| Miscellaneous Information / Notes |
| CONSTRUCTION OF CITYSIDE CLUBHOUSE |
| |
| |
| |
| |
| 9/7/06 ROSE P/U RESTAMP SPALMER |
| 9-6-6 CALLED FOR P/U PLMG RESTAMP "A" KSTEVENS |
| 8/15/06 PLUMBING REV. P/U BY ROSE AJP |
| 8-15-6 CALLED FOR P/U PLMG REV. "A" KSTEVENS |
| 8/3/06 CUST PAID FOR RESTAMP OF PLANS. $25 TA |
| 6/22/06 PU BY ROSE SEW |
| 6/22/06 CALLED FILED UNDER "A" JW |
| 6/19/06 BLDG REV POOL SLAB FOR EQUIP $60 SEW |
| 6/19/06 CHRIS P/U REV SPALMER |
| 6/19/06 CALLED FILED UNDER "W" JW |
| 6/16/06 BLDG REV FOR POOL EQUIPMENT SHELTER READY |
| TO BE P/U BY DAISY(W) ADARROUGH |
| 6/12/06 DAISY P/U REV & TURNE IN NOC SPALMER |
| 6-10-6 CALLED FOR P/U "W" KSTEVENS |
| 6/1/06 PLUMBING REVISION SLS |
| 5/18/06 BLDG/ELEC REV $90 SEW |
| 5/11/06 REV.(APPROVED EL/PLBG/MECH, DENIED FIRE) |
| P/U BY ROBERT AJP |
| 5/2/06 MOVED TO LARGE PLAN BIN "W" AJP |
| 5-2-6 CALLED FOR P/U "W" KSTEVENS |
| 4/5/06 ELEC/PLUMB/MECH REV $110 FEE CHG TA |
| ************************************************** |
| ************************************************** |
| 03-16-05 DENIED UNDER "W" NAM |
| 3/17/05 PLANS ROUTED BACK TO JWITMER |
| ADARROUGH |
| 3/21/05 BRIAN P/U DENIED PLANS SPALMER |
| 3/22/05 PLANS FILED UNDER 'W' LM |
| 3-24-5 PLANS PU/BRIAN R - KAM |
| 5/5/05 1ST RESUB NO FEE SPALMER |
| 6-16-5 CALLED FOR P/U "W" KSTEVENS |
| 6/16/5 P/U BY BRIAN FG |
| |
| |
| 6/29/5 2ND RESUB FEE $692.23 FG |
| 7/29/05 BRIAN P/U DENIED PLANS SPALMER |
| 8-8-5 3RD RESUB FEE - $692.23 - KAM |
| 8/8/05 REVIEW ON HOLD FOR LACK OF PAYMENT, PLANS |
| FILED UNDER 'W' LM |
| 8/10/5 3RD RESUB PAID/PLANS ROUTED TO INCOMING FG |
| 10-19-5 CHANGE OF CONTR-$100 - KAM |
| 11/09/05 LETTER RECV'D CHANGED SUB CONTRAC $50 FEE |
| FG |
| 12/16/05 CALLED/PRODUCT APPROVALS/UNDER 'W' RM |
| 12/20/05 CHANGE OF SUB CONTRACTOR MECH $50 FEE FG |
| 12/28/05 PLANS P/U BY BRIAN AJP |
| 2-17-06 REV #1 ELEC/PLUMB/MECH $150 WL |