| Miscellaneous Information / Notes |
| SINGLE FAMILY RESIDENCE |
| LOT 2 |
| |
| |
| |
| |
| |
| 5/25/06 PU BY SHELDON SEW |
| 5/24/06 ELEC REV UNDER "S"./WRT. |
| 5/24/06 ELEC REV $60 SLS |
| 5/12/06 PU BY SHELDON SEW |
| 4/26/06 ELEC REV OK, CALLED, LEFT MESSAGE, UNDER |
| "S" FOR PU. DVPALMER. |
| 4/21/06 ELEC REV $60 SEW |
| 4/3/06 DENIED EL. REV.PLANS/APP P/U BY BRIAN AJP |
| 4/3/06 ELEC REV UNSAT,CALLED LEFT MESSAGE,UNDER |
| "S" FOR PU. DV PALMER |
| 3-31-06 REV # 4 ELEC $60 WL |
| ************************************************** |
| ************************************************** |
| 9/21/04 UP FRONT 'S' CALLED CONTRACTOR FAILED ELEC |
| MECH & BLDG. LS |
| 9/22/04 SHELDON P/U DENIED PLANS SPALMER |
| 9-24-04 1ST RESUB NFL |
| 10/12/04 UP FRONT 'S' FAILED MECH LS CALLED CONT |
| 10/18/04 PLANS + APP P/U BY SHELDON PT |
| 10/21/04 UP FRONT 'S' FEES DUE LS |
| 10-21-4 PLANS PU/SHELDON FOR IMPACT FEES - KAM |
| 10/21/04 UP VALUE $703.67 BZ247132 SPALMER |
| 10-21-4 IMPACT FEES PD-KAM |
| 10-28-4 PERMIT PU/SHELDON - KAM. |
| 12/5/05 ELEC REV TO BT./WRT. |
| 12/5/05 ELEC REV UNDER "S"./WRT. |
| 12/8/05 SHELDON P/U ELEC REV SPALMER |
| 12/14/05 2ND REVISION $60 FEE, GIVEN TO BTROBAUGH. |
| LTM |
| 12/14/05 ELEC REV TO SHELDON./WRT. |
| 2/2/06 ELEC REV $60 SPALMER |
| 2/9/06 ELEC REV UNSAT,CALLED, UNDER "S'FOR PU. DVP |
| 2/17/06 SHELDON PICKED UP REVISION |