| Miscellaneous Information / Notes |
| REMODEL INTERIOR & EXTERIOR ADD @ GARAGE |
| |
| |
| |
| FLOOD ZONE A5. NEED ELEVATION CERTIFICATE. 7.5'MIN |
| DENIED BY ZONING 3/20/01 SG FAXED COMMENTS 3/27/01 |
| REV PU 4-9-02 TJ |
| CONTRACTOR (BRYANT)PICKED UP PLANS.4-11-01. JG. |
| 1ST RESUB 6-7-01 AN |
| 7/24/01 KURK PU PERMIT YD |
| TRUSS DRAWINGS NO FEE 12/28/01 SJOHNSON |
| CALLED CONTRACTOR. DWGS UNDER "S". 01-02-02. JG. |
| SUBMITTAL PU 1-3-02 TJ |
| SUBMITTAL BLDG NO FEE 1/29/02 SJOHNSON |
| PLUMB REV 01 $50 BZ 199140 2-14-02 WL |
| TRUSS DRAWINGS NO FEE 2/21/02 SJOHNSON |
| YES, THERE ARE RE-SUBMITTAL FEES. SEE BZ-200866 |
| FOR RE-SUBMITTAL FEES. 2-26-02. JG. |
| 2-26-02 CALLED CONTRACTOR. DWGS UNDER "S". JG. |
| CALLED FOR P/U PLMB 2-27 "S" KSTEVENS |
| REV PU 3-1-02 TJ |
| REV FOR PLUMB 3-1-02 TJ-THESE ARE GAS PLANS - ---- |
| --FOR PERMIT #01111177 KSTEVENS |
| |
| 03/14/02 REV MECH DRAWINGS $40.00 BZ# 201518 MM |
| MECH REV P/U BY JEFF 3-14-02 PHK |
| 03/15/02 PLUMB REV BZ# 202123 MM |
| 03/15/02 SUBMITTAL PRODUCT APPROVAL BLDG MM |
| 3-21-02. CALLED CONTRACTOR. DWGS UNDER "S". JG. |
| 4-2-02 REV FOR BUILD TJ |
| 4-2-02 SUBMITTAL PU TJ |
| DENIED BY ZONING, SEPARATE PERMITS REQUIRED FOR |
| WALLS & FENCES, SUBMIT SURVEY & COMPLETE PLANS |
| & EASEMENT RELEASE SG 4-8-02 |
| 4-8-02- CALLED CONTRACTOR. DWGS UNDER "S". JG. |
| 9-19-02 SUBMITTAL NFL |
| 10-01-02 CALLED CONTRACTOR TO PICK UP DENIED |
| PRODUCT APPROVAL PACKAGE. DWGS UNDER "S". JG. |
| PROD APPR P/U KIRK 10/03/02 SJOHNSON |
| SUBMITTAL NO FEE 11-1-02 KAM |
| 11/5/02 REV/AS BUILT ELEC PT |
| 11/6/02 ELED REV PASSED,CALLED,UNDER"S"./WRT. |
| 11-8-02 REV PU TJ |
| 11-8-02 REV FOR PLUMB TJ |
| CALLED FOR P/U 11-12 "S" KSTEVENS |
| 11/20/02 REV P/U BY KIRK LOPEZ PT |
| SUBMITTAL P/U KIRK 12/04/02 SJOHNSON |
| C/O OPTION WAS ISSUED IN ERROR MEANT TO PRINT |
| CERTIFICATE OF COMPLETION 12-9-02 WL |