2020-12-10 13:21:48THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. DRAINAGE SYSTEM TO BE DESIGNED PER THE MASTER ERP
 PERMIT FOR THE SITE.
  
 2. PROVIDE THE VERTICAL SEPARATION BETWEEN THE PROPOSED
 STORM PIPE AND THE EXISTING STORM PIPE IN THE DRIVE
 AISLE ALONG THE EAST SIDE OF THE SITE.
  
 3. CAR WASH WATER IS NOT TO BE INTRODUCED INTO THE
 DRAINAGE SYSTEM.
 4. SITE IS LOCATED WITHIN A SPECIAL FLOOD HAZARD AREA
 (SFHA). STRUCTURES WITHIN A SFHA ARE TO PROVIDE MINIMUM
 TWO FEET OF FREEBOARD ABOVE THE BASE FLOOD ELEVATION.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE FDEP ERP MODIFICATION AND
 DRAINAGE CALCULATIONS PRIOR TO STARTING CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved