| Miscellaneous Information / Notes |
| SPRINGHILL SUITES HOTEL - 5 STORIES W/130 UNITS |
| SEPARATE ROOFING & MECH PERMITS REQ'D (MIN. FEE). |
| |
| |
| |
| 12/9/15 THIS PARCEL IS COVERED BY LOMR38, VILLAGES |
| OF PALM BEACH (PREVIOUSLY SPENCER LAKES 3) SH |
| |
| |
| 4/26/11 ADDED (2) TCO EXTENSION FEES OF ($825 X 2) |
| CASE #1391 ALSO SEE PERMIT #06111071 CASE #1392 |
| PER DWISE TAKES IT UP TO 12/17/10 SEW |
| 3/3/10 LAVONNA P/U TCO EXTENSION. RB |
| 3/1/10 LETTER SUBMITTED REQUESTING TCO EXTENSION |
| $955(OK PER RBROWN) ROUTED TO DFULCHER SEW |
| 12/21/2009 RETROACTIVELY ISSUED TCO EXTENSION |
| ORIGINALLY REQUESTED ON OCTOBER 28 EFFECTIVE |
| NOVEMBER 14. STILL NEED ADRIANNA TO |
| CREDIT/TRANSFER FEE PAID FOR CBAA TO THIS PERMIT, |
| SINCE NOVEMBER FEE RESOLUTION GRANTED AUTHORITY |
| FOR ADDITIONAL EXTENSION WITHOUT CBAA AND HEARING |
| WAS CANCELLED. TCO VALID FOR 90 DAYS AND WILL |
| EXPIRE FEBRUARY 14, 2010. DBW. |
| 12/08/2009 REQUEST AN EXTENSTION FOR A TCO FEES |
| $225.00 PER DOUG ROUTED TO DIANE FULCHER'S DESK |
| MMILLER |
| 11-3-09 DONNA PICKUP ELEC REV (DATED 10-26-09) WL |
| 10/30/09 ELECTRICAL REVISIONS UNDER "D" (LARGE |
| BINS FOR PU ONCE FEE BALANCE OF $212.50 IS PAID. |
| CALLED AND SPOKE TO DONNA AND LEFT MESSAGE ALSO |
| ABOUT FEE. DV PALMER. |
| 10/28/09 RECD EXTENSION LETTER FOR 4TH TCO $500 |
| GAVE TO KEN SLS |
| 10/26/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN |
| TO LUIS MARTINEZ SPALMER |
| 10/26/09 ELECTRICAL REV $410 SPALMER |
| 9-24-09 DONNA PICKUP 1 SET OF DENIED ELEC REV |
| (DATED 9-14-09) WL |
| 9/23/09 REQUEST FOR EXTENTION OF TCO $500 SPALMER |
| 9/20/09 DENIED ELECTRICAL REVISIONS UNDER "D" REAR |
| LARGE BINS. CALLED AND SENT E-MAIL TO DONNA FROM |
| PERMITS EXPRESS. DV PALMER. |
| 9/14/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN TO |
| LUIS MARTINEZ SPALMER |
| 9/14/09 ELEC REV $200 SPALMER |
| 8/17/09 DONNA P/U REV DATED 8/10/09 NO REVIEW WAS |
| DONE SPALMER |
| 8/14/09 RECD PLBG CLARIFICATION LETTER FROM |
| ENGINEER PER GARY SALFELDER SLS |
| 8/13/09 DISCUSSED WITH DVP. I CONFIRM THAT PLANS |
| CAN BE PICKED UP, CORRECTED AND SUBMITTED ONCE |
| READY FOR REVIEW. RB |
| 8/13/09 ELECTRICAL REV SUBMITTED ON 8/10/09 IN |
| **LARGE BINS** "D" FOR P/U NO REVIEW DONE/NO |
| EXPEDITED REVIEW DONE OK TO RELEASE ALL 3 SETS |
| STILL HAVE CREDIT FOR $380 DVPALMER/SPALMER |
| 8/11/09 TEMPORARY CERTIFICATE OF OCCUPANCY $500 |
| SPALMER |
| 8/10/09 ELEC REVISION # 23 AS-BUILTS $380 RECD |
