| Miscellaneous Information / Notes |
| BLDG #1 - ADMIN BLDG - 2 STRY CMU/PIP CONCRETE |
| W/STRUCTURE STEEL DECK SYS |
| |
| 1-13-03. DENIED. CALLED STILES FOR P/U. 'S'. RB |
| DENIED PLANS P/U RICHARD 1/17/03 SJOHNSON |
| *PLEASE NOTE: WHEN PLANS RETURN THEY GO UNDER 2ND |
| PLAN CHECK $100 PER PERMIT NUMBER |
| PLAN CHECK $100 BZ#220695 3-13-03 KAM |
| 4-25-03 CALLED FOR P/U UNDER 'S',PLANS NEXT TO |
| CONF.ROOM.SHERN. |
| 5-1-03 RESUB AS PERMIT APPLIC $9945.60 BZ223966.RB |
| CHANGED FROM PLANA CHECK TO PERMIT 5-1-03 KAM |
| 6-25-03 APPLIC & PLANS TO P/U,ON RACK NEXT TO CONF |
| ROOM, CALLED LEFT MSGE.SHERNANDEZ |
| 1ST RESUB - NO FEE 9-10-03 KAM |
| 11-3-03 CALLED FOR P/U. ON PLAN REVIEW RACK. RB |
| 2/6/04 2ND RESUB BZ237139 PSMITH |
| 3-4-04 SHEETS NEED LICENSE # CALLED FOR P/U. PLANS |
| ON PLAN REVIEW RACK. RB |
| 4-27-04 MET RICHARD BLUESTEIN TO GO OVER ITEMS |
| REQ'D FOR PERMIT ISSUE. RB |
| 5-5-04 PLANS AND APPL P/U BY CHILDRENS PLACE. RB |
| 11-3-04 RICHARD BLUESTIEN CAME IN TO DISCUSS |
| PROJECT PHASING AND COLLECT A STATEMENT OF |
| OUTSTANDING PERMIT FEES. RB |
| 1-6-05 RICHARD BLUESTIEN BROUGHT IN THE PLANS FOR |
| RE-SUBMITTAL AND WAS TOLD THAT HE WOULD NEED TO |
| SUBMIT A LETTER REQUESTING AN EXTENSION IN |
| TIME.RB |
| 2/3/05 PERMIT EXTENTED UNTIL MAY 4 2005 PER LETTER |
| FROM NEIL MELICK DR |
| 2/3/05 PLANS ON RACK (COMMERCIAL BOARD #17) RB |
| 5-11-05 PERMIT READY TO PRINT BUT OWES $199.CALLED |
| RICHARD FOR P/U.'S'.RB |