| Miscellaneous Information / Notes |
| CONSTRUCTION OF CHRISTIAN SCHOOL |
| |
| WORK TO BE COMPLETED ON PERMIT 05070334 HHP |
| |
| 4-18-03 LEFT MSGE TO P/U UNDER'D'.SHERNANDEZ |
| 4-21-03 PLANS PU TJ |
| 5-1-03 1ST RESUB NFL |
| 5/20/03 PASS ZONING MM |
| CALLED FOR P/U 6-4-3 "D" KSTEVENS |
| DONALD BROWN PICK UP PLANS 6-5-03 WL |
| 2ND RESUB - $925 BZ#227812 7-15-03 KAM |
| PLEASE SEE BZ ATTACHED FOR 4X FEE ADDED PER FS |
| 553.80(2)(B). TO BE PAID BEFORE SUBMITTING FOR |
| NEXT REVIEW. BZ# 228657 $11,100.00 7/30/03 DV PALM |
| CALLED TO P/U "D" ALANGE |
| DENIED PLANS P/U DONALD 8/20/03 SPALMER |
| RESUB #3 $925 BZ 231179 (ROLLED PLANS) 9-19-03 WL |
| 10-3-03 CALLED FOR P/U UNDER D PHK |
| 10/8/03 PERMIT PU JOHNNY PSMITH |
| 11/12/03 SUBMIT LETTERS JW |
| 11/12/03 CALLWD CONT LETTERS FILED UNDER "D" JW |
| 12/29/03 BLDG SUBMITTALS NO FEE PSMITH |
| 01-07-04 CALLED CONT PLANS FILED UNDER "D" JW |
| 2/18/04 (2) BLDG SUBMITTAL P/U DON PSMITH |
| 4/20/04 SUBMITTAL CHANGE OF A/C DRAWINGS SPALMER |
| 5-5-04 MECH SUBMITTAL CALLED FOR P/U UNDER D PHK |
| 5-18-4 SUBMITTAL PU/DON - KAM |
| 5/18/04 SUBMITTAL LTRS NO FEE SPALMER |
| 5/20/04 CALLED CONT PICK UP DETAIL FILED UNDER"D" |
| 5/26/04 REV MECH $140 BZ230648 SPALMER |
| 5-28-04 MECH REV CALLED FOR P/U UNDER D PHK |
| 6/4/04 DONALD P/U REV SPALMER |
| 6/30/04 SUBMITTAL BLDG LTR NO FEE PSMITH |
| 7-1-04 CALLED TO PICK UP , SUBMITTAL AL |
| 7/23/04 BLDG SUBMITTAL LTRS NO FEE PSMITH |
| 7/23/04 ELEC REV $80 BZ244162 PSMITH |
| 7/23/04 BLDG SUBMITTAL P/U DON PSMITH |
| 7-26-04 CALLED TO P/U SUBMITTAL "D" ALANGE |
| 7/28/04 ELEC REV UNDER'D'CALLED,LEFT MESS.DV PALME |
| 8-2-4 ELEC REV PU/DONALD - KAM |