| EXPEDITED PLAN REVIEW REQUEST FORM GAVE TO LUIS |
| SLS |
| 08/03/2009 MECHANICAL REVISION P/U BY DONNA |
| MMILLER |
| 08/03/2009 RCVD REQUEST FOR TCO FEES $ 500.00 |
| ROUTED TO KEN CONRAD'S DESK MMILLER |
| 8/2/09 EXPEDITED REVIEW FEE FOR REVIEW 7/31,8/2 |
| ADDED. BALANCE OF $403.75. DV PALMER. |
| 7/31/09 MECH RESTAMP 1 PG $55 GAVE TO JIM W PER |
| HIS REQUEST SLS |
| 7/31/09 BLDG/ZONING SUBMITTAL DATED 7/8/09 P/U BY |
| DONNA SLS |
| 7-31 CALLED CONTRACTOR PLANS FILED UNDER "D" LARGE |
| PLANS JW |
| 7/30/09 EXPEDITED PLAN GIVEN TO DEWEY LM |
| ****RCVD EXPEDITED PLAN REVIEW REQUEST FORM" |
| ROUTED TO DOUG WISE'S DESK ALONG WITH ELECTRICAL |
| REVISION MMILLER |
| 07/30/2009 ELECTRICAL REVISION #22 FEES $290.00 |
| MMILLER |
| 07/16/2009 ELECTRICAL REVISION #21 FEES $80.00 |
| MMILLER |
| 7/16/09 ELEV REV SUBMITTED 7/8 ARE IN BINS IN BACK |
| AS THEY ARE DENIED. UNDER *D*, CALLED AND LEFT |
| MESSAGE ON DONNA'S CELL VM. PLANS NOT BEING PICKED |
| UP UNLESS ABSOLUTELY NEEDING ONE COPY. PER DW. DV |
| PALMER. |
| 7-9-09 ELEC. REV. SENT TO DEWEY'S DESK. JG. |
| 7/8/09 ELEC REV $110 SPALMER |
| 7/8/09 BLDG/ZONING REV $260 SPALMER |
| 06-25-09 CALLED CONTRACTOR PLANS FILED UNDER |
| **LARGE BINS** "D" JW |
| 06/25/2009 ELECTRICAL REVISION THAT WAS SUBMITTED |
| ON 06/19/2009 WAS P/U BY KRISTY MMILLER |
| 6/25/09 ELEC REV OK, CALLED AND SPOKE TO DONNA, |
| SMALL REVISION UNDER "D" FOR PU. DV PALMER. |
| 6/19/09 ELEC REV E501 PANEL $80 SEW |
| 06/16/09, PLACED PLANS IN J.WHITMERS CHAIR. |
| 6/2/09 BLDG/ZON/FIRE/ENG REV $230 SPALMER |
| 05/13/2009 BLDG & FIRE REVISION THAT WAS SUBMITTED |
| ON 04/09/2009 CUSOTMER REQUESTING THAT REVISION BE |
| VOIDED OUT IT NO LONGER NEEDED MMILLER |
| 05/06/2009 APPROVED BLDG APPROVED FIRE THAT WAS |
| SUBMITTED ON 04/27/2009 WAS P/U BY 04/27/2009 |
| MMILLER |
| 05/06/2009 APPROVED BLDG APPROVED ELECTRICAL |
| APPROVED ZONING THAT WAS SUBMITTED ON 04/06/2009 |
| WAS P/U BY DONNA MMILLER |
| 5/06 REVISIONS CALLED CONTRACTOR AND SPOKE WITH |
| DONNA, PLANS ARE FILED UNDER "D" LARGE PLANS JW |
| 5/5/09 REVISIONS SUBMITTED 4/6 ARE UNDER "D" FOR |
| PICK UP. THESE ARE LARGER FOLDED PLANS WHICH WILL |
| ALSO BE WITH THE PLANS FOR THE SECOND HOTEL IN |
| BROWN BINS. THE "D" IN DBC IS HIGHLIGHTED. LEFT |
| MESSAGE ON DONNA'S CELL VM. DV PALMER. |
| 4/27/09 BLDG REV CORRECTIONS TO REV #4 SEW |
| 4/27/09 PU BY KRISTY SEW |
| 04/24/09 CALLED FOR PLANS P/U; IN LARGE BIN "D" |
| MAW |
