| LYNCH WILL BE THE PERSON TO P/U PERMIT MMILLER |
| 4-17-09 CALLED FOR P/U OF APPROVED REVISIONS |
| SUBMITTED 3-25 AND LEFT A MSG ON BILL L'S VOICE |
| MAIL INDICATING THE REQUIREMENT FOR THE RECIEPT OR |
| BLUE CARD. "B" KSTEVENS. |
| 4/17/09 BLDG REV # 5 $140 SLS |
| 4-9-09 BILL BARBALATO PICKUP 2 REV (BLDG DATED |
| 4-7-09) & MECH (DATED 4-1-09) WL |
| 4/9/09 CALLED FOR P/U PLANS IN BOX (B) HM. |
| 4-08-09 CALLED CONTRACTOR AND SPOKE WITH BILL, |
| REVISIONS FILED UNDER "B" SMALL PLANS JW |
| 4/7/09 BLDG REVISION # 3 ROOF STRUCTURE $260 SLS |
| 3/31/09 MECHANICAL REVISION # 3 $80 SLS |
| 3-25-09 REV #2 BLDG/PLUMB $260 "REVISION" WL |
| 1-26-09 JEFF HALVERSON PICKUP PLUMB/FIRE REV |
| (DATED 1-23-09) WL |
| 1/23/09 SPOKE TO J HALVERSON FOR P/U "B" LARGE BIN |
| MRW |
| 1/23/09 PLUMBING REV REVISED SHEET 6 REGARDING |
| FIRE LINE $80 SEW |
| 01/08/2009 PERMIT PLUS PLANS P/U BY MICHAEL HAMAN |
| MMILLER |
| 01-07-09 CALLED CONTRACTOR LEFT MESSAGE FOR |
| CONTRACTOR ON VOICE MAIL PLANS FILED LOWER BINS, |
| E-MAILED JEFF HALVERSON & NEIL MELICK OF ISSUANCE |
| OF PLANS JW |
| 1/2/09 PERMISSION GRANTED FOR EARLY START ALL |
| TRADES PER RAB/AMM |
| 12/9/08 CHANGE FROM PROJECT TO PERMIT SPALMER |
| 12/3/08 HALVERSON TROOK PLANS LM |
| 12/02/08 CALLED FOR PLANS P/U; IN BOTTOM BIN "C" |
| MAW |
| 11/17/08 5TH MAJOR REVIEW RESUB $920 SEW |
| 10/21/08 ***ONCE BLD COM PERMIT IS ISSUED, ALL |
| PERMIT DOCUMENTATION FOR FOUNDATION PERMIT |
| #08080277 SHALL BE INCORPROATED INTO THE |
| DOCUMENTATION FOR THIS PERMIT TO FACILITATE |
| CONTINUATION OF THRESHOLD INSPECTION PLAN AND |
| SPECIAL INSPECTOR AGREEMENT. RJR |
| 10/21/08 JEFF HALVERSON P/U DENIED PLANS SPALMER |
| 10/16/08 CALLED FOR PLANS P/U; LEFT MESSAGE |
| 644-7416 J.HALVERSON PHONE; PLANS FILED IN BOTTOM |
| BIN "C" MAW |
| 10/03/08 SPECIAL INSPECTOR MEETING COMPLETED.NEED |
| COMPLETED SPECIAL INSPECTOR AGREEMENT.KC |
| 09/29/08 4TH MAJOR WORK IN REVIEW $920 SPALMER |
| 08/08/08 APPL & PLANS PU BY JEFFREY SEW |
| 08/07/08 CALLED FOR PLANS P/U; UNABLE TO REACH |
| JEFF HALVERSON BY PHONE; PLANS FILED IN BOTTOM BIN |
| "C" MAW |
| 06/30/08 3RD MAJOR WORK IN REVIEW SPALMER |
| 06/2/08 JEFF P/U DENIED PLANS SPALMER |
| 05-30-08 CALLED JEFF HALVERSON PLANS FILED UNDER |
| "C"LARGE PLANS JW |
| 04/30/08 PLANS TAKEN OFF HOLD, FEES WERE PAID AND |
| NEW *RESUB * DATE WILL BE 4/30. DV PALMER. |
| |
| 04/15/08 PLANS WERE PLACED ON HOLD AND NOT TO BE |
| REVIEWED AS FEES FROM FIRST AND SECOND SUBMITTAL |
| FOR PLAN REVIEW WAS NOT PAID. PER R. BROWN AND N. |
| MELICK. DV PALMER. |
| 04/7/08 2ND MAJOR WORKING DRAWING REVIEW 82 PAGES |
| SLS |
| 11/2/07 PLANS/APP/COMMENTS P/U BY JEFF HALVOERSON |
| AJP |
| 10/30/07 BUILDING PLANS CALLED FOR P/U. LEFT MSG |
| FOR JEFF H. LG BIN UNDER "C" RJR |