2022-11-14 12:28:18 | 1) SUBMITTED DRAWING SHOWS WOOD POWER POLE (LABELED AS |
| WPP) AND CONNECTED DOWN GUY WIRE IN AREA OF PROPOSED |
| DRIVEWAY ON 11TH ST. POLE/DOWNGUY WILL NEED TO BE |
| RELOCATED. |
| |
| 2) WESTERNMOST DRIVEWAY FLARE MUST BEGIN PAST RADIUS |
| CURVE OF THE INTERSECTION OF 11TH ST. AND CARVER AVE.; |
| EASTERNMOST DRIVEWAY FLARE MUST END AT EASTERN PROPERTY |
| LINE. |
| |
| 3) CONSTRUCT DRIVEWAY APRON IN COMPLIANCE WITH WPB |
| CONSTRUCTION STANDARD DETAIL GC-5 (WHEN DISTANCE |
| BETWEEN CURB OR EDGE OF PAVEMENT IS 10 FT. OR GREATER), |
| OR STANDARD DETAIL GC-6 (WHEN DISTANCE BETWEEN CURB OR |
| EDGE OF PAVEMENT IS LESS THAN 10 FT.) CITY STANDARD |
| DETAIL IS REQUIRED, AVAILABLE HERE: HTTPS://WWW.WPB.ORG |
| /GOVERNMENT/ENGINEERING/ENGINEERING-STANDARDS-DETAILS |
| UPDATE SURVEY WITH REQUESTED INFORMATION AND RESUBMIT |
| WITH A COPY OF THE APPLICABLE STANDARD DETAIL FOR |
| DRIVEWAYS. |
| |
| 4) DIMENSIONS ARE MISSING FROM PROPOSED DRIVEWAY ON |
| CARVER AVE. IS THIS A SEPARATE ADDRESS AND PERMIT? |
| |
| FOR QUESTIONS ABOUT HOW TO RESUBMIT, SEE INFO ON |
| WEBSITE OR EMAIL [email protected] AND A BUILDING DIVISION |
| TEAM MEMBER WILL HELP YOU. |
| |
| THANKS, |
| RICK ROSSANO, SENIOR PROJECT COORD., WPB ENG. SERVICES |
| DEPT., 561-494-1098, FAX: 561-494-1116 [email protected] |