| Miscellaneous Information / Notes |
| CONSTRUCT NEW GYMNASIUM |
| |
| |
| |
| |
| ORDINANCE 3941-06 REQUIRES ALL PARCELS TO BE |
| UNIFIED PRIOR TO CONSTRUCTION. |
| |
| |
| |
| |
| 08/04/2009 APPROVED BLDG REVISION THAT WAS |
| SUBMITTED ON 07/30/2009 WAS P/U BY ROSE MMILLER |
| 8-03 CALLED ROSE PLANS ARE FILED UNDER "A" SMALL |
| PLANS JW |
| 7/30/09 BLDG REV $260 SPALMER |
| 07/14/2009 APPROVED BLDG SUBMITTAL THAT WAS |
| SUBMITTED ON 07/08/2009 WAS P/U BY ROSE MMILLER |
| 07/14/2009 DENIED ZONING REVISION THAT WAS |
| SUBMITTED ON 06/25/2009 WAS P/U BY ROSE MMILLER |
| 7-14-09 CALLED CONTRACTOR SUBMITTAL FILED UNDER |
| "A" SMALL PLAN JW |
| 7/8/09 BLDG REV BILKO HATCH SUBMITTAL $80 SPALMER |
| 6/30/09 CALLED ROSE FOR 2ND TCO P/U.KC |
| 6/25/09 LETTER SUBMITTED FOR TCO $500 ROUTED TO |
| KCONRAD SEW |
| 6/16/09 ROSE P/U PLMG & BLDG REV/AMM |
| 6-15-09 CALLED FOR P/U OF APPROVED PLMG REVISIONS |
| AND TALKED TO ROSE K. INDICATING THE REQUIREMENT |
| FOR THE RECIEPT OR BLUE CARD. "A-LARGE" KSTEVENS. |
| 6-15-09 CALLED CONTRACTOR SPOKE WITH ROSE |
| SUBMITTAL FILED UNDER "A" SMALL PLAN JW |
| 06/11/2009 PLUMBING REVISION #16 FEES $200.00 |
| MMILLER |
| 6-1-09 ROSE PICKUP 2 MECH REV (DATED 5-18-09 & |
| 5-20-09) WL |
| 6/1/09 MECH REV FROM 5/18 AND 5/20 PASSED, CALLED |
| FOR P/U. LEFT MSG FOR ROSE. LG BIN UNDER "A" RJR |
| 5/29/09-ISSUED TCO. TO CO BOX, FILED UNDER "A".KC |
| 5/29/09 BLDG REVISION # 15 $200 GEO FOAM PER JIM |
| SLS |
| 5/29/09 LANDSCAPE REVISION P/U BY ROSE SLS |
| 05/26/2009 RETURNED FROM ZONING READY FOR P/U |
| FILED UNDER "A" MMILLER/ ANNA MARIA APONTE |
| 5/20/09 MECH REV $260 SPALMER |
| 5/20/09 ANNA MARIE TOOK LANDSCAPE REVISIONS FROM |
| PICK-UP DRAWER LM |
| 5/19/09 P/U ROSE/AMM |
| 5-18-09 REV #13 MECH WL |
| 5/18/09 ROSE P/U REV DATED 4/30/09 SPALMER |
| 5/18/09 ROSE P/U MECH REV DATED 5/4/09 SPALMER |
| 5/15/09 MECH REVISION (SUBMITTED 5/4) CALLED FOR |
| P/U. LEFT VOICEMAIL FOR ROSE ON CELL PHONE. LG BIN |
| UNDER "A" RJR |
| 5/15/09 REVISION (SUBMITTED 4/30) READY FOR P/U. |
| LEFT MSG FOR ROSE ON CELL PHONE. LG BIN UNDER "A" |
| RJR |
| 5/12/09 LANDSCAPE REVISION # 12 FOR ROBERT KUSSNES |
| $80 SLS |
| 5/7/09 LETTER SUBMITTED FOR TCO $500 SEW |
| 05/04/2009 MECHANICAL REVISION # 11 FEES $260.00 |
| MMILLER |
| 04/30/2009 BLDG PLUMBING & MECHANICAL REVISION #10 |
| FEES MMILLER |
| 4-21-09 ROSE KENNEY PICKUP LANDSCAPE REV (DATED |
| 3-31-09) WL |
| 4/20/09 LANDSCAPE REVISIONS FROM 3/31 FILED UNDER |
| 'A' LM |
| 4/20/09 PU BY ROSE SEW |
| 04/14/09 RVSD PLANS READY FOR P/U; LARGE BIN "A" |
