| Miscellaneous Information / Notes |
| NEW CONSTRUCTION 3 STORY |
| FS PERMIT # 02051434 5.28.02 MEC-WPBFR |
| FOUNDATION PERMIT #01120343 |
| SENT TO PLANNING 7-30-01 SG |
| CKLST CONT CALLED 2/1/02 HHP PLAN FILED "L" |
| PLANS P/U RICHARD 2/5/02 SJOHNSON |
| SUBMITTAL 5-8-2002 BUILD NO FEE AN |
| RESUB BACK TO ZONING 8-10-01 SJ |
| RESUB SENT TO PLANNING 8-13-2001 SG |
| 8-22 JASON P/U PLANS |
| 1ST RESUB FOR PLAN REVIEW 11-29-2001 BUILD ELEC |
| PLUMB MECH AN |
| REV READY CALLED CONTR 12/5/01 SJOHNSON |
| 12/11/PLANS FILED UNDER "L" JW |
| 12/11/01 RICHARD PU PLANS YD |
| 2ND RESUB BLDG FIRE MECH PLUM BZ196512 12/27/01 SJ |
| 3RD RESUB FOR BUILD PLUMB MECH 3-4-02 TJ |
| REV BLDG $80 BZ202949 4/11/02 SJOHNSON |
| 4/22/02 RICHARD PU REVISION YD |
| SUBMITTAL TRUSS DRAWINGS 5-8-02 AN |
| 5-15-02 SUBMITTAL PU TJ |
| FA PERMIT # 02060709 6.13.02 MEC-WPBFR |
| 8/27/02 SUBMITTAL NO FEE YD |
| 9/4/02 RICHARD PU SUBMITTALS YD |
| SUBMITTAL SHOP DRAWINGS NO FEE 10/17/02 SJOHNSON |
| REV MECH $60 BZ213332 10/17/02 SJOHNSON |
| MECH REV CALLED FOR P/U 10-25-02 UNDER C PHK |
| 3/10/03 CALLED FOR P/U,NEEDS SEPERATE PERMIT./WRT |
| 10-29-02 REV PU TJ |
| 11-19-02 REVISION BZ 215397 $110 NFL |
| JASON ACKNER PICK UP MECH/REV DATED 11-19-02 WL |
| E,P REV $60. BZ#220243 2-28-03 KAM |
| E REV $80. BZ#220244 2-28-03 KAM |
| BLDG SUBMITTAL - NO FEE 2-28-03 KAM |
| 3-6-03 SUBMITTAL PU TJ |
| 3/10/03 FOUNTAIN NEEDS SEPERATE PERMIT PER DVP, |
| CALLED FOR P/U./WRT |
| RICHARD ACKNER PICK UP ELEC REV DATED 2-28-03 |
| & ELEC/PLUMBING REV DATED 2-28-03 ON 3-10-03 WL |
| |
| 3/12/03 - MECH/ELEC FOR FOUNTAIN APP - ST |
| 4-1-03 SUBMITTAL NFL |
| 4-9-03 SUBMITTAL PU TJ |
| PER CONTRACTOR THIS IS REV # 10 ELEC SUBMITTED ON |
| 4-14-03 (INPUT AS REV #10) $60 BZ222753 4-14-03 WL |
| 4/14/03 ELEC REV.UNDER"L",CALLED FOR PU./WRT. |