| Miscellaneous Information / Notes |
| OFFICE RENOVATION |
| |
| |
| |
| 6/21/06 ROBERT P/U 2 REVS SPALMER |
| 6/20/6 REV OK, CALLED CONTR L/M, 'J' SMH |
| 6/15/06 BLDG REVISION $80 SLS |
| 6/13/06 ROBERT P/U DENIED PLANS SPALMER |
| 6/7/6 CORR REV, CALLED CONTR, 'J' SMH |
| ************************************************ |
| ************************************************ |
| 4/7 SENT TO FIRE, NOT ON BOARD HHP |
| 10/22/03 CKLST CALLED MILLAR FILED "L" HHP |
| CALLED FOR P/U 12-10-02 UNDER "L" PHK |
| 1/15/03 CHUCK PICKED UP PLANS LM |
| 2/27/03 2ND PLAN CHECK BZ# 220198 $100 MM |
| PLANS SUBMITTED ON 2/27 ARE UNDER"L " FOR PU,NEEDS |
| TO COME BACK WHEN SETS ARE COMPLETED. DV PALMER. |
| 10-23-3 CALLED FOR P/U "L" KSTEVENS |
| 10/28/03 CHUCK P/U PLANS.SH |
| 3/8/04 3RD PLAN CHECK/$200/BZ#238488.SH |
| 4/14/04 PLANS FILED UNDER 'L' LM |
| 4/15/04 PLANS PICKED UP BY ARCH. LM |
| 6/16/04 CHNG FROM PROJ TO PERMIT $1598.40BZ242340 |
| 6/16/04 NO SUBS ON BACK OF APPLICATION SPALMER |
| 7-6-4 CALLED FOR P/U "J" KSTEVENS |
| 7/6/04 PLANS P/U TO PAY IMPACT BY JAMES H DR |
| 7/15/04 1ST RESUB/NC PLANS + APP PT |
| 7/20/4 ISSUED, CALLED CONTR, 'J' SMH |
| 7-20-4 PERMIT PU/JAMES - KAM |
| 9/20/4 RESPONSE TO FAX FROM SLA, FAXED TO |
| ARCHITECT SMH |
| 1-11-05 PERMIT EXTENDED UNTIL 4-20-05 PER LETTER |
| FROM NEIL MELICK - KAM |