| MAW |
| 04/02/09 REV SUBMITTED ON 3/12/09 PU BY ROSE SEW |
| 03/31/09 REV SUBMITTED 3/12/09, READY TO P/U, |
| W/CORR'S, UNDER(A) LEFT VM MESSAGE FOR ROSE KENNEY |
| ADARROUGH |
| 03/31/09 LANDSCAPE ZON REV $80 SPALMER |
| 03/12/09 LANDSCAPE ZON REV $80 SPALMER |
| 03/10/09 ROSE P/U REV LANDSCAPE REV DATED 1/30/09 |
| SPALMER |
| 03/06/09 BLDG/ELEC/PLUMB/FIRE REV $ SPALMER |
| 03/03/09 - PERMIT FAILED. CALLED APPLICANT FOR |
| P/U. FILED UNDER A. ~MC |
| 02/27/2009 ZONING REVISION #06 FEES $ 80.00 |
| MMILLER |
| 02/27/2009 DENIED ZONING REVISION THAT WAS |
| SUBMITTED ON 02/12/2009 WAS P/U BY ROSE MMILLER |
| 2/26/09 REV DATED 2/12/09, READY FOR P/U W/CORR'S, |
| UNDER(A), LEFT VM MESSAGE FOR ROSE KENNEY |
| ADARROUGH |
| 2-25-09 KEVIN HATFIELD PICKUP REV (DATED 2-9-09) |
| WL |
| 02/24/09 CALLED FOR RVSD SPRINKLER PLANS TO BE |
| SUBMITTED UNDER PERMIT #08060337; LARGE BIN "B" |
| MAW |
| 02-24-09 CALLED FOR P/U OF DENIED/APPROVED |
| REVISIONS SUBMITTED 1-16-09 AND LEFT A MSG ON ROSE |
| K'S VOICE MAIL INDICATING THE REQUIREMENT FOR THE |
| RECIEPT OR BLUE CARD. "A-LARGE" KSTEVENS. |
| 2/12/09 ZONING REV LANDSCAPE PLANS $80 SEW |
| 2/9/09 FIRE SPRINKLER AS BUILTS REV # 4 $260 SLS |
| 1/16/09 REV ALL TRADES $ SPALMER |
| 12/30/08 PERMISSION GRANTED TO HANG DRYWALL ON 2ND |
| FLOOR, 1 SIDE ONLY PER RAB/AMM |
| 12/19/08 BLDG SUBMITTAL DRYWALL REQUEST LETTER SEW |
| 11-13-08 ROSE KENNEY PICKUP BLDG SUBMITTAL (DATED |
| 10-29-08) WL |
| 11-12-08 CALLED CONTRACTOR PLANS FILED UNDER |
| "A"SMALL PLANS, SPOKE WITH ROSE. JW |
| 10/29/2008 BLDG SUMBITTAL (PER JERALD SMITH) NO |
| FEE MMILLER |
| 8/15/08 ROSE P/U REVISIONS JREYES |
| 8/14/08 REVISIONS FOR BUILDING, ELECTRICAL, |
| MECHANICAL UPFRONT FOR PICK UP UNDER "A" (LARGE |
| BINS). CALLED ROSE, DV PALMER. |
| 07/28/2008 ELECTRICAL REVISION # 02 FEES $ 80.00 |
| MMILLER |
| |
| 7/21/08 BLDG/MECH/PLBG/FIRE REVISION P/U BY ROSE |
| SLS |
| 7-21-8 CALLED FOR P/U AND LEFT A MESSAGE ON ROSE'S |
| VOICE MAIL INDICATING THAT THE REVISIONS WERE |
| READY FOR P/U AND BLDG, PLMG AND FIRE APPROVED |
| WITH ELECT AND MECH. FAILING. INDICATED THAT THE |
| RECIEPT OR BLUE CARD WAS REQUIRED TO RETRIEVE THE |
| REVISIONS. "A-LARGE" KSTEVENS |
| 7/2/08 BLDG SUBMITTAL DATED 6/16 P/U BY ROSE SLS |
| 6/30/08 CALLED FILED UNDER "A" LARGE PLAN JW |
| 6/19/08 BLDG/ELEC/PLUMBING/MECH/FIRE REV AS PER |
| PLANS SEW |
| 6/16/08 BLDG SUBMITTAL SHORING 2ND & 3RD FLOORS |
| SHOP DRAWINGS MISC METALS SEW |
| 6-4-08 ROSE KENNEY PICKUP BLDG SUBMITTAL "BAR |
| JOIST" (DATED 5-15-08)& SUBMMITTAL DATED 5-29-08 |
