| Miscellaneous Information / Notes |
| BUILDING REVOVATIONS & CONSTRUCTION OF NEW COVERED |
| ENTRY |
| |
| |
| |
| 2/3/09 JOSE P/U REV DATED 1/16/09 SPALMER |
| 2/3/09 CALLED RON FOR P/U . PLANS IN BOX (C) HM. |
| 2/3/09 **********ROLL PLAN****************** LM |
| 1-23-09 RON YURGOSKY PICKUP BLDG/PLUMB/MECH/ZONING |
| REV (DATED 10-17-08), BLDG REV #5 (DATED |
| 10-20-08), & LANDSCAPE SUBMITTAL (DATED 12-16-08)) |
| WL |
| 1/16/09 MECH REVISION # 8 GAS VENTILATION $140 SLS |
| 12/18/08 - LANDSCAPE PLAN READY FOR P/U. CALLED |
| CONTRATOR FOR P/U. FILED UNDER C. ~MC |
| 12/16/2008 LANDSCAPING SUBMITTAL NO FEE (CHANGE OF |
| PLANT TYPES & LOCATIONS REQUESTED BEFORE FINAL |
| INSPECTION MMILLER |
| 11/25/2008 GREGG P/U APPROVED PLUMBING & GAS & |
| MECHANICAL THAT WAS SUBMITTED 0N 11/21/2008 OK PER |
| RON REGUERIO MMILLER |
| 11-25-08 GREG LAMANNA PICKUP REV #6 GAS (DATED |
| 11-3-08) WL |
| 11-24-08 REMOVED PLMG/MECH REVISION FROM #13 AND |
| PLACED IN RON"S OFFICE FOR REVIEW. |
| 11-24-08 CALLED FOR P/U OF PLUMBING REVISIONS AND |
| TALKED TO GREG INDICATING THAT THE REVISION WAS |
| DENIED AND THAT HE NEEDS THE RECIEPT OR BLUE CARD |
| TO RETRIEVE THE REVISIONS. "C" KSTEVENS |
| 11/21/08 PLUMBING/MECH REV AS BUILT PLUMBING & |
| MECH ADDITIONAL ITEMS $70 SEW |
| 11/19/08 REV DATED 11/17/08, UP FRONT |
| UNDER(C),(PART OF REV APPROVED, OTHER PART |
| DENIED), LEFT VM MESSAGE ADARROUGH |
| 11/18/8 ROUTED REVISION (PARTIAL DENIED, PARTIAL |
| PASSED) TO MM DESK FOR PROCESSING SMH |
| 11/18/8 ADJUSTED VALUE, INCREASED $10K FOR LIGHT |
| POLES, KNEE WALL, SKYLIGHT PER CONTRACTOR SMH |
| 11/10/08 REV DATED 10/20/08, APPROVED AND READY |
| FOR P/U, UNDER(C) SPOKE TO JASON CAMERON ADARROUGH |
| 11/7/8 TO MM DESK FOR PROCESSING SMH |
| ***PLEASE SEE NOTES****MMILLER |
| 11/03/2008 GAS REVISION #06 FEES $ 60.00 MMILLER |
| 10/21/2008 BUILDING REVISION #05 FEES $ 100.00 |
| MMILLER |
| 10/17/2008 BLDG, PLUMBING, MECHANICAL & ZONING |
| REVISION #04 FEES $100.00 MMILLER |
| 09/16/2008 APPROVED BLDG REVISION THAT WAS |
| SUBMITTED ON 08/22/2008 IS P/U BY JASON MMILLER |
| 09/09/2008 CALLED CUSTOMER APPROVED BLDG REVISION |
| THAT WAS SUBMITTED ON 08/22/2008 IS READY FOR P/U |
| FILED UNDER "C" MMILLER |
| 9/8/8 BUILDING REVISION ROUTED TO MM DESK FOR |
| PROCESSING; PROVISO TO ADDRESS BLDG REVIEW #8 |
| COMMENTS SMH |
| 9/8/8 FEES PAID, ON SMH DESK FOR REVIEW SMH |
| 8/29/8 CONTR DID NOT PAY FEES, 'C' SMH |
| 8/26/8 FEES DUE, PLANS ON HOLD, NOT PAID AT TIME |
| OF REVISION SUBMITTAL (PAGES WRONG), CALLED CONTR; |
| SAID HE'D PAY, I INSTRUCTED HIM TO CALL ME AFTER |
| FEES PAID SMH |
| 8/26/08 ENERGY CALCS P/U BY JASON. 8/26/08 RJR |
| 8/26/08 MECH SUBMITTAL ENERGY CALCS THAT WERE LOST |
