Plan Review Details - Project E09110009
Plan Review Stops For Project E09110009
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status F Date 11-12-2009 Cont ID  
Sent By   Date 11-12-2009 Time   Rev Time 4.00
Received By   Date 11-12-2009 Time   Sent To  
Notes
2009-11-12 07:26:01PROJECT HAS BEEN REVIEWED: STATUS IS FAILED DUE TO THE
 FOLLOWING.
 #1 REVISE COST ESTIMATE TO REFLECT ELEMENTS ON THE
 PLAN.
 MISSING COPPER PIPING, MISSING FIRELINE, MISSING SAMPLE
 POINTS
 (ONCE REVISED COST ESTIMATE MUST BE ACCEPTED BY BRIAN
 MOREE)
 #2 COLLECTION OF FEES BASED ON MIN $1,750 OR 5.5% OF
 COST ESTIMATE (*BASED ON ENGINEERING FEE DIRECTORY)
 (FEE HAS BEEN ACCEPTED)
 #3 BASED ON COST ESTIMATE POST A SURETY FOR THE UTILITY
 WORK IN TOPB, 110% OF THE UTILITY COST, PLUS THE BOND
 ADMINISTRATION FEE $128.75.
 #4 REVIEW CUSTOMER SERVICE METER QUOTE TO SEE IF
 FEASIBLE RELOCATING METER.
 (QUOTE HAS BEEN PROVIDED AND DISCUSSED WITH EOR)
 #5 FUTURE CONDUITS MUST TERMINATE ON-SITE (THIS REVIEW
 ONLY COVERS WATER ELEMENTS)
 (A SEPARATE REQUEST MUST BE SENT IN IN WRITING TO ESD
 REQUESTING PERMISSION TO CROSS CITY OF WPB WATERMAIN
 WITH PRIVATE UTILITIES - IT IS ENCOURAGED THAT AN
 EXHIBIT BE SUBMITTED)
 #6 BACTEES WILL BE REQUIRED BY OUR DEPARTMENT BEFORE
 SETTING METER DUE TO LENGTH OF SERVICE.
 #7 PLANS ARE REQUIRED TO BE ON 24X36, PLEASE BE
 PREPARED TO CHANGE TO THIS STANDARD AT THE NEXT PHASE.
 #8 TAPPING VALVE WAS SHOW AT WRONG LOCATION.
 #9 EXISTING FIREHYDRANT WAS NOT SHOWN, IT MUST BE 150'
 MIN FROM THE FDC LOCATION.
 #10 FDC LOCATION WAS NOT SHOWN, PLEASE SHOW.
 REDLINED PLANS AND CERTIFIED CONSTRUCTION COST ESTIMATE
 WHERE RETURNED TO EOR FOR REVISION 11/12/09.
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 MOBILE: (561) 644-7301
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  
  
  
  
  
  
  
  
  
  

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status P Date 11-25-2009 Cont ID  
Sent By   Date 11-30-2009 Time   Rev Time 24.00
Received By   Date 11-25-2009 Time   Sent To  
Notes
2009-11-30 12:25:59REVISIONS WHERE NOTED.
 PLANS APPROVED AS-NOTED, IT IS REQUIRED THAT AS-BUILTS
 ARE SUBMITTED 24X26 SHEET SIZE.
 FILE NOTICE OF COMMENCEMENT AS REQUIRED.
 SURETY IN PLACE BY TIME THE PRECONSTRUCTION IS
 REQUESTED
 COST ESTIMATE APPROVED 11/25/09
  
 MANNY GONZALEZ
 PROJECT COORDINATOR
 (561) 494-1085
 [email protected]

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status P Date 10-18-2010 Cont ID  
Sent By   Date 10-21-2010 Time   Rev Time 4.00
Received By   Date 10-21-2010 Time   Sent To  
Notes
2010-10-21 07:58:08PASSED
 FIELD WALK THRU WAS PERFORMED.
 TOWN OF PB WAITING FOR OUR CLOSURE TO CLOSE-OUT PERMIT.
 PRESENTED MR MOREE WITH SURETY RELEASE PROJECT CLOSURE
 DOCUMENTATION 10/21/2010

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status N Date 10-21-2010 Cont ID  
Sent By mgonzale Date 10-21-2010 Time 07:59 Rev Time 0.00
Received By mgonzale Date 10-21-2010 Time 07:58 Sent To  
Notes
***NONE***