| Miscellaneous Information / Notes |
| NEW SFR - LOT 5 |
| |
| |
| |
| |
| |
| 2/20/07 DUSTIN P/U ELEC REV DATED 2/14/07 SPALMER |
| 2/18/07 ELEC REV OK,CALLED, SPOKE TO VICKI, TOLD |
| TO BRING BLUE CARD, UNDER "D' FOR PU. DV PALMER |
| 2-14-07 REV # 7 ELEC $60 WL |
| 1/5/07 DUSTY P/U REV DATED 1/2/07 SPALMER |
| 1/5/07 ELEC REV OK,CALLED, SPOKE TO BOB, UNDER "D" |
| FOR PU. DV PALMER. |
| 1-2-07 REV #6 ELEC PER D PALMER INCREASE LOW |
| VOLTAGE VALUE ONTO BLD-RES PERMIT ADDTL $12,000.00 |
| FOR WIRING AND SPEAKERS ONLY (PLAN REVIEWER |
| INCREASED VALUE OF HOME ON 8-24-05 TO 423,089.00 |
| BUT DID NOT INCREASE VALUE ON 1ST RESUB..CORRECTED |
| THAT VALUE) TOTAL FEES DUE $202.53 WL |
| 1/2/07 DUSTY P/U DENIED REV DATED 12/14/06 |
| SPALMER |
| 12/18/06 ELEC REV UNSAT,CALLED AND LEFT MESSAGE ON |
| VICKI'S VM AS SHE HAD CALLED. THE VM CUT OFF IN |
| MID-STREAM, HOWEVER TOLD PLANS WERE OUT FRONT TO |
| BE CORRECTED.** SEE NOTE ENTERD BY MIRELLE FROM |
| 12/15 DV PALMER |
| 12/15/06 CALLED CUSTOMER TO INFORM THEM THAT THEY |
| LEFT THEIR BLUE CARD BY THE CASHIER'S DESK IF ANY |
| QUESTIONS WHEN READY FOR P/U IN CASE CUSOTMER DOES |
| NOT HAVE BLUE CARD I MIRELLE MILLER HAVE THE BLUE |
| CARD AT MY DESK THANK YOU MMILLER |
| 12/14/06 ELECTRICAL REVISION FEES $ 60.00 |
| MMILLER 5/22/06 COU PU BY DUSTIN SEW |
| 5/22/06 PU BY DUSTIN SEW |
| 5/15/06 ELEC REV $60 SEW |
| 3/31/06 BLDG |
| REV. P/U BY DUSTIN AJP |
| 3/28/06 BLDG REV OK/CALLED/UNDER 'D' RM |
| 3-22-06 REV #2 ELEC $60 & REV #3 BLDG $60 WL |
| ************************************************** |
| ************************************************** |
| 8/24/05 DENIED/CALLED/UNDER 'D' RM |
| 8/29/05 DUSTIN P/U DENIED PLANS SPALMER |
| 9-23-05 1ST RESUB DA |
| 10/5/05 DENIED/CALLED/UNDER 'D' RM |
| 10/6/05 PLANS + APP P/U BY DUSTIN PT |
| 10-19-05 2ND RESUB $451.76 NFL |
| 11/9/05 DENIED BY ELEC/CALLED/UNDER 'D' RM |
| 11/15/05 PLANS PICKED UP BY DUSTIN TO GET NEW ELEC |
| SHEETS, OK, TO COME BACK IN W/OUT A RESUB FEE. |
| DVP. |
| 11/23/05 3RD RESUB NO FEE PER DVP SPALMER |
| 11/30/05 READY TO ISSUE PERMIT, FEES MUST BE PAID, |
| . PLANS UNDER "D" FOR PU,CALLED. DV PALMER |
| 12/09/05 DUSTIN P/U PERMIT SPALMER |
| 01/18/06 MECHANICAL REVISION $60 FEE FG |
| 1-26-06 P MECH. REV. P/U BY ED. |