| Miscellaneous Information / Notes |
| VIBRO FLOTATION, AUGER CAST PILE, PILE CAPS & |
| SPREAD FOOTINGS NO SLAB WORK, |
| |
| |
| 2-4-2013 REVOKED PERMIT; STRUCTURE DEMOLISHED - |
| SEE 10050758 - ENTIRE BLOCK - DRF |
| |
| |
| 11/16/07 PERMIT EXTENSION TO 2/13/08 HHP |
| 11/9/07 CHANGE OF CONTR $100 NOC NEEDED BEFORE |
| INSPECTIONS SEW |
| 8/21/07 EXTENSION TO 11/15/07 HHP |
| 5/21/07 EXTENSION TO 8/17/07 SEE NOTES HHP |
| 2/23/07 EXTENSION TO 5/19/07 HHP |
| 1/23/07 EXTENSION GRANTED FROM 11/20/06 HHP |
| 1/19/07 VOID PERMIT. NO WORK STARTED.KC |
| 8/21/06 SPOKE TO DFULCHER HAD REC'D FAX REQUESTING |
| AN ADD'L EXT OKAY FOR PERMIT EXT TO 11/15/06 SEW |
| 5/22/6 PERMIT EXT PER NEIL MELICK TO 8-16-06/AMM |
| ********************************************* |
| 5/26/5 1ST RESUB NO FEE FG |
| 6/06/05 CALLED CONT PLANS FILED UNDER "D" JW |
| 6-7-05 MARGRET P/P PLANS DA |
| 7-8-05 RECEVD CHANGE OF CONTR LTR DA |
| 7-29-05 CHG PERMIT TYPE TO MISC NO FIRE REVIEW FEE |
| SHOULD HAVE BEEN CHARGED PER J WITMER REFUND FOR |
| FIRE REVIEW DUE TO CONTRACTOR WL |
| 7-29-05 MARGARET SCHALLENBERG BROUGHT IN DUPL OF |
| ORIG COPY OF CHG OF CONTRACTOR PERMIT APPL THAT |
| WAS LEFT OUT OF CHG OF CONTR DONE BY DEBBIE |
| ALVAREZ ON 7-8-05 & SUBMITTED SUBMITTALS REQUESTED |
| BY J WITMER MARGARET ONLY HAD COPY OF CHG OF CONTR |
| LETTER ENCLOSED IN PKG WE ARE TO FIND ORIG BROUGHT |
| IN BY D ALVAREZ WL |
| 7/31/05 PLANS FILED UNDER "C" JW |
| 8/1/05 MARGARET P/U PERMIT SPALMER |
| 10-14-05 REV DA |
| 12-01-05 CALLED FILED UNDER "C" JW |
| 12/2/05 REV/BLDG P/U BY MARGARET PT |
| 2/13/06 EXT PERMIT UNTIL 5/16/06 PER NM/AM |
| |
| |
| |
| 12-01-05 CALLED FILED UNDER "C" JW |