| Miscellaneous Information / Notes |
| TO INSTALL HURRICANE SHUTTERS ON 12 OPEING 2 |
| OPENINGS TO BEPANELS 10 OPENINGS TO BE ACCORDIANS |
| |
| |
| |
| |
| 9/12/07 PERMIT P/U BY DAVID AJP |
| 09/11/2007 CALLED CUSTOMER LEFT MESSAGE PERMIT |
| PLUS PLANS READY FOR P/U FILED UNDER "L" MMILLER |
| 9/10/7 TO MM DESK SMH |
| 9/04/07 3RD RESUB $50 FEE- CORRECTIONS MADE FG |
| 08/29?2007 DENIED PLANS PLUS APP P/U BY WAYNE |
| MILLER MMILLER |
| 8/28/07 CORRECTIONS NEEDED CALLED CONT LEFT MSG |
| FOR DAVID FILED UNDER "L" LARGE BIN 2 RESUBS SAME |
| PKG SLS |
| 8/28/7 TO MM DESK SMH |
| 8/10/07 3RD RESUB W/PLANS & APPL SEW |
| 8/10/07 DAVID PICKED UP PLANS LM |
| 8/3/07 CORRECTIONS NEEDED CALLED LEFT MSG FOR |
| DAVID FILED UNDER "L" SLS |
| 8/3/7 TO MM DESK SMH |
| 7/31/07 2ND RESUB W/PLANS & APPL SEW |
| 7/31/07 DENIED RESUB P/U BY DIANE AJP |
| 7/31/07 MOVED TO LARGE PLAN BIN "L" AJP |
| 7/30/07 CORRECTIONS NEEDED CALLED LEFT MSG FOR |
| DAVID FILED UNDER "L" SLS |
| 7/30/7 TO SLS DESK SMH |
| 07/18/07 ST RESUB NO FEE- PROVIDED FLOOR PLAN AND |
| INSTALLATION SCHEDULE FG |
| 7-17-07 DIANA MILLER PICKUP DENIED PLANS WL |
| 7/13/07 CORRECTIONS NEEDED CALLED LEFT MSG FOR |
| DAVID FILED UNDER "L" SLS |
| 7/13/7 TO SLS DESK SMH |