| Miscellaneous Information / Notes |
| BUILD "A" 3 STORY/TYPE IV/PROTECTED/SPRINKLERED |
| HAS NOC 605 EXECUTIVE CENTER DR |
| 7/18/01 HAROLD PU PLANS YD |
| IMPACT FEES PD PR 01026582 7/19/01 SJOHNSON |
| REV BLDG $100 BZ188961 8/7/01 SJOHNSON |
| REV BLDG $100 BZ189178 8/20/01 SJOHNSON |
| REV PLUMB $70 BZ190218 9/20/01 SJOHNSON |
| REV BLDG $150 BZ190219 9/20/01 SJOHNSON |
| 10/11/01 REVISION FOR ELEC BZ191981 $100 YD |
| 10/12/01 REVISION BZ192118 $160 YD |
| ELEC REV FROM 10/11 UNDER "B",CALLED 10/29/01 DVP |
| PU BY SAL 10-30-2001 REVISION AN |
| 11/16/01 REVISION FOR PLUMB BZ193746 $70 YD |
| CALLED FOR P/U 11-29 "B" KSTEVENS |
| PU JOE I REVISIONS 11-30-01 |
| REV ALL BLDG MECH $60 BZ198105 2/4/02 SJOHNSON |
| REV CALLED FOR P/U (NO ANSWER) 2-8-02 UNDER B PHK |
| REV MECH PU JOE I 2/15/02 NCD |
| 2-15 JO I P/U PLANS |
| 2/15/02 SUBMITTALS NO FEE FOR BLDG YD |
| 2-26-02 REV FOR MECH TJ |
| SUBMITTAL FOR MECH 2-26-02 TJ |
| SUBMITTAL FOR BUILD TJ 3-4-02 TJ |
| MECH SUBMITTAL & REV CALLED FOR P/U 3-12-02 |
| UNDER "B" PHK |
| SUBMITTAL SHOP DRAWINGS NO FEE 3/13/02 SJOHNSON |
| REV P/U MEHMET 3/13/02 SJOHNSON |
| SUBMITTAL SHOP DRAWINGS NO FEE 3/14/02 SJOHNSON |
| 3/20/02 SUBMITTAL PART OF SUBMITTAL FOR 3/14/02 YD |
| 04/08/02 SBUMITTAL BLDG BLDG A NO CHARGE MM |
| REV ELEC MECH BZ203061 $70 4/9/02 SJOHNSON |
| 4/15/02 SUBMITTAL NO FEE YD |
| MECH,ELEC REV CALLED FOR P/U 4-15-02 UNDER B PHK |
| 4-16-02 REV FOR MECH TJ |
| MECH REV CALLED FOR P/U 4-23-02 UNDER "B" PHK |
| 8-26-02 REV PU TJ |
| REV $60. BZ #211667 9-24-02 KAM |
| 9-25-02 LETTERS SUBMITTED TO DON NEELY FROM THE |
| ARCHITECT. JG. |
| CALLED FOR P/U 1-22-3 "B" KSTEVENS |