2021-09-22 13:31:07 | E21080001 ? WPB GOLF COURSE, 7201-7301 GEORGIA AVE. - |
| 8-25-2021 SUBMITTAL |
| |
| COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE |
| SUPER., WPB PUBLIC UTILITIES, 561-494-2262 OR |
| [email protected]: |
| |
| LABEL THE GATE VALVES IMMEDIATELY UPSTREAM OF DCDA?S AS |
| POINT OF SERVICE. RESPONSE: THE GATE VALVES FOR THE |
| DCDA?S HAVE BEEN ADDED TO THE PLANS, REFER TO SHEETS |
| C3.0?C3.2. |
| FOLLOWUP: ADJUST THE LABELING TO THE NEXT GATE VALVE |
| EAST ON BOTH. SECOND GATE VALVES FROM THE WATER MAIN |
| SHOULD BE THE POINT OF SERVICE. |
| DETAIL/LABEL THE TRANSITION UPSTREAM OF THE 3 INCH |
| METERS AND DOWNSTREAM OF THE TAPPING VALVES. RESPONSE: |
| THE TRANSITION HAS BEEN LABELED, REFER TO SHEET C3.2. |
| FOLLOWUP: WAS LOOKING FOR INFORMATION ON THE PIPE |
| MATERIAL (DIP) AND OFFSETS (LOOKS LIKE 45S). PLEASE ADD |
| CALLOUT/LABEL. |
| MAINTENANCE BUILDING WATER PLAN NEEDS TO BE REDESIGNED. |
| 16 INCH WATER MAIN WHERE 6 INCH FIRE MAIN IS PROPOSED |
| CANNOT BE USED. |
| CLOSEST TAP LOCATION WOULD BE GREGORY/GEORGIA FOR |
| ADDITIONAL WATER SERVICES. FIRE HYDRANT NEAR BUILDING |
| WOULD BE PRIVATE AND DOWNSTREAM OF A DCDA. WATER METERS |
| WOULD BE ADJACENT GEORGIA/GREGORY |
| RESPONSE: THIS ITEM HAS BEEN DISCUSSED FURTHER WITH |
| WEST PALM BEACH STAFF AND WE ARE LOOKING INTO COST |
| SAVING OPPORTUNITIES TO AVOID HAVING TO RUN A 2? AND 4? |
| LINE FROM GREGORY/GEORGIA ALL THE WAY TO THE |
| MAINTENANCE BUILDING (APPROXIMATELY 200FT.). |
| FOLLOWUP: NOT SATISFIED. SUBMITTED PLAN LOOKS ROUGHLY |
| THE SAME. PLEASE SUBMIT NEW PLAN. |
| NEW COMMENTS: |
| -CHECK THE LOS ANALYSIS FOR THE OFFICE WATER AND SEWER. |
| THE CANNOT REPRODUCE THE CALCULATIONS USING THE |
| INFORMATION SHOWN. NOT SURE IF TYPO OR PART OF EQUATION |
| MISSING. |
| -SHEET C5.3 WATER SYSTEM NOTES TALKS ABOUT CITY OF FT. |
| LAUDERDALE. PLEASE EDIT. |
| |
| |
| COMMENTS FROM TRACY WARD, SR. STORMWATER ENG., |
| ENGINEERING SERVICES, [email protected] 561-494-1120: |
| |
| 1. UNLESS INDICATED ELSEWHERE, FOR THE PGD SHEETS, |
| INDICATE WHICH EXFILTRATION DETAIL ON SHEET C4 IS TO BE |
| FOLLOWED FOR THE EXFILTRATION TRENCHES SHOWN ON THE PDG |
| SHEET. THIS CAN BE: (A) A GENERAL NOTE ON EACH SHEET IF |
| ALL EXFILTRATION TRENCHES ARE TO BE CONSTRUCTED PER ONE |
| PARTICULAR DETAIL; (B) PUT THE PARTICULAR OR CUSTOMIZED |
| EXFILTRATION TRENCH DETAIL ON THE PGD SHEET IF THERE IS |
| ROOM; OR (C) LABEL EACH EXFILTRATION TRENCH ON THE PGD |
| PLANS AS 5? X 6?, 4? X 6? OR 4? X 4?. NOTE THE PIPE |
| INVERT ELEVATIONS FOR THE EXFILTRATION TRENCHES ON |
| SHEETS C2.3 AND C2.4 DO NOT MATCH ANY OF THE PIPE |
| INVERTS SHOWN IN THE THREE EXFILTRATION TRENCH DETAILS |
| ON SHEET C4. |
| |
| 2. AT THE MAINTENANCE BUILDING, IS THE INTENT TO HAVE |
| THE FLOW FROM THE BUBBLE UP STRUCTURE CB#4 FLOW OVER |
| THE TOP OF BERM AND INTO THE C-51 CANAL? IS THERE ANY |
| STORAGE PROVIDED AT CB#4? |
| |
| COMMENTS FROM MIKE TECHNOW, PUBLIC UTILITIES ENGINEER, |
| [email protected], 561-494-1047: |
| |
| -SHEET C3.1 ADD MATCH LINE. |
| - ADD NOTE THAT THIS PROJECT IS WITHIN LS 3 SERVICE |
| BOUNDARY. |
| -SHOW PROFILE OF POINT OF SERVICE & WATER MAIN OFFSET. |
| -ON SHEET C6.3 SHOW WM UNDER 8? WW WITH MIN. 12? |
| VERTICAL SEPARATION. |
| -PLEASE REVISE PLANS ONCE SOFT DIG INFORMATION IS |
| AVAILABLE PRIOR TO CONSTRUCTION STARTING. |
| -ADD NOTE ON SHEET C3.2 TO RESTRAIN 8? WM ON EACH SIDE |
| AS REQUIRED (TYPICAL). |
| -CHECK LOCATION OF NEAREST VALVE, MAY HAVE TO ADD TWO |
| INSERTION VALVES OR TWO LINE STOPS AND GATE VALVE. |
| -IN ?WATER SEWER NOTES? REMOVE BROWARD COUNTY AND |
| REPLACE WITH PALM BEACH AND CITY?S STANDARDS. |
| -ADD NOTE REQUIRING BAC-T TEST. |
| -PROVIDE POST CCTV ON SEWER. |
| -REMOVE NON-CITY APPROVED DETAILS. |
| -ADD PROFILE FOR ANY PIPE THE CITY WILL OWN & MAINTAIN. |
| FROM TAP TO POINT OF SERVICE. |
| -TIE IN WITH 16? TRANSMISSION MAIN MUST BE COORDINATED |
| WITH WATER PLANT. MUST BE DOWN DURING LOW FLOW PERIOD. |
| |
| FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| CONCERNS, THANKS. |
| RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES |
| DEPARTMENT (561) 494-1098 [email protected] |
| |
| |
|