2011-01-10 14:40:15APPROVED AS-NOTED:
  
 #1 AS-BUILTS WILL BE REQUIRED TO BE SUBMITTED ON
 24"X36" SIZE PLANS.
 #2 METER VAULT WILL REQUIRED AN EASEMENT (SKETCH AND
 LEGAL) IF PLACED JUST INSIDE PROPERTY LINE AS SHOWN.
 #3 BACKFLOWS WILL BE INSTALLED AS CLOSE TO THE SOURCE
 AS POSSIBLE. COORDINATION WITH UTILITIES CUSTOMER
 SERVICE WILL BE PARAMOUNT AS TO THE PLACEMENT OF
 BACKFLOWS.
 WE WILL MEET ON-SITE AT TIME OF PRE-CONSTRUCTION TO
 COORDINATE LOCATION. LOCATION AND HEIGHT WILL BE
 IMPORTANT AS BUILDING WILL SIT APPROXIMATELY 2 FEET
 HIGHER THAN SIDEWALK.
 #4 BACKFLOW FOR IRRIGATION SHALL BE A REDUCED PRESSURE
 PRINCIPAL ASSEMBLY (RPZ) AND NOT A PRESSURE VACUUM
 BREAKER.
 #5 IN THE EVENT WATERMAIN CANNOT BE SHUT DOWN TO
 INSTALL TEE'S FOR SERVICES IT WILL BE THE CONTRACTOR'S
 RESPONSABILITY TO PROVIDE ALTERNATE METHODS AT THEIR
 EXPENSE, SUCH AS "DIRECT TAP".
 #6 EXISTING WATER SERVICES TIED TO MAIN MUST BE CUT
 BACK AT THE MAIN. METER BOX IN SIDEWALK MUST BE REMOVED
 AND SIDEWALK REPAIRED TO ACCOMODATE SUCH REMOVAL.
 #7 WHERE PRIVATE WATER LINES AND SERVICES CROSS 10'
 UTILITY EASEMENT SLEEVES MAY BE REQUIRED FOR PROPER
 CLEARANCE AND SAFETY WHEN CROSSING OTHER UTILITIES.
 #8 ON-SITE WATER AND SEWER CROSSINGS MUST BE IDENTIFIED
 AND MUST PROVIDE ALLOWABLE CLEARANCES AS PER HEALTH
 STANDARDS.
 #9 ALL HYDRANTS IN THE VICINITY OF THE PROJECT MUST BE
 ACTIVE PRIOR TO CONSTRUCTION.
 #10 POLLUTION PREVENTION IS APPLICABLE ON ANY WATER
 SERVICE TIE-IN.
 #11 MATERIALS IN THE ROW WILL BE AS PER LATEST CITY OF
 WPB DETAILS AND LATEST APPROVED MATERIAL LIST. A LIST
 MAY BE OBTAINED VIA WEB SITE AT THE LINK BELOW:
 HTTP://WWW.CITYOFWPB.COM/ENGINEERING/ENG_FORMS.PHP
 WE WILL REQUIRE SUBMITTAL OF THIS LIST BY UNDERGROUND
 CONTRACTOR PRIOR TO PRE-CONSTRUCTION.
 #12 SEWER TIE-INS AS WELL AS STORMWATER WILL BE THE
 JURISDICTION OF THE TOWN OF PALM BEACH AND
 ENGINEER-OF-RECORD.
 #13 IT WILL BE THE CONTRACTOR'S RESPONSABILITY TO
 OBTAIN TOWN OF P.B. ROW PERMIT PRIOR TO ANY
 RIGHT-OF-WAY EXCAVATION.
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 MOBILE: (561) 644-7301
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  
  
  
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved