Plan Review Notes
Plan Review Notes For Project Z14040016
Project Number Z14040016
Review Stop STORM
Sequence Number 1
Notes
Date Text
2014-05-08 16:13:391. SHOW VERTICAL DATUM ON THE ENGINEERING PLAN.
 2. MODIFY SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION.
 3. OBTAIN NPDES STORMWATER CONSTRUCTION PERMIT PRIOR TO
 START OF CONSTRUCTION.
 4. SUBMIT WITH THE ENGINEERING PERMIT APPLICATION
 DRAINAGE CALCULATIONS; PAVING, GRADING AND DRAINAGE
 PLANS; AND EROSION CONTROL PLAN.
 5. HANDICAP PARKING NEEDED FOR PHASE 1?
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120