| Miscellaneous Information / Notes |
| NEW CONSTRUCTION OF AUTOMOBILE SHOWROOM AND 7 BAY |
| SERVICE FACILITY |
| SENT TO BLDG FOR REVIEW WHILE WAITING FOR |
| PLANNING APPROVAL 7-31-01 |
| PLANS PU BY AMY T 08/15/01 DR |
| 1ST RESUB NO FEE 9/14/01 SJOHNSON |
| CALLED FOR P/U 9-28 LEFT MSG "R" KSTEVENS |
| BRADFORD SMITH PICK UP DENIED PLANS 10-3-01 WL |
| 2ND RESUB $800 BZ191233 10/4/01 SJOHNSON |
| PLANS READY FOR IMPACT FEES CALLED CONT "R" 10/9/0 |
| 10/10/01 DONALD PICKED UP PLANS TO PAY IMPACT FEES |
| MM |
| 10-12-01 IMPACT FEES PAID PR#01037128 22,156.13 TJ |
| FS PERMIT # 01071328 2.8.02 MEC-WPBFR |
| 3-12-02 SUBMITTAL FOR BUILD TJ |
| 3/18 SUBMITTALS 1 SET PUT WITH ROLL PLAN |
| 3/20/02 SUBMITTAL NO FEE YD |
| DONALD CHASE PICK UP SUBMITTALS DATED 3-20-02 & |
| 3-12-02 PICKUP DATE 4-19-02 WL |
| 4-25-02 REV FOR PLUMB TJ |
| 4-25-02 SUBMITTAL FOR BUILD TJ |
| CALLED CONTRACTOR: SUBMITTAL IS FOR CANOPY & |
| SHUTTERS. NEED SEPARATE PERMIT BY CONTRACTOR |
| UP FRONT UNDER 'R' LS 4/26/02 |
| CALLED FOR P/U 5-15 "R" KSTEVENS |
| REV P/U DONALD 5/21/02 SJOHNSON |
| 6-5 SUBMITTAL NFL |
| SUBMITTAL CALLED FOR P/U 6-12-02 UNDER "R" PHK |
| 6/21/02 KEVIN PU SUBMITTAL YD |