| 04/09/09 BLDG/FIRE REV PER INSPECTOR $1550 SEW |
| 04/09/09 PU BY DONNA SEW |
| 04/08/09 CALLED CONTRACTOR REVISION FILED UNDER"D" |
| SMALL PLAN JW |
| 04/07/09 REV PU BY DONNA SEW |
| 04/07/09 CALLED FOR P/U UNDER "D" 3592 LEW |
| 04/06/09 ELEC & ZONING REVISION # 14 $ |
| 04/06/09 ELEC/ZONING/LANDSCAPING REVISION # 13 |
| RESUBMITTED NO FEE PER NOTE BELOW FROM LUIS SLS |
| 04/02/09 PLUMBING(GAS) REV CORRECTIONS $80 SEW |
| 03/31/09 REV #13 DATED 3/24/09 IS BEING PULLED BY |
| DONNA TO SUBMIT AT A LATER DATE OKAY PER LMARTINEZ |
| AND WE WILL HONOR FEES PREVIOUSLY PAID WHEN COMING |
| BACK IN SEW |
| 03/24/09 DELETED REV #9 SEE NOTE ON 3/11/09/AMM |
| 03-24-09 REV #13 $590 ELEC, ZONING, LANDSCAPING, |
| "CORRECTIONS TO COMMENTS ISSUED FROM ZONING & |
| LANDSCAPE" WL |
| 3/18/09 PU BY DONNA SEEW |
| 3/17/09 APPLIED $260 REV FEE TO FIRE SP PERMIT/AMM |
| 3-16-09 CALLED CONTRACTORS EXPEDITER DONNA JONES |
| PLANS FILED UNDER"D" LARGE PLAN JW |
| 3/11/09 PU BY DONNA SEW |
| 3/11/09 FIRE SPRINKLER REVISION SHOULD HAVE GONE |
| UNDER FIRE SPRINKLER PERMIT # 08070151 NO |
| MECHANICAL REVISION INCLUDED ON THIS PER DEWEY |
| GIVEN TO ADRIANNA TO TRANSFER MONIES TO RIGHT |
| PERMIT # SLS |
| 2/26/09 BLDG REV S202 S307 A501 DELETE COLUMNS @ |
| VESTIBULE & REVISE FRAMING DETAILS $140 SEW |
| 2/26/09 PLUMBING REV FOR FIELD CONDITIONS $80 SEW |
| 2/20/09 BLDG/ELEC/MECH REV AS PER ATTACHED PLANS |
| $320 SEW |
| 2/9/09 MECH & FIRE SPRINKLER REVISION # 9 $260 SLS |
| 1/9/09 PU BY DONNA SEW |
| 01-07-09 CALLED DONNA FOR PICK UP OF ENERGY CALCS |
| FILED UNDER "D" SMALL PLAN JW |
| 11/24/08 APP/PLANS P/U BY DONNA SLS |
| 11-21-08 CALLED DONNA JONES REVISION# 4 FILED |
| UNDER |
| "D" LARGE PLAN JW |
| 11/5/08 ROOFING REVISION $90 CHGD ROOFING SYSTEM |
| SLS |
| 11/03/2008 DENIED ELECTRICAL FOR ZONING & |
| ENGINEERING & ELECTRICAL THAT WAS SUBMITTED ON |
| 10/09/2008 WAS P/U BY DONNA MMILLER |
| 10/31/08 REVISIONS FILED UNDER 'D' (LARGE BIN) LM |
| 10-29-08, CALLED DONNA JONES, 1-954-536-3959, LEFT |
| MESSAGE THE PLANS READY TO BE PICKED UP. |
| 10/22/08, PASSED ENGINERING REVIEW |
| 10/20/08 CHANGE OF CONTRACTOR $100 SPALMER |
| 10/9/08 ENGINEERING/LANDSCAPING/ZONING REVISION # |
| 7 $210 SLS |
| 10/3/08 DONNA PICKED UP ELECTRICAL REVISION ONLY, |
| HAD BLUE CARD. DID NOT HAVE BLUE CARD FOR MECH REV |
| AND AUTHORIZED AGENT WAS EXPIRED. PLANS STILL |
| UNDER "D" (LARGE BINS) DV PALMER. |
| 10/3/08 ELEC REV DENIED, CALLED AND SPOKE TO |
