Plan Review Notes For Permit 23020205 |
Permit Number |
23020205 |
|
Review Stop |
Z |
Sequence Number |
3 |
|
Notes |
Date |
Text |
2023-07-18 16:29:55 | PROVISOS: | | | | 1) THIS DEMOLITION PERMIT DOES NOT PERMIT THE | | DEMOLITION OF ANYTHING OUTSIDE OF THE PROPERTY LINE. | | ANY WORK WITHIN THE RIGHT-OF-WAY MUST BE SPECIFICALLY | | APPROVED BY THE ENGINEERING DEPARTMENT AS PART OF A | | RIGHT-OF-WAY PERMIT. | | | | 2) IN ACCORDANCE WITH TIMELINES OUTLINED IN SECTION IX | | OF THE ROSEMARY SQUARE CORE DEVELOPMENT REGULATIONS: | | | | A. THE SITE MUST BE SODDED/SEEDED IF A BUILDING PERMIT | | FOR VERTICAL CONSTRUCTION HAS NOT BEEN ISSUED WITH 90 | | DAYS OF THE COMPLETION OF THE DEMOLITION. | | B. 73 LINEAR FEET OF SEATING MUST BE INSTALLED IF A | | LEVEL III SITE PLAN HAS NOT BEEN APPROVED WITHIN 120 | | DAYS OF THE COMPLETION OF THE DEMOLITION. | | C. 1,461 SQUARE FEET OF TREE CANOPY MUST BE INSTALLED | | IF A LEVEL III SITE PLAN HAS NOT BEEN APPROVED WITHIN | | 180 DAYS OF THE COMPLETION OF THE DEMOLITION. |
|