Plan Review Notes For Permit 23020210 |
Permit Number |
23020210 |
|
Review Stop |
B |
Sequence Number |
3 |
|
Notes |
Date |
Text |
2023-07-12 07:51:08 | PETER E VALENTI | | BUILDING PLANS EXAMINER II/INSPECTOR | | [email protected] | | 561 805 6673 | | | | FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020) | | FBC B = FBC BUILDING | | FBC R = FBC RESIDENTIAL | | FBC EB = FBC EXISTING BUILDING | | FBC A = FBC ACCESSIBILITY | | FBC EC = FBC ENERGY CONSERVATION | | FBC M = FBC MECHANICAL | | FBC FG = FBC FUEL GAS | | | | THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A | | DEMO PERMIT PER FLORIDA BUILDING | | CODE, BUILDING 3303: | | | | | | 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT | | APPLICATION TO BUILDING DIVISION); | | SCHEDULE A FINAL PLUMBING #703. | | A SEPARATE PLUMBING PERMIT (TURN AROUND PERMIT) AND A | | FINAL FIELD INSPECTION OF THE CAPPING ARE REQUIRED FOR | | THE SEWER LATERAL CAPPING. THIS NEEDS TO BE COMPLETED | | PRIOR TO DEMO PERMIT ISSUANCE. | | |
|