| Miscellaneous Information / Notes |
| KIT. REMODEL & ADDITION. SHUTTERS SEPARATE PERMIT |
| ELECT., MECH AND PLUMBING SEPARATE PERMITS ALSO. |
| DRAWINGS IN JULIO'S DESK. 7-27-01. JG. |
| SENT TO ZONING 8-7-01 PHK. |
| CALLED CONTRACTOR 8/14 TO P/U FOR CORRECTIONS LS |
| PU BY GREG 8-17-2001 DENIED APP PLANS AN |
| 9/10/01 1ST RESUB NO FEE YD |
| PLANS PU BY GREGG 9-25-01 TJ |
| 10-25 2ND RESUB BZ 182711 $104.96 NFL |
| PLANS AT JULIO'S DESK 10-31 KSTEVENS |
| CALLED CONTRACTOR FOR PICK UP. 11-02-01. JG. |
| RESUB 11-29-2001 BUILD BZ 182711 104.96 AN |
| BILL STAPLES CALLED CONTRACTOR TO LET HIM KNOW |
| THAT CHECKLIST WAS NOT PROPERLY ADDRESSED AGAIN. |
| PU BY PAUL 12-20-2001 DENIED APP PLANS AN |
| 3RD RESUB $104.96 BZ196304 12/21/01 SJOHNSON. |
| MET WITH OWNER, ARCHITECT, CONTRACTOR & STAPLES ON |
| 12-28-01. CONTRACTOR TOOK PLANS AND APPL. JG. |
| 3RD RESUB 1-11-02 TJ |
| CALLED CONTRACTOR @ CELL 662-0309. TOLD HIM THAT |
| PRODUCT APPROVAL STILL NOT SIGNED & SEALED BY THE |
| ARCHITECT AS REQUESTED SEVERAL TIMES. 1-23-02. JG. |
| ARCHITECT SIGNED PRODUCT APPROVAL AND REVISED |
| DESIGN PRESSURES ON 1-29-02 (NOT 1-26-02). JG. |
| CALLED CONTRACTOR. PERMIT UNDER "B" 1-30-02. JG. |