| Miscellaneous Information / Notes |
| CONSTRUCTION OF COMBINATION OF DRY & COLD DISTRIB |
| FACILITY AND RELATED SITE WORK PRIMARY BUILD COMP |
| TO BE CONCRETE TILT UP PANELS AND PRE ENGINEERED |
| METAL BUILD IMPACT FEES $190575.54 PR02027117 |
| 12/21 1 COPY TO ZONING JW |
| ADDITIONAL STEEL DRAWINGS SUBMITTED AFTER FIRE, |
| ELEC,ENG REVIEWS 01/11/02 DR/LM |
| CALLED GEORGE FOR P/U 1-25 "M" KSTEVENS |
| 1-25-02 PLANS PU BY DOUG TJ |
| 3/5/02 1ST RESUB NO FEE YD |
| PLANS P/U BILL KNIGHT 4/22/02 SJOHNSON |
| 2ND RESUB 5-14-2002 5,938.00 BZ 204546 AN |
| PLANS TAKEN BILL KNIGHT FOR IMPACT FEES 7/15/02 SJ |
| IMPACT FEE PD $190578.54 7/23/02 SJOHNSON |
| PLANS STAMPED, READY TO ISSUE PERMIT WHEN |
| THRESHOLD INSPECTOR IS APPROVED BY DON NEELY |
| 7/31/02 LS |
| 8/16/02 THRESHOLD OK PER DON NEELY PERMIT CAN BE |
| RELEASED. LS |
| UP FRONT 'M' 8/16/02 LS ADD'L FEES DUE $2257.80 |
| CORRECTED PERMIT TYPE FROM DRIVEWAY APPROACH TO |
| BLD-COM 8/16/02 & REPRINTED PERMIT |
| 8/19/02 BILL PU PERMIT YD |
| 12/12/02 SUB/SHOP DRAWINGS P/U BY BILL KNIGHT PT |
| 12/22/02 SUBMITTAL NO CHG LTRS & DRAWINGS MM |
| SUBMITTALS PU/BILL 1-8-03 KAM |
| 1-17-03 SUBMITTAL PU TJ |
| 1-17-03 2 SUBMITTALS FOR BUILD TJ |
| 1-23-03 SUBMITTAL FOR BUILD TJ |
| SUBMITTAL P/U KIRT 1/23/03 SJOHNSON |
| 1/24/03 SUBMITTAL LTRS NO CHG MM |
| 2-4-03 REV FOR ELEC BZ219058 & SUBMITTAL TJ |
| 2/12/03 SUB/LIGHTING N/C PT |
| 2/12/03 SUB/SURVEYOR'S REPORT FOR BLDG PAD |
| ELEVATION CERTIFICATION P/U BY KIRK CRABTREE PT |
| 2-18-03 SUBMITTAL FOR BUILD TJ |
| ELEC REV FROM 2/4/03 UNDER "M" FOR PU. CALLED CONT |
| 2/19/03 DV PALMER. |
| REV P/U KIRT 2/20/03 SJOHNSON |
| 3-25-03 SUBMITTAL FOR BUILD TJ |
| 3-31-03 SUBMITTAL FOR BUILD TJ |
| SUBMITTAL - LETTERS - NO FEE 4-1-03 KAM |
| SUBMITTAL-SKY LIGHT TESTING - NO FEE 4-1-03 KAM |
| PROD APP SUBMITTAL PU/KIRT 4-1-03 KAM |
| 4-7-3 CURT P/U SUBMITTALS NFL |
| 5/2/03 SUBMITTAL SHOP DRAWINGS MM |
| 5-5-03 SUBMITTAL NFL |
| 5/6/03 SUB/BLDG P/U BY KIRT CRABTREE PT |
| 5/6/03 SUB/BLDG PRODUCT APPROVALS DRAWINGS P/U |
| BY KIRT CRABTREE PT |
| 5-28-03 SUBMITTAL FOR BUILD TJ |
| 6/30 P/U BY KURT.LS |
| 8/25/03 REV/MECH BZ 229486 $60 PT |
| MECH REV CALLED FOR P/U 8-27-03 UNDER M PHK |
| KURT CRABTREE PICK UP MECH REV 9-4-03 WL |
| 10/9/03 PD TCO $500 BZ232151 PSMITH |
| 10-27-03 E,F REV $180 BZ#232693 KAM |
| REVISION CALLED FOR P/U 10-28-03 UNDER "R" NAM |
| 10/29/03 REVISION PU CARMEN PSMITH |
| 10/29/03 CO P/U BY LOUIS PERKINS PT |