| Miscellaneous Information / Notes |
| CONDOMINIUM PROJECT 3 LEVELS OVER PARKING - 25 |
| UNITS - BLDG # 4 & 5 |
| |
| |
| |
| |
| 5-21-07 KEN TORRES PICKUP BLDG REV WL |
| 5/21/07 CALLED KEN TORRES FOR P/U OF REVISION AND |
| SUBMITTAL FOR MULLIONS, SGD'S AND SH WINDOWS. |
| LARGE BINS.'T'. RB |
| 5/18/07 BLDG REV LETTER TO ADDRESS REV #15 SEW |
| 05/04/04 BLDG REV $60 FEE-FG |
| 4-26-07 BLDG #10 KEN TORRES PICKUP BLDG REV WL |
| 04-18-07 CALLED FILED UNDER "T" LARGE PLAN JW |
| 04/13/2007 BLDG REVISIONS FEES $ 60.00 MMILLER |
| (REVISION PRODUCT NOA) |
| 3/26/07 HILARY P/U REV DATED 3/14/07 SPALMER |
| 3-17-07 CALLED FILED UNDER (FEES OWED INVOICE |
| ATTACHED) **LARGE BINS** "T" JW |
| 3/14/07 BLDG SUBMITTAL OVERHEAD GARAGE DOOR (BLDG |
| #1-6)SEW |
| 3/9/07 LETTER SUBMITTED FOR MECH INSP FOR 3/10/07 |
| SATURDAY PM $300 ROUTED TO HMOSER SEW |
| 3/8/07 LETTER SUBMITTED FOR MECH INSP FOR 3/10/07 |
| SATURDAY AM $300 ROUTED TO HMOSER SEW |
| 3/8/07 SAM P/U REV DATED 1/31/07 SPALMER |
| 3/8/07 MECH/ELEC REV CALLED FOR P/U LG BIN UNDER |
| 'W' RJR |
| 2/28/07 SAM P/U REV DATED 2/15/07 SPALMER |
| 2/26/07 CALLED PUT OUT FRONT **LARGE BINS**"W" JL |
| 2/15/07 ELEC REVISION $70 SLS |
| 1/31/07 MECH REVISION $110 SLS |
| 1/30/07 MECH REV CALLED FOR P/U LARGE BIN UNDER |
| 'W' RJR |
| 12/22/06 TOM P/U 6 REV DATED 12/15/06 SPALMER |
| 12/22/06 PUT OUT FRNT UNDR "W" CALLED TOM JL |
| 12/15/06 MECH REV SHT M-207 BLDG 5 SEW |
| 12/15/06 ELEC REV SHT E-207 BLDG 5 SEW |
| 12/15/06 ELEC REV SHT E-503 SEW |
| 12/7/06 TOM P/U REV DATED 11/22/06 SPALMER |
| 12/6/06 ELEC REV FROM 11/22 UNDER "T" FOR |
| PU,CALLED, SPOKE TO TOM. DV PALMER. |
| 11/22/06 ELECTRICAL REV $60.00 MMILLEER |
| 11/16/06 TOM P/U REV DATED 11/13/06 SPALMER |
| 11/13/06 ELECTRICAL REV $ 70.00 MMILLER |
| 11/8/06 PU BY DON WOODS SEW |
| PUT REVISIONS OUT FRONT **LARGE BINS** "T" CALLED |
| JL |
| 10/23/06 NEW NOC SUBMITTED SEW |
| 10/20/06 MIKE PICKED UP PLANS LM |
| 10/6/06 ELEC REV BLDG 4/5 RISER SEW |
| 8/1/06 APPROVED MECH REV( CUST. REF "MECH PLAN |
| M-208,REV. 12, DATED 7/17/06) P/U BY TOM AJP |
| 7/28/06 CALLED FOR P/U PLANS IN BOX T HM. |
| 7/21/06 EL. REV. P/U BY TOM AJP |
| 7/21/06 CALLED FOR P/U "T" MRW |
| 7/19/06 FIRE REV PLANS P/U BY TOM SLS |
| 7/19/06 MECH REVISION $60 SLS |