| DONNA. UNDER "D" (SMALL BINS) FOR PU. DV PALMER. |
| 10-01-08 CALLED CONTRACTOR AND SPOKE WITH JOE |
| MADEYA |
| PLANS FILED UNDER "D" LARGE PLANS JW |
| 09/25/2008 ELECTRICAL REVISION #06 FEES $ 60.00 |
| MMILLER |
| 09/23/2008 BLDG REVISION # 05 FEES $ 90.00 MMILLER |
| 9/16/08 CHRISTY P/U DENIED PLANS SPALMER |
| 9/9/8 CORR, CALLED CONTR, BIG BIN 'DBC |
| CONSTRUCTION' SMH |
| 9/9/8 PLANS SENT TO ENGINEERING INBOX SMH |
| 09/05/08 PLANS SENT TO DEWEY PALMER'S DESK; |
| MAW/FIRE |
| 09/03/08 DAN P.U PLANS JREYES |
| 08-25-08 CALLED CONTRACTOR CELL PHONE NUMBER LIST |
| DAN ROOT, CALLED ANSWERED NOT AVAILABLE CALLED |
| HOME OFFICE PLANS FILED UNDER "D" LARGE PLAN JW |
| 8/7/08 SHOP DRAWING PU BY MIKE HEERY SEW |
| 08/7/08 BLDG REV GLASS GLAZING WINDOWS SEW |
| 08/5/08 BLDG/ELEC/MECH/ZONING REV ADDRESSING |
| DENIED COMMENTS SEW |
| 07-31-08 CALLED FILED UNDER "D"LARGE PLAN JW |
| 7/15/08 SUBMITTAL PRECAST SHOP DRAWINGS SPRINGHILL |
| NO FEE BLUE CARD GIVEN TO CUSTOMER SPALMER |
| 07-9-08 MIKE HEERY PICKUP BLDG SUBMITTAL DATED |
| (07-03-08) WL |
| 07-03-08 CALLED CONT FILED UNDER "D" LARGE PLAN JW |
| 07/03/08 BLDG SUBMITTAL PRECAST CONCRETE PLANK |
| SHOP DRWGS NO FEE SLS |
| 06/03/08 DONNA P/U STRUCTURAL STEEL SHOP DRAWINGS |
| SPALMER |
| 06/03/08 DONNA P/U PRECAST CONCRETE PLANK SHOP |
| DRAWINGS SPALMER |
| 06/03/08 DONNA P/U ELEVATOR SHOP DRAWINGS SPALMER |
| 06-03-08 CALLED FILED UNDER "D" LARGE PLANS JW |
| 05/30/08 PU BY DONNA SEW |
| 05/29/08 CALLED FOR PLANS P/U; IN LARGE BIN "D" |
| MAW |
| 05/22/08 STRUCTURAL STEEL SHOP DRAWINGS NO FEE |
| SPALMER |
| 05/22/08 PRECAST CONCRETE PLANK SHOP DRAWINGS NO |
| FEE SPALMER |
| 05/22/08 ELEVATOR SHOP DRAWINGS NO FEE SPALMER |
| 5-6-08 MANNY FAGUNDES PICKUP DENIED ZONING REV |
| DATED 4-23-08 WL |
| 05/05/08 ZON. REV. FAILED, CALLED DONNA TO P/U. |
| FILED UNDER "D". LMF |
| 04/29/08 - REVISIONS PERTAIN ONLY TO LANDSCAPING. |
| NEED TO CHECK WITH THE CB #4 AND #42 AND COORD. |
| LMF |
| 4/28/08 - ZON. REV. SENT TO LMF - 5TH FLOOR CJH |
| 04/23/2008 BLDG ELECTRICAL PLUMBING MECHANICAL |
| ZONING & ENGINEERING REVISION # 02 FEES $830.00 |
| MMILLER |
| |
| 04/23/2008 ZONING REVISION # 01 FEES $90.00 |
| MMILLER |
| 3/31/08 THE OUSTANDING RESUBMITTAL FEE HAS BEEN |
| PAID. RB |
| 03/28/2008 GAVE CUSTOMER RCPT IN THE AMOUNT OF |
| $9017.14 MMILLER |
| ***AS OF 3/20/08 $8250 RESUBMITTAL FEE IS DUE*** |
| ***FEE NOT YET POSTED BUT MUST BE PAID BY |
| 3/31/08*** |