| "DECK PLACEMENT" WL |
| 6-02-08 CALLED FILED UNDER "A" LARGE PLAN JW |
| 5/29/08 BLDG SUBMITTAL APPROVED DECK PLACEMENT & |
| STEEL STAIRS & MISC STEELS SEW |
| 5/15/08 BLDG SUBMITTAL BAR JOIST SHOP DRAWINGS NO |
| FEE SPALMER |
| 5/6/08 BLDG SUBMITTALS STEEL SHOP DRWGS & SHORING |
| CERTIFICATIONS P/U BY ROSE SLS |
| 5-06-08 CALLED CONTRACTOR AND SPOKE WITH ROSE, |
| PLANS FILED UNDER A **LARGE BIN** JW/WL |
| 4/30/08 BLDG SUBMITTAL SHORING CERTIFICATION NO |
| FEE SPALMER |
| 4-30-08 BLDG SUBMITTAL "ATTN: JERALD SMITH STEEL |
| SHOP DRAWING" NO FEE WAS CHARGED WL |
| 4-17-08 ROSE KINNEY PICKUP STRUCTURAL STEEL |
| SUBMITTAL DATED4-7-08 WL |
| 4-16-08 CALLED SUBMITTALS ARE FILED UNDER "A" |
| LARGE PLANS JW |
| 4-15-08 "3RD SET OF SHOP DRAWINGS FOR STRUCTURAL |
| STEEL REQUESTED BY JIM WITMER..ROUTED TO SAMANTHA |
| HILL" WL |
| 4/07/08 BLDG SUBMITTAL STRUCTURAL STEEL SHOP |
| DRAWINGS NO FEE SPALMER |
| 2/21/08 BLDG SUBMITTAL P/U BY ANNA SLS |
| 2-21-08 SUBMITTALS READY FOR PICK UP CALLED ROSE |
| FILED UNDER "A" SMALL PLAN JW |
| 2/13/08 BLDG SUBMITTAL MASONARY INFO ROUTED TO |
| LMARTINEZ JDS |
| 2/12/08 BLDG SUBMITTAL MASONARY INFO ROUTED TO |
| GSMITH SEW |
| 2/01/08 BLDG SUBMITTAL CONCRETE MIX DESIGN ROUTED |
| TO LUIS MARTINEZ JDS |
| 1/30/08 BLDG SUBMITTAL CONCRETE MIX DESIGN ROUTED |
| TO GSMITH SEW |
| 01/03/2008 RCVD NOC PERMIT PLUS PLANS P/U BY ROSE |
| MMILLER |
| 01-02-08 CALLED CONTRACTOR AND SPOKE TO ROSE, |
| PLANS ARE SET LOWER BINS, NEEDS NOC |
| 12/11/07 PLANS CAME BACK IN FROM PAYING IMPACT |
| FEES NO FEE SPALMER |
| 12/3/07 PLANS (4 ROLLS,LOOSE PLANS) APP, COMMENTS |
| P/U BY ANA AJP |
| 12-01-07 CALLED FOR P/U AND LEFT A MESSAGE ON ROSE |
| KENNEY'S ANSWERING MACHINE AND INDICATED THAT THE |
| PLANS WERE READY FOR PICK UP AND THAT THERE WERE |
| COMMENTS BY ADDRESSING AND IMPACT FEES TO BE PAID. |
| ALSO STATED THAT THE RECIEPT OR BLUE CARD WAS |
| REQUIRED TO RETRIEVE THE PLANS. "A-LARGE ON THE |
| FLOOR" KSTEVENS |
| 10/11/07 3RD RESUB PLANS/APP $7050 SLS |
| 9/17/07 PLANS (4 ROLLS, 3 BOOKS, 1 PKG) |
| APP/COMMENTS P/U BY ROSE AJP |
| 09/17/07 CALLED FOR DENIED PLANS P/U ON FLOOR #10 |
| MAW 08/10/07 BLDG SUBMITTAL SPECIAL INSPECTOR |
| APPLICATIONS ROUTED TO HPISKURA SEW |
| 07/23/07 RESUB $7050 FEE- PER PLAN REVIEW COMMENTS |
| FG 6-14-07 ROSE KENNEY PICKUP PLANS WL |
| 6-11-07 CALLED ROSE PLANS FILED UNDER LOWER BINS |
| ADDITIONAL FEES DUE JW |
| 3/29/07 1ST RESUB PLANS/APP NO FEE SLS |
| 2/23/07 PLANS/APP P/U BY ROSE SLS |
| 02/07/07 CALLED FOR PLANS P/U; LARGE BIN "A" MAW |