2011-01-10 14:40:15 | APPROVED AS-NOTED: |
| |
| #1 AS-BUILTS WILL BE REQUIRED TO BE SUBMITTED ON |
| 24"X36" SIZE PLANS. |
| #2 METER VAULT WILL REQUIRED AN EASEMENT (SKETCH AND |
| LEGAL) IF PLACED JUST INSIDE PROPERTY LINE AS SHOWN. |
| #3 BACKFLOWS WILL BE INSTALLED AS CLOSE TO THE SOURCE |
| AS POSSIBLE. COORDINATION WITH UTILITIES CUSTOMER |
| SERVICE WILL BE PARAMOUNT AS TO THE PLACEMENT OF |
| BACKFLOWS. |
| WE WILL MEET ON-SITE AT TIME OF PRE-CONSTRUCTION TO |
| COORDINATE LOCATION. LOCATION AND HEIGHT WILL BE |
| IMPORTANT AS BUILDING WILL SIT APPROXIMATELY 2 FEET |
| HIGHER THAN SIDEWALK. |
| #4 BACKFLOW FOR IRRIGATION SHALL BE A REDUCED PRESSURE |
| PRINCIPAL ASSEMBLY (RPZ) AND NOT A PRESSURE VACUUM |
| BREAKER. |
| #5 IN THE EVENT WATERMAIN CANNOT BE SHUT DOWN TO |
| INSTALL TEE'S FOR SERVICES IT WILL BE THE CONTRACTOR'S |
| RESPONSABILITY TO PROVIDE ALTERNATE METHODS AT THEIR |
| EXPENSE, SUCH AS "DIRECT TAP". |
| #6 EXISTING WATER SERVICES TIED TO MAIN MUST BE CUT |
| BACK AT THE MAIN. METER BOX IN SIDEWALK MUST BE REMOVED |
| AND SIDEWALK REPAIRED TO ACCOMODATE SUCH REMOVAL. |
| #7 WHERE PRIVATE WATER LINES AND SERVICES CROSS 10' |
| UTILITY EASEMENT SLEEVES MAY BE REQUIRED FOR PROPER |
| CLEARANCE AND SAFETY WHEN CROSSING OTHER UTILITIES. |
| #8 ON-SITE WATER AND SEWER CROSSINGS MUST BE IDENTIFIED |
| AND MUST PROVIDE ALLOWABLE CLEARANCES AS PER HEALTH |
| STANDARDS. |
| #9 ALL HYDRANTS IN THE VICINITY OF THE PROJECT MUST BE |
| ACTIVE PRIOR TO CONSTRUCTION. |
| #10 POLLUTION PREVENTION IS APPLICABLE ON ANY WATER |
| SERVICE TIE-IN. |
| #11 MATERIALS IN THE ROW WILL BE AS PER LATEST CITY OF |
| WPB DETAILS AND LATEST APPROVED MATERIAL LIST. A LIST |
| MAY BE OBTAINED VIA WEB SITE AT THE LINK BELOW: |
| HTTP://WWW.CITYOFWPB.COM/ENGINEERING/ENG_FORMS.PHP |
| WE WILL REQUIRE SUBMITTAL OF THIS LIST BY UNDERGROUND |
| CONTRACTOR PRIOR TO PRE-CONSTRUCTION. |
| #12 SEWER TIE-INS AS WELL AS STORMWATER WILL BE THE |
| JURISDICTION OF THE TOWN OF PALM BEACH AND |
| ENGINEER-OF-RECORD. |
| #13 IT WILL BE THE CONTRACTOR'S RESPONSABILITY TO |
| OBTAIN TOWN OF P.B. ROW PERMIT PRIOR TO ANY |
| RIGHT-OF-WAY EXCAVATION. |
| |
| MANUEL JULIAN GONZALEZ |
| ENGINEERING PROJECT COORDINATOR |
| ENGINEERING SERVICES DEPARTMENT |
| 401 CLEMATIS STREET, 4TH FLOOR |
| WEST PALM BEACH, FL 33401 |
| (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| MAIN PHONE: (561) 822-1200 |
| DIRECT: (561) 494-1085 |
| FAX: (561) 494-1116 |
| MOBILE: (561) 644-7301 |
| EMAIL: [email protected] |
| WWW.WPB.ORG/ENGINEERING |
| |
| |
| |
| |
|
Print |