2014-05-08 16:13:39 | 1. SHOW VERTICAL DATUM ON THE ENGINEERING PLAN. | | 2. MODIFY SFWMD ERP PERMIT BEFORE START OF | | CONSTRUCTION. | | 3. OBTAIN NPDES STORMWATER CONSTRUCTION PERMIT PRIOR TO | | START OF CONSTRUCTION. | | 4. SUBMIT WITH THE ENGINEERING PERMIT APPLICATION | | DRAINAGE CALCULATIONS; PAVING, GRADING AND DRAINAGE | | PLANS; AND EROSION CONTROL PLAN. | | 5. HANDICAP PARKING NEEDED FOR PHASE 1? | | | | TRACY L. WARD, P.E. | | SENIOR STORMWATER ENGINEER | | ENGINEERING AND PUBLIC WORKS DEPARTMENT | | 561-494-1120 |
|