2020-12-10 13:21:48 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| APPLICATION PROCESSES. |
| |
| THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| PLAN APPROVAL: |
| |
| 1. DRAINAGE SYSTEM TO BE DESIGNED PER THE MASTER ERP |
| PERMIT FOR THE SITE. |
| |
| 2. PROVIDE THE VERTICAL SEPARATION BETWEEN THE PROPOSED |
| STORM PIPE AND THE EXISTING STORM PIPE IN THE DRIVE |
| AISLE ALONG THE EAST SIDE OF THE SITE. |
| |
| 3. CAR WASH WATER IS NOT TO BE INTRODUCED INTO THE |
| DRAINAGE SYSTEM. |
| 4. SITE IS LOCATED WITHIN A SPECIAL FLOOD HAZARD AREA |
| (SFHA). STRUCTURES WITHIN A SFHA ARE TO PROVIDE MINIMUM |
| TWO FEET OF FREEBOARD ABOVE THE BASE FLOOD ELEVATION. |
| |
| THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| |
| 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| |
| 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| WITH THE ENGINEERING PERMIT APPLICATION. |
| |
| 3. PROVIDE A COPY OF THE FDEP ERP MODIFICATION AND |
| DRAINAGE CALCULATIONS PRIOR TO STARTING CONSTRUCTION. |
| |