Plan Review Notes
Plan Review Notes For Project Z19040019
Project Number Z19040019
Review Stop STORM
Sequence Number 1
Notes
Date Text
2019-05-07 18:31:22THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. UPDATE THE FEMA FLOODZONE INFORMATION ON THE
 AMERICAN BOUNDARY SURVEY. FIRMS WERE REVISED IN 2017.
  
 2. THE CITY?S VERTICAL DATUM IS NGVD 1929. THE CITY HAS
 ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION
 EQUATION TO NGVD 1929 IS PROVIDED ON THE SHEET(S). LIST
 THE CONVERSION EQUATION ON THE ENGINEERING PLANS AND ON
 THE WALLACE SURVEY.
  
 3. LABEL S. DIXIE HWY AND S. QUADRILLE BLVD. ON THE
 ENGINEERING PLANS.
  
 4. UPDATE PROJECT DESIGN TEAM ON THE ARCHITECTURAL
 COVER SHEET. CIVIL ENGINEER IS LISTED AS KEITH AND
 ASSOCIATES BUT PRELIMINARY ENGINEERING PLAN PREPARED BY
 REIKENIS & ASSOCIATES, LLC IN ASSOCIATION WITH MCLEOD
 MCCARTHY & ASSOCIATES. LANDSCAPE ARCHITECT IS LISTED AS
 TBG BUT LANDSCAPE PLANS PREPARED BY SCHMIDT-NICHOLS.
  
 5. THE PRELIMINARY ENGINEERING PLAN REFERENCES A SITE
 PLAN PREPARED BY SCHMIDT-NICHOLS . THIS PLAN WAS NOT
 PROVIDED.
  
 6. PRELIMINARY ENGINEERING PLAN (CONCEPTUAL PAVING,
 GRADING & DRAINAGE PLAN) APPEARS TO SHOW EXISTING AND
 PROPOSED IMPROVEMENTS WITH NO DIFFERENTIATION BETWEEN
 THE TWO.
  
 7. SHOW FLOW ARROWS ON THE CONCEPTUAL PG&D PLAN,
 PARTICULARLY AT THE DRIVEWAYS.
  
 8. ALLEY WILL NEED TO BE REGRADED TO ELIMINATE LOW
 SPOTS WHERE WATER PONDS.
  
 9. S. QUADRILLE BLVD IS MAINTAINED BY FDOT. AN FDOT
 PERMIT WILL BE REQUIRED FOR ANY IMPROVEMENTS PROPOSED
 IN THE RIGHT-OF-WAY.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  