| Miscellaneous Information / Notes |
| 1-STORY CBS MASTER BEDROOM ADDITION APPROX. |
| 641SQ.FT. |
| |
| |
| |
| |
| |
| 3-19-08 P MECH/REV. P/U BY KEN B. TG. |
| 03/17/2008 MECHANICAL REVISION #03 FEES $ 60.00 |
| MMILLER |
| 3/5/08 REV OK/P/U BY MILTON RM |
| 03/05/2008 BLDG REVISION # 02 FEES $ 70.00 |
| MMILLER |
| 2/8/08 PU BY MILTON SEW |
| 2/7/08 REV DENIED/LEFT MESSAGE/UNDER 'G' RM |
| 02/06/2008 BLDG REVISION #01 FEES $70.00 MMILLER |
| 11/2/07 PERMIT P/U BY MILTON GREY AJP |
| 11/1/07 CALLED/UNDER 'G' RM |
| 10-30-07 3RD RESUB $119.91 "SIGNED PROD APPROVALS |
| AS REQUESTED & COPY DRAWINGS FOR MECH W/ARI |
| CERTIFIED" WL |
| 10/26/07 DENIED RESUB PLANS/APP/COMMENTS P/U BY |
| MILTON GREY AJP |
| |
| 10/26/07 TO LARGE PLAN BIN "G" AJP |
| 10/26/07 DENIED/CALLED MILTON/UNDER "G" RM |
| 10/18/07 2ND RESUB $ SPALMER |
| 10/18/07 DENIED RESUB PLANS/APP/COMMENTS P/U BY |
| MILTON GREY AJP |
| 10/18/07 MOVED TO LARGE PLAN BIN "G" AJP |
| 10/17/07 DENIED/CALLED/UNDER 'G' RM |
| ****WILL PROVIDE NOC AT THE TIME OF P/U OF PERMIT |
| *** MMILLER |
| 09/12/2007 1ST RESUB PLANS PLUS APP NO FEE |
| MMILLER |
| 8/2/07 PLANS/APP/COMMENTS P/U BY MILTON GREY AJP |
| 8/2/07 PLANS UNDER "G" JHL |