| Miscellaneous Information / Notes |
| NORTH BLDG# 1, (4) UNIT CONDO |
| |
| |
| |
| 4/22/10 BILL P/U CO. RB |
| 3/1/10 BILL P/U TCO SPALMER |
| 2/25/10 ADDED TCO FEE. CALLED DENVILLE TO P/U TCO. |
| IN CO BOX UNDER 'T'. RB |
| 2/24/10 CHANGED ADDRESS ON PERMIT RECORD FROM 2010 |
| TO 2018 PONCE DE LEON AVE FOR THIS BUILDING. |
| ADDRESS FOR THE SOUTH BUILDING RB |
| 10/14/09 REV PU BY DENVILLE SEW |
| 10/14/09 LANDSCAPE REVISION UNDER *T* (SMALL BINS) |
| READY FOR PICKUP. TWO IN ONE PACKAGE, OTHER FOR |
| PERMIT # 04120945. CALLED AND SPOKE TO DENVILLE |
| REMINDING OF BLUE CARDS. DV PALMER |
| |
| |
| 10/5/09 LANDSCAPE REV CHANGES FROM ORIGINAL |
| DRAWINGS $110 SEW |
| |
| 6/17/08 PU BY DENVILLE SEW |
| 6-04-08 FILED UNDER "T" SMALL PLAN OWES FEES UNDER |
| PERMIT 04120945 JW |
| 6/4/08 BLDG REVISION # 19 $70 SLS |
| 3-12-08 DENVILLE DEACON PICKUP BLDG REV & RESTAMP |
| WL |
| 3-10-08 CALLED CONTRACTOR AND SPOKE WITH TIM PLANS |
| FILED UNDER "T" SMALL PLAN. JW |
| 3/6/08 BLDG REV UL ASSEMBLY FOR 6" WALL BETWEEN |
| GARAGE & LIVING AREA CORRECT MANUFACTURE FOR |
| WINDOWS & SLIDING DOORS CHGS TO A/C CLOSET DOORS |
| FROM WOOD TO METAL DETAIL FOR GABLE VAULETED |
| CEILING $90 SEW |
| 03/04/2008 APPROVED MECHANICAL REVISION THAT WAS |
| SUBMITTEDON 02/28/2008 WAS P/U BY DENVILLE |
| MMILLER |
| 2-29-08 P MECH/REV. CALLED TIM P/U "T" TG. |
| |
| 2/28/08 BLDG SUBMITTAL RESTAMP PRODUCT APPROVALS |
| $25 SEW |
| 2/28/08 MECH REV AS BUILTS $60 SEW |
| 11/29/07 RE-STAMPED PLANS P/;U BY KATE AJP |
| 11-08-07CALLED FILED PLANS UNDER "W" LARGE PLAN |
| JW |
| 11-6-07 RESTAMP $25 "THE SITE DRAWINGS WERE LOST & |
| WE NEED A RE-STAMP ON WORKING SITE PLANS"**2 |
| SETS**ROUTED DIRECTLY TO JIM WITMER WL |
| 08/17/07 PER A MCKENZIE OK TO CHANEG CONTRACTOR |
| $100 FEE W/ ATTACHED LETTER FG |
| 8/16/07 SEE NOTES HHP |
| 5/15/07 SEE NOTES HHP |
| |
| |
| |
| |
| |
| 2-8-07 P MECH/REV. P/U BY BOB TG. |
| 1/31/07 MECH REV AS BUILTS $70 SEW |
| 8/17/06 APPROVED PLUMBING REV. P/U BY LORI AJP |
| 8-15-6 CALLED FOR P/U PLMG. REV. "T" KSTEVENS |
| 7/20/06 BLDG (STAIR) REV. P/U BY LORI AJP |
| 7-20-06 CALLED STAIR REV FILED UNDER "T" JW |
| 7/18/06 BLDG REV ENERGY CALCS $60 SPALMER |
| 7/18/06 BLDG REV STAIRWAY LANDING $60 SPALMER |
| 7-13-06 LORI STEELE PICKUP BLDG/ZONING REV WL |
| 7-13-06 CALLED FILED UNDER "T" JW |
| 7/5/06 RETURNED (APPROVED)PLANS TO INCOMING FOR |
| FURTHER PROCESSING MM |
| 7/5/06 ROUTED TO ERIC S, PPLANNER 822-1435 MM |
