Plan Review Notes
Plan Review Notes For Project Z18050028
Project Number Z18050028
Review Stop STORM
Sequence Number 3
Notes
Date Text
2018-11-09 16:22:41THE FOLLOWING COMMENTS ARE FROM THE OCTOBER 11, 2018
 SUBMITTAL PACKAGE:
  
 1. COORDINATE THE STORM PIPE SIZE SHOWN ON THE SHEET
 C1.1 CONCEPTUAL PG&D PLAN (12" HDPE) WITH THE ON-SITE
 EXFILTRATION TRENCH DETAIL (18" HDPE) AMD POLLUTION
 REDTARDANT BAFFLE (PRB) DETAIL (18" HDPE) ON SHEET C2.1
 CONCEPTUAL ENGINEERING DETAILS.
  
 2. THE MILL AND OVERLAY LIMITS ON MALVERNE ROAD MAY
 NEED TO BE EXPANDED INTO THE EASTBOUND LANE DEPENDING
 ON THE TRENCH CUT NEEDED TO INSTALL THE SANITARY WYE.
  
 3. CONSIDER MOVING THE CLEANOUTS OUT OF THE SIDEWALK TO
 ELIMINATE A TRIPPING HAZARD.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  