| 7/17/06 FIRE REV DRAWINGS/PROD APPROVALS SEW |
| 7-13-06 BOB CERVIERI PICKUP BLDG/ELEC/PLUMB/MECH |
| REV WL |
| 7/12/06 CALLED FOR P/U PLANS IN BOX T UP FRONT HM. |
| 6/30/06 MECH REVISION $80 SLS |
| 6/30/06 (3) REV PU BY TOM SEW |
| 6/29/06 ELEC REV'S OK,UNDER **LARGE BINS** "T" FOR |
| PU. CALLED, LEFT MESSAGE. DV PALMER |
| 6-28-06 MECH REV GIVEN TO H. MOSER PHK |
| 6-23-06 CALLED FILED UNDER "T" LARGE PLAN JW |
| 6/23/06 MECH REV M-206/BLDG 4 |
| 6/15/06 ELEC REV BLDG 4 $60 SEW |
| 6/8/06 MECH/PLBG REVISION $90 SLS |
| 6/8/06 ELEC REVISION $60 SLS |
| 5/3/06 PU BY HILARY SEW |
| 5/3/06 MOVED TO LARGE PLAN BIN "T" AJP |
| 5-03-06 CALLED FILED UNDER "T" JW |
| 5/1/06 SUBMITTAL SHORING LETTER BLDG #5 LEVEL #4 |
| SEW |
| 5/1/06 SUBMITTAL SHORING LETTER BLDG #5 ROOF SEW |
| 4/24/06 TWO DENID BLDG SUBMITTALS P/U BY IVY AJP |
| 4/20/06 REV $80 FEE PERMIT-04110184-04110183- |
| 04110185-04110182 FG |
| 4/5/06 BLDG REV. P/U BY TOM AJP |
| 4-04-06 CALLED FILED UNDER "T" JW |
| 3-31-06 NO FEE BLDG SUBMITTAL "OVERHEAD GARAGE |
| DOORS TYPICAL FOR BLDG #1-6" WL |
| ************************************************** |
| *DO NOT ISSUE UNTIL UNITY OF TITLE * |
| 12-31-04 CALLED FOR P/U 3ROLLS AT BOTTOM SHELF |
| PHK |
| |
| 1/5/5 PLANS P/U BY KERRY W DR |
| 1/19/05 1ST RESUB NO FEE PSMITH |
| 1/24/05 CHANGE OF CONTRACTOR $100 (FROM MANHATTAN) |
| TO THE WEITZ PT |
| 1/26/05 SUB/ALTERNATE DRYER EXHAUST FAN GIVEN TO |
| NEIL PT |
| 02-28-05 CALLED FOR P/U NAM |
| 3/1/05 UNDER "M" ROLLS AND 1BOX ADARROUGH |
| 3-2-05 LARRY P/U PLANS NFL |
| 4-15-5 2ND RESUB - $5650 - KAM |
| 4-26-05 SUB BLDG LTRS DA |
| 5-12-05 SUBMIT DUPL PERMIT APPL REQUESTED BY JIM |
| WITMER...PER DEAN RUNNELS OK TO ADD SUBS AT THIS |
| TIME & CHG $50 SUB FEES PER SUBCONTRACTOR WL |
| 5/27/05 PERMIT P/U BY JEFF PT |
| 5/27/05 SUB/BLDG P/U BY JEFF PT |
| 6/2/5 SUMITTAL/SURVEY NO FEE FG |
| 6-3-05 REV $100 DA |
| 6-16-05 CALLED CONT FILED UNDER "T" JW |
| 6-20-05 JEFF P/U REV NFL |
| 6-23-5 CALLED FOR P/U PLMG. REV. "T" KSTEVENS |
| 6-23-05 JEFF P/U REV NFL |
| 7/26/5 PLUMING REV P/U BY JEFF FG |
| 8-10-05 FORM BOARD SURVEY (SUBMITTAL) DA |
| 8/18/5 BLDG SUBMITTAL NO FEE FG |
| 8-28-05 CALLED, FILED UNDER "T" JW |
| 9-7-05 SUBMITTAL (3) DA |
| 9-8-05 SUBMITTAL DA |