| 6/23/06 BLDG REV FENCE SEW |
| 6/23/06 PLUMBING REV P3 VENTING ISOMETRIC SEW |
| 6/16/06 LORI P/U REV SPALMER |
| 6-15-06 F MECH/REV. TO E-CAL'S CALLED LORI P/U "T" |
| TG. |
| 6/15/06 CALLED FILED UNDER "T" JW |
| 6/13/06 LORI P/U DENIED PLUMB REV SPALMER |
| 6/12/06PLBG REV DENIED UNDER "T" JHL |
| 6/8/06 BLDG REV FLORIDA ENERGY EFF. TA |
| 6/8/06 PLUMB REV REV DW6, P2, P3. TA |
| 5/16/06 REV P/U BY LORI STEELE FG |
| 5/12/06 REV/PLBG DENIED CALLED FOR P/U UNDER "T" |
| MRPERSON |
| 5/4/06 REV/PLUMB $70 PT |
| 4/14/06 REV. P/U BY TOM AJP |
| 4/10/06 FIRE REV $60 SEW |
| 4/3/06 CALLED FILED UNDER "T" JW |
| 3/23/06 BLDG REV DRAWINGS SUBMITTED FOR PERMITS |
| 04120942 & 04120945 FEE CHG $70//OK TO ACCEPT DUE |
| PER RB TA |
| ************************************************* |
| 3/23/06 BLDG REV SUBMITTED FOR PERMIT 04120942 & |
| 04120945//1 FEE CHG $80 OK PER RB DUE TO 1 SET OF |
| PLANS REV BY JW. TA |
| *********************************************** |
| UNITY OF TITLE IS BEING FILED DO NOT PRINT UNTILL |
| SUBMITTED |
| 1-26-05 DENIED CALL TO P/U UNDER "T" MJACOBS |
| 2/2/05 STEVEN P/U DENIED PLANS SPALMER |
| 5-16-05 POSSIBLY 1ST RESUB - SHOWS IN INCOMING ON |
| 5-16-05 - KAM |
| 5-21-05 CALLED FOR P/U PLANS IN BOX T HM. |
| 6-22-05 STEVE P/U PLANS NFL |
| 7-5-05 2ND RESUB DA OWES $ 606.87 |
| 7/13/05 AMY P/U PLANS TO PAY IMPACT FEES SPALMER |
| 7-25-05 RESUB FOR IMPACT FEES (NO FEES)PLANS FROM |
| IMPACT FEES DATE STARTS 7-25-05 FOR REVIEWS NO |
| ELECTRICAL TO REVIEW THIS ROUND D. PALMER/DA |
| 8-23-05 CALLED FOR P/U BOTTOM SHELF UNDER T PHK |
| 8-23-05 ALLISON P/U ALL DOCS & CORR DA |
| 8/25/05 PLANS WERE RETURNED FOR PLUMBING REVIEW, |
| PLANS ARE WITH KEN STEVENS LM |
| 8-26-5 CALLED FOR P/U "T" KSTEVENS |
| 8/30/05 THOMAS BROWNE P/U DENIED PLANS SPALMER |
| 09/07/5 RESUB |
| 9-27-05 FILED UNDER LOWER BINS JW |
| 9/30/05 P/UPERMIT THOMAS/AM |
| 10-3-5 BLDG REV $90 - KAM |
| 10-13-5 BLDG REV $100 - KAM |
| 10-19-05 REV # 3 PROD APPROVALS PER L MARTINEZ |
| $110 WL |
| 11/23/05 PLANS P/U BY ALISON AJP |
| 12/8/05 REV $100 SPALMER |
| 12/9/05 GIVEN TO PLANNING & ZONING 822-1435 MM |
| 12/9/05 APPROVED MM |
| 12/9/05 WALL REVISION FILED UNDER 'T' LM 12/12/05 |
| SITE WALL REV. P/U BY TOM BROWNE AJP 12-19-05 |
| CALLED REV FILED UNDER "T" JW |
| 12/27/05 REV KP/U BY TOM AJP |
| 01/18/06 BLDG REV $150 FEE FG |
| 2-06-06 CALLED FILED UNDER T JW |
| 2/6/06 REV. P/U BY ALISON AJP |