| ***OK TO RELEASE PERMIT CARD AND PLANS, RB*** |
| |
| 3/21/08 DONNA P/U PERMIT SPALMER |
| 3/21/8 ADDED RADON FEES, PLANS AND PERMIT CARD UP |
| FRONT BIG BIN 'DBC CONST' SMH |
| 3/21/8 IMPACT FEES PAID ON FOUNDATION PERMIT |
| 07110311 SMH |
| 3/20/08 CALLED DONNA JONES FOR PERMIT P/U. PERMIT |
| CARD ONLY. PLANS WILL BE STAMPED LATER. 'D'. RB |
| 2/19/08 RESUBMITTAL FEE MUST BE PAID, BUT 4X PLAN |
| REVIEW FEE IS NOT DUE AT THIS TIME. ON 2/12/08, |
| THE ARCHITECT AND ENGINEER MET WITH ROBERT BROWN |
| AND KEN STEVENS TO DISCUSS THE COMMENTS, AND |
| PERMITTING DOCUMENTS. SOME OF THE COMMENTS WERE |
| SHOWN TO HAVE BEEN ADDRESSED BY THE SPEC BOOK, AND |
| ENGINEER AGREED TO REPEAT THE PERTINENT |
| INFORMATION ON THE PLANS.RB |
| 02/15/08 RESUB W/O FEE UNTIL LUIS TALKS TO |
| ROBERT/AMM |
| 02/11/08 CALLED FOR PLANS P/U; IN BOTTOM BIN "D" |
| MAW |
| ************************************************* |
| 02-01-08 4X THE FEE HAS BEEN ADDED PER FS |
| 553.80(2)(B) WHICH IS REQUIRED TO BE PAID BEFORE |
| THE NEXT RESUBMITTAL OF THE PLANS $99,000.00 IS |
| THE FEE AMOUNT DUE.KSTEVEN |
| ************************************************** |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| 01/03/08 3RD RESUB $8250 SPALMER |
| 12/17/07 ELEC SUB PERMIT APPL UP FRONT IN FILE |
| UNDER "A" (ATLANTIC CERT ELEC) TO BE PUT W/THIS |
| PERMIT PKG SEW |
| 12/05/07 NEIL MELICK HAS ISSUED AN AUTHORIZATIO TO |
| START WORK BEFORE THE PERMIT ISSUANCE. JDS |
| 11/27/07 PLANS (4-ROLLS,3 BINDERS, 3 SPEC BOOKS) |
| P/U BY DONNA AJP |
| 11-24-07 CALLED FOR P/U AND LEFT A MESSAGE ON |
| DONNA'S ANSWERING MACHINE INDICAING THAT THERE |
| WERE COMMENTS TO BE ADDRESSED AND THAT SHE NEEDED |
| THE RECIEPT OR THE BLUE CARD TO RETRIEVE THE |
| PLANS. "A-LARGE ON THE FLOOR IN FRONT OF THE "A" |
| BOXES. KSTEVENS |
| 9/20/07 CHANGE OF CONTRACTOR $100 SPALMER |
| 08/31/2007 2ND RESUB PLANS PLUS APP MMILLER |
| 6-1-2007 DONNA JONES PICKUP DENIED PLANS WL |
| 5-29-07 CALLED PERMIT EXPRESS AND SPOKE WITH DONNA |
| JONES ANSWER MACHINE PLACED PLANS IN THE LOWER |
| BINS BRING BLUE CAARD JW |
| 3/21/07 1ST RESUB PLANS/APP NO FEE SLS |
| 2/22/07 DONNA P/U DENIED PLANS SPALMER |
| 2/20/07 PLANS UNDER "A" IN LARGE BINS FOR PU, |
| CALLED LEFT MESSAGE ON BOB ROTH'S VM, TOLD TO |
| BRING IN BLUE CARD. DV PALMER |
| 02/19/07 PLANS RETURNED TO CSD BUILDING. |
| MAW/FIRE |
| 02/17/07 1 OF 2 PLANS TAKEN FROM CSD BUILDING BY |
| MAW/FIRE |
| 11/30/06 SENT TO LILI FOR ADDRESSING SEW |