| REQUEST BY RREGUEIRO SEW |
| 8/25/08 MARTA P/U REVISIONS JREYES |
| 08/22/2008 CALLED CUSTOMER APPROVED BUILDING |
| REVISION THAT WAS SUBMITTED ON 08/20/2008 IS READY |
| FOR P/U FILED UNDER "C" MMILLER |
| 08/22/2008 BLDG REVISION #03 FEES $ 60.00 MMILLER |
| 8/22/08 JASON P/U PERMIT JREYES |
| 8/21/8 TO MM DESK FOR PROCESSING SMH |
| 8-20-08 NO FEE RFG BLDG SUBMITTAL "ATTACHED PLS |
| FIND PRODUCT APPROVAL REVIEWED BY DESIGNERS" WL |
| 8/12/08 MARTA P/U REVISIONS JREYES |
| 8/11/08 PRODUCT APROVAL SUBMITTAL DENIED CALLED |
| CONT LEFT MSG FILED UNDER "C" SLS |
| 8/11/8 TO MM DESK SMH |
| 8/1/08 PROD APRROV REV $60 SPALMER |
| 7-23-08 CALLED FOR P/U PLMG REVISION AND LEFT A |
| MESSAGE FOR RON INDICATING THAT THE REVISIONS WERE |
| DENIED AND THAT THE RECIEPT OR BLUE CARD WAS |
| REQUIRED TO RETRIEVE THE REVISIONS. "C" KSTEVENS |
| 7/10/08 PLUMBING REVISION FROM OUTSIDE OF BLDG TO |
| INSIDE $80 SLS |
| 6/26/08 RON P/U PERMIT & TURNED IN NEW NOC |
| SPALMER |
| 6/26/08 CALL FOR P/U, UNDER(C)**LARGE BINNS**, |
| READY TO PRINT, COUNTY LICENSE EXPIRED, NOC |
| EXPIRED LEFT VM MESSAGE |
| ADARROUGH |
| 5/29/08 4TH RESUB NO FEE PER AMCKENZIE SPALMER |
| 5-20-08 RON YORGOSKY PICKUP DENIED PLANS WL |
| 05/19/08 CALLED FOR PLANS P/U; IN LARGE BIN "C" |
| MAW |
| 05/02/08 RON YURGOSKY SUBMITTED PROD APPROVAL (2 |
| COPIES) THAT WERE LEFT OUT OF RESUB..OK PER R |
| BROWN TO INSERT IN PKG AS BLDG HAS NOT |
| REVIEWED...ROUTED TO S HILL BY ROBERT BROWN WL |
| 04/30/2008 3RD RESUB PLANS PLUS APP MMILLER |
| 03/03/08 RAY LEWIS PICKUP DENIED PLANS WL |
| 02/29/08 PLANS UNDER "C" FOR PU, CALLED AND SPOKE |
| TO RON, TOLD TO BRING IN BLUE CARD. (LARGE BINS) |
| DV PALMER. |
| 02/27/08 PLANS AT DV PALMER DESK PER 2/01/08 NOTE |
| MAW |
| *************************************** |
| **** 2/1/08 PLEASE DO NOT RELEASE PLANS IF THIS |
| NOTE IS STILL IN COMPUTER. DV PALMER. |
| 2/1/08 THE NOTICE OF COMMENCMENT SUBMITTED HAS |
| EXPIRED PER FS 713.13(2). PLEASE ALSO SEE THAT A |
| 4X FEE WAS ASSESSED PER FS 553.80(2)(B) WHICH IS |
| REQUIRED TO BE PAID BEFORE NEXT REUSBMITTAL OF |
| PLANS. $3,408 IS FEE AMOUNT DUE. DV PALMER. |
| ************************************************ |
| |
| |
| 1/29/08 2ND RESUB W/PLANS & APPL SEW |
| 12-20-07 RON YURGOSKY PICKUP DENIED PLANS WL |
| 12-05-07 CALLED FOR P/U AND LEFT A MESSAGE ON |
| GARY'S ANSWERING MACHINE AND INDICATED THAT THERE |
| WERE COMMENTS TO BE ADDRESSED AND THAT THE RECIEPT |
| OR BLUE CARD WAS REQUIRED TO RETRIEVE THE PLANS. |
| "C-LARGE" KSTEVENS |
| 10/22/07 1ST RESUB PLANS/APP NO FEE SLS |
| 10/22/07 PLANS/APP/COMMENTS P/U BY RON AJP |
| 09/24/07 CALLED FOR PLANS P/U; IN LARGE BIN "C" |
| MAW |