| 9/16/05 REV/ELEC PLUMB MECH $650 PT |
| 9-26-5 SUBMITTAL - NO FEE - KAM |
| 10-12-05 SUBMITTAL BLDG #4 DA |
| 10-12-05 SUBMITTAL BLDG # 5 DA |
| 10-12-05 SUBMITTAL BLDG #1 DA |
| 10-12-05 SUBMITTAL BLDG # 4 DA |
| 10-12-05 SUBMITTAL BLDG # 5 DA |
| 10-12-05 SDUBMITTAL BLDG # 5 DA |
| 10-13-5 SUBMITTAL TO HAROLD PISKURA - KAM |
| 10/14/05 DENIED SHORING LETTER CONT CALLED HHP |
| 10/14/05 SYLVANNA P/U DENIED LETTER SPALMER |
| 10/14/05 SUBMITTAL TO HAROLD PISKURA SPALMER |
| 11/10/05 SUBMITTAL MECHANICAL EQUIP. NO FEE |
| 11-17-05 BLDG SUBMITTAL BLDG #4 LEVEL 3 FLOOR POUR |
| SHORING LTR WL |
| 11/21/05 SUB/BLDG (ELEVATION CERTIFICATE BDG #5) |
| PT |
| 11/28/05 SUBMITTAL BLDG 5 LEVEL 2 SHORING LTRS |
| SPALMER |
| 12/15/05 SUBMITTAL NO FEE ROUTED TO K CONRAD FG |
| 12-29-05 NO FEE SUBMITTALS BLDG 4 TRUSSES ALSO |
| APPLIANCE SUBMITTAL/ BLDG 5 LEVEL 3 SHORING MECH |
| SKETCHES/ FIRE- PROOFING/WINDOW SHOP DIANE WAS |
| ASKED TO INITAL DATE CHGS & FILL IN ALL BLANKS.. |
| DID NOT COMPLETE SUBMITTAL FORM & DID NOT INITIAL |
| ALL CHGS WL |
| 1-5-06 REV/MEP'S/FIRE CALLED FOR P/U BOTTOM SHELF |
| FOUR ROLLS OF PLANS PHK |
| 1-13-06 BLDG/ELEC/MECH SUBMITTALS FOR BLDG 4 & 5 |
| WL |
| 01/17/06 BLDG SUBMITTAL NO FEE FG |
| 1/17/6 SUBMITTALS TO JAH DESK SMH |
| 1-17-06:CALLED CONTR 4 PU, DENIED, UNDER W. JAH |
| 1/20/06 SUBMITTAL TO JAH DESK SMH |
| 1-22-06:CALLED CONTR 4 PU, UNDER W. JAH |
| 1/26/6 CORR, FEES DUE, CALLED CONTR, BIN 'THE |
| WEITZ COMPANY' SMH |
| 1/26/06 SUBMITTAL SHORING COMPLIANCE LTR BLDG 4 |
| LEVEL 4 POUR SPALMER |
| 1/27/06 ALL PLANS/APPS P/U BY DIANE AJP |
| 2-7-06 SUBMITTAL TO HHP BY RB NFL |
| 2/8/6 BLDG SUBMITTAL TO JAH DESK SMH |
| 2/8/06 SUBMITTAL PU BY TOM SEW |
| 2-9-06:CALLED CONTR TO PU BLDG. SUBMITTALS. JAH |
| 2-14-04 SUBMITTEL FROM 1-13-06 DRY-IN-PLANS P |
| CALLED FOR P/U "T" TG. |
| 2/16/6 SUBMITTAL OK, CALLED CONTR, 'T' SMH |
| 2/21/06 DIANE P/U SUBMITTALS SPALMER |
| 2/21/06 SUBMITTAL LTR NO FEE SPALMER |
| 2/28/06 SUBMITTAL SHORING LTR BLDG 5 LEVEL 4 |
| SPALMER |
| 3/1/6 TO JAH DESK SMH |
| 3-1-06:CALLED CONTR TO PU SHOR LTR SUBMITTAL. "T" |
| JAH |
| 3-1-06:CALLED CONTR TO PU DENIED SHOR LTR |
| (DIFFERENT THAN ABOVE LETTERS.) "T" JAH |
| 3/14/6 TO JAH DESK SMH |
| 3-1-06:CALLED HILLARY TO PU DENIED SHOR LTR. "T" |
| JAH |