Plan Review Notes For Project Z20110013 |
Project Number |
Z20110013 |
|
Review Stop |
STORM |
Sequence Number |
2 |
|
Notes |
Date |
Text |
2021-01-06 07:53:11 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE | | 12/29/2020 SUBMITTAL PACKAGE AND ARE CONDITIONS FOR | | SITE PLAN APPROVAL. | | | | 1. WHAT IS THE PURPOSE OF THE TRENCH DRAIN ON THE EAST | | SIDE OF THE BUILDING. THE PAVEMENT SLOPES AWAY FROM THE | | BUILDING. | | | | 2. HOW WAS THE FINISHED FLOOR ELEVATION OF 20.25 NAVD | | DETERMINED? IT APPEARS IF THE FFE ELEVATION IS LOWERED, | | THE PAVEMENT SLOPES CAN BE FLATTENED. THE LONGITUDINAL | | SLOPE AT THE CAR WASH EXIT IS 6%, AND THE CROSS SLOPE | | ALONG THE WEST EDGE IS OVER 4%. | | | | 3. ADD A CATCH BASIN NEAR THE DUMPSTER TO CAPTURE MORE | | ONSITE STORMWATER RUNOFF. | | | | TRACY WARD, P.E. | | SENIOR STORMWATER ENGINEER | | ENGINEERING SERVICES DEPARTMENT | | 561-494-1120 (O) | | 561-351-0510 (M) |
|