Plan Review Notes
Plan Review Notes For Permit 99100504
Permit Number 99100504
Review Stop ENG
Sequence Number 1
Notes
Date Text
2001-01-08 00:00:00SIDEWALK AND DRIVEWAY REQUIREMENTS:
 1.ALL BROKEN SIDEWALKS ALONG THE
 PROPERTY (ALL SIDES) MUST BE REPLACED.
 2.ALL DRIVEWAYS THAT WILL NOT BE USED
 MUST BE REMOVED AND THE REGULAR CURBS (&
 GUTTERS) MUST BE REPLACED.
 3.ALL BROKEN UP CURBS (& GUTTERS) MUST
 BE REPLACED.
 4.ALL DRIVEWAY APPROACHES MUST BE (AT A
 MINIMUM) PER CITY STANDARD DETAIL INDEX.
 5.ALL GRADES FOR CITY SIDEWALKS WILL BE
 SET BY THE CITY SURVEY CREW, CALL 659-
 8040 AND ASK FOR ED RYAN TO SET UP AN
 APPOINTMENT.
 SANITATION:
 IF GARBAGE IS TO BE PICKED UP BY CITY OR
 IF IT IS PRIVATE PICKUP, IF TO BE PICKED
 UP BY THE CITY THEN THE FOLLOWING
 REQUIREMENTS MUST BE MET.IF THE
 CONTRACTOR WISHES TO CHANGE ANY OF THE
 FOLLOWING REQUIREMENTS HE WILL NEED TO
 MEET WITH PETE SPATARA OF THE SANITATION
 DIVISION AND SUBMIT THE CHANGES TO
 BUILDING AND ZONING FOR INCLUSION IN THE
 BUILDING PLAN SETS:
 1.DUMPSTER MUST HAVE A MINIMUM OF 12'-6"
 OPENING BETWEEN THE GATE POSTS.
 2.INTERIOR DIMENSIONS OF THE ENCLOSURE
 MUST BE A MINIMUM OF 12'-6" WIDE AND 12'
 DEEP.A CONCRETE PARKING STOP BARS 10'
 LONG MUST BE CENTERED (FROM GATES) AND
 INSTALLED 18" FROM THE BACK WALL.STEEL
 BARS WILL BE DRILLED THRU THE STOP BAR
 AND INTO THE INTERIOR FLOOR OF THE
 ENCLOSURE TO STOP THE STOP BAR FROM
 MOVING WHEN THE DUMPSTER IS SET INSIDE.
 3.THE OPENING OF THE DUMPSTER ENCLOSURE
 MUST BE ANGLED SO THAT A 40' LONG TRUCK
 WITH THE FORKS EXTENDED CAN APPROACH THE
 OPENING AND PICK UP THE DUMPSTER WITHOUT
 MAKING A SHARP TURN.
 4.THE TRUCK NEEDS TO HAVE NO LESS THAN A
 16' HIGH VERTICAL CLEARANCE AREA FOR THE
 TRUCK TO PICK UP THE DUMPSTER. THE CLEAR
 AREA MUST OVER THE DUMPSTER AND WHERE
 THE TRUCK WILL BE STOPPED TO UNLOAD THE
 DUMPSTER.
 5.THE TRUCK NEEDS TO HAVE NO LESS THAN
 14' HIGH VERTICAL CLEARANCE AND 12'
 HORIZONTAL CLEARANCES FOR THE TRUCK TO
 DRIVE THROUGH.
 6.IT IS STRONGLY SUGGESTED THAT YOU ADD
 A RECYCLING CENTER TO YOUR DUMPSTER
 ENCLOSURE.
 7.THE GARBAGE TRUCK WILL NOT BE ABLE TO
 DRIVE INTO THE DUMPSTER AS DRAWN, IT
 SHOULD BE AT A 45 DEGREE ANGLE TO THE
 ALLEY WITH THE GATE FACING NORTHWEST.
 (CITY) IRRIGATION AND LANDSCAPE CONFLICT
 REQUIREMENTS:
 1.ANY LANDSCAPE DISRUPTED BY
 CONSTRUCTION SHALL BE REPAIRED AND OR
 REPLACED AT THE CONTRACTORS EXPENSE.
 2.IT IS THE CONTRACTORS RESPONSIBILITY
 TO MAINTAIN ANY CITY OWNED LANDSCAPING
 IF THE IRRIGATION SYSTEM IS DISRUPTED.
 3.ANY TREES NEEDING TO BE REMOVED AND OR
 RELOCATED SHALL BE AT THE DIRECTION OF
 THE GROUNDS OPERATIONS DIVISION
 SUPERINTENDENT (659-8044) AT THE
 CONTRACTORS EXPENSE.
 4.ANY IRRIGATION SYSTEM REPAIRED OR
 REPLACED OR ANY CONDUITS LAID FOR FUTURE
 SYSTEMS SHALL BE AT THE DIRECTION OF THE
 GROUNDS OPERATIONS DIVISION
 SUPERINTENDENT AT THE CONTRACTORS
 EXPENSE AND SHALL BE "AS-BUILT" BY THE
 CONTRACTOR THRU A PE OR LAND SURVEYOR.
 A COPY OF THE IRRIGATION AS-BUILTS WILL
 BE SUBMITTED TO ENGINEERING FOR THIER
